Progress
Gujarat State Electricity Corporation Limited (GSECL), Vadodara, publishes a procurement for a Self Priming Pump conforming to IS 5120 under the Q3 category. The tender notes a flexible quantity clause allowing ±25% variation at contract award and during the contract, with delivery periods tied to the last date of the original delivery order. The ATC confirms material delivery per Schedule-B and final authority on technical terms lies with GSECL. No BOQ items or explicit start/end dates are listed, signaling a streamlined pump supply requirement within Gujarat state procurement.
Self Priming Pump
IS 5120 compliance (Q3)
No BOQ items published
Schedule-B alignment
ATC final authority with GSECL
Delivery period linked to original delivery order with 25% quantity variation
Quantity may vary +/- 25% at contract award and during currency
Delivery schedule based on last date of original order; minimum 30 days for extensions
ATC and Schedule-B govern technical compliance; IS 5120 standard required
Not specified in data; assume standard government terms per tender ATC
Delivery starts from last date of original delivery order; extended delivery time calculated as (increase/original) × original period, minimum 30 days
Not defined in data; ATC may specify LD terms
Experience in supplying pumps or IS 5120-compliant equipment
GST registration and financial stability as per tender terms
Compliance with Schedule-B and OEM authorizations if applicable
Quantity
2
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
3 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
Yes (Arbitration clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 Arbitration should not be routinely included in contracts
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Self Priming Pump Conforming To IS 5120 (Q3)
Advisory Bank
Bank Of Baroda
ePBG Percentage
5%
ePBG Duration (Months)
4
Max Delivery Days
60
Delivery Locations
1
Delivery Cities
Tapi
Delivery Pincodes
394680
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Pallavkumar Maganbhai Solanki | 394680,GSECL UKAI TPS, UKAI DAM, DIST: TAPI | Tapi | Gujarat | 394680 | 2 | 60 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
22-Oct-2026, 9:30 am
Opening Date
23-Oct-2026, 9:30 am
Extended Deadline
12-Oct-2026, 9:30 am
Opening Date
13-Oct-2026, 9:30 am
Discover companies most likely to bid on this tender
GST registration
PAN card
Experience certificates (relevant to self priming pumps or IS 5120-compliant equipment)
Financial statements (as required by tender terms—not disclosed in data)
EMD/Security deposit documentation (amount not disclosed in data)
Technical compliance certificates (IS 5120 conformity, Schedule-B references)
OEM authorization letters (if bidding through an authorized channel)
Any ATC-specified documents published by GSECL
Key insights about GUJARAT tender market
Bidders must submit GST, PAN, and experience certificates for IS 5120-compliant pumps. Provide Schedule-B references and OEM authorization if applicable. Ensure compliance with the ATC final terms and the 25% quantity variation clause. Delivery terms follow last order date with potential extensions per option clause.
Submit GST registration, PAN, company financials, pump-related experience certificates, EMD/security deposit proof, OEM authorizations (if applicable), and Schedule-B compliant technical documents. ATC-specified items must be included; ensure pump model meets IS 5120 Q3 requirements.
Technical scope centers on a Self Priming Pump conforming to IS 5120. While no explicit performance metrics are listed, bidders must align with Schedule-B and the ATC document issued by GSECL. IS 5120 compliance is mandatory; ensure pump design and materials meet IS 5120 standards.
Delivery begins from the last date of the original delivery order; if the quantity is increased under the option clause, the additional time is calculated as (increased quantity/original quantity) × original delivery period, with a minimum of 30 days.
EMD amount is not disclosed in the provided data; follow standard state tender practice for EMD. Payment terms are not specified in the available ATC; bidders should await formal terms in the ATC and Schedule-B documentation.
Eligible bidders should have IS 5120 pump experience or similar, valid GST/PAN, and financial stability documentation. OEM authorizations may be required if bidding through a distributor, and compliance with Schedule-B and ATC terms is mandatory for bid submission.