Bid Publish Date
01-Sep-2026, 6:09 pm
Bid End Date
01-Oct-2026, 12:00 pm
EMD
₹49,000
Value
₹24,57,530
Location
Progress
Organization: Nhpc Limited; Product/Service: Deputation of an OEM Expert for Supervisory services on replacement of MIV disc seal and related works for CPS-1. Location: Chamba, Himachal Pradesh 176207; Estimated Value: ₹2,457,530; EMD: ₹49,000; Contract Period: 21 days (portal shows 1 month, actual 21 days). OEM Reservation: GE Vernova Hydro Power India Private Limited. Bidders must quote total contract price inclusive of all charges and taxes; item-wise rate breakup may be required on demand. No BOQ items are listed. This opportunity targets specialized supervision from the OEM expert to ensure scope compliance and schedule adherence. Unique constraint: OEM-restricted participation and short execution window.
EMD of ₹49,000 required; submission via online portal
Contract reserved for GE Vernova Hydro Power India Pvt Ltd; OEM participation only
Total price inclusive of all charges; itemized breakup to be provided on demand
Delivery window stated as 21 days; actual scope to be confirmed by buyer
Total Contract Price payable per buyer; item-wise rate breakup may be demanded; ensure compliance with EMD and taxes
Actual contract period indicated as 21 days; ensure timely supervision and completion per Scope of Work
Not specified in available terms; penalties, if any, to be defined in the final contract/per ATC
Only GE Vernova Hydro Power India Private Limited can participate
Must upload all mandatory certificates as per ATC
Demonstrated experience in OEM supervision for similar disc-seal replacement works
Quantity
1
Similar Category
Hiring of Third-Party Inspection Agency Support Services
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Tech Clarification Time
3 Days
EMD Required
Yes
MII Compliance
Yes
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Service
Bid To RA
No
Bid To RA Enabled
No
Item Category
Custom Bid for Services - Deputation of OEM Expert for Supervisory services of replacement of MIV disc seal and associated works of all units of CPS-1 as per Scope of work and SCC
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
4
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of service delivery acceptance certificate (SDAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Delivery Locations
1
Delivery Cities
Chamba
Delivery Pincodes
176325
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Rakesh Baboo | 176325,NHPC LIMITED, CHAMERA POWER STATION1, PO-KHAIRI, TEHSIL-DALHOUSIE, DISTT. CHAMBA | Chamba | Himachal Pradesh | 176325 | Project / Lumpsum Based | - | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
01-Oct-2026, 6:30 am
Opening Date
02-Oct-2026, 6:30 am
Extended Deadline
26-Sep-2026, 6:30 am
Opening Date
27-Sep-2026, 6:30 am
Extended Deadline
21-Sep-2026, 6:30 am
Opening Date
22-Sep-2026, 6:30 am
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for OEM supervision in similar projects
Financial statements / solvency certificate
EMD submission proof (₹49,000)
Technical bid documents and compliance certificates
OEM authorization/institutional confirmation for GE Vernova (restricted bidder)
Key insights about HIMACHAL PRADESH tender market
Bidders must be GE Vernova Hydro Power India Pvt Ltd; prepare EMD ₹49,000, GST/PAN, financials, OEM authorization, and experience certificates. Upload all mandatory documents per ATC, and quote the Total Contract Price inclusive of taxes. Be ready to provide itemized rates on demand and complete within 21 days.
Submit GST registration, PAN, experience certificates, financial statements, EMD proof, technical compliance certificates, and OEM authorization proving GE Vernova eligibility. Ensure all documents align with bid conditions and ATC; missing documents may lead to rejection.
The ATC specifies a 21-day contract period, though GeM portal data may show one month. Confirm start date with Nhpc Limited, ensure full completion within 21 days, and maintain schedule discipline to avoid penalties.
Estimated value is ₹2,457,530 with an EMD of ₹49,000. Bidder must provide payment proof for EMD and ensure pricing includes all charges, taxes, and duties as required by the buyer.
Only GE Vernova Hydro Power India Private Limited is eligible to bid, per OEM reservation. Bid submissions must include OEM authorization and compliance with scope of work and SCC.
Scope includes supervision of replacement of MIV disc seal and related works across all CPS-1 units per Scope of Work and SCC. Detailed technical specs are provided in the ATC; vendors should align with OEM standards and deliver within 21 days.
Payment is based on the Total Contract Price inclusive of all charges; an itemized rate breakup may be requested by the buyer. Ensure compliance with EMD terms and timely delivery to facilitate prompt payment per contract terms.
Mandatory certificates must be uploaded as per Bid Document/ATC. OEM-authenticated submissions from GE Vernova are required, with relevant financials and experience demonstrating capability in supervision for disc-seal replacement projects.