Bid Publish Date
15-Oct-2026, 8:21 am
Bid End Date
26-Oct-2026, 9:00 am
Location
Progress
Hindustan Aeronautics Limited (Department of Defence Production) invites bids for a General Purpose Hydraulic Test Rig in India. Although the BOQ shows 0 items, bidders must align with data-sheet submissions, OEM installation/commissioning, and Malicious Code certification. Key bidder obligations include GST/PAN verification, cancelled cheque, and EFT mandate. The procurement emphasizes OEM-certified deployment and rigorous parameter verification against provided data sheets. An optional site visit is allowed at bidder cost to assess installation constraints and site readiness. The quantity may be adjusted by the purchaser up to 50%, influencing total value potential. This tender targets suppliers capable of end-to-end deployment, including training if scope requires.
General Purpose Hydraulic Test Rig
OEM-certified installation and commissioning
Data Sheet alignment with offered specs
Malicious Code Certificate submission
Optional site visit at bidder cost
Quantity variation up to 50%
GST/PAN verification and EFT mandate submission
Data sheet must match technical parameters
OEM-certified installation and optional site visit
Malicious Code Certificate required
Quantity adjustment up to 50% at purchaser discretion
Not specified in available data; standard HAL terms to be awaited
Delivery and installation by OEM-certified personnel; no fixed date provided
Not specified in provided terms; typical HAL contracts may apply post-award
Must supply OEM-certified installation resources
Submit GSTIN, PAN, EFT Mandate, Cancelled Cheque
Provide Data Sheet aligned with offered product
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
Yes
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
Bid Splitting Applied
No
Min. Avg. Annual Turnover
33
Warranty Period
3 years
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
GENERAL PURPOSE HYDRAULIC TEST RIG
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
60
Delivery Locations
1
Delivery Cities
LUCKNOW
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | LUCKNOW | LUCKNOW | - | - | 1 | 60 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST certificate
PAN card
Cancelled cheque
EFT Mandate
Data Sheet of offered product
OEM authorization/certification (OEM-certified resource or OEM-authorized reseller)
Malicious Code Certificate
Key insights about UTTAR PRADESH tender market
Bidders must submit GSTIN, PAN, cancelled cheque, and EFT mandate; upload the product data sheet, OEM authorization, and Malicious Code Certificate. Ensure OEM-certified installation capability and align with site-visit terms. The process requires data-sheet verification against offered parameters and potential 50% quantity adjustment by HAL.
Required documents include PAN, GSTIN, cancelled cheque, EFT Mandate, product data sheet, OEM authorization, and Malicious Code Certificate. Ensure GST applicability and data-sheet compatibility; optional site visit at bidder cost may be conducted to assess installation readiness.
Technical specifics focus on the General Purpose Hydraulic Test Rig; ensure the data sheet exactly matches offered parameters; installation/commissioning must be undertaken by OEM-certified personnel; no fixed numeric specs provided in the available data.
HAL may increase or decrease the order quantity up to 50%, impacting total contract value and delivery planning. Bidders should plan for scalable capacity and verify unit pricing under possible quantity changes during evaluation.
Installation and training, if scoped, must be performed by OEM-certified resources or OEM-authorized resellers. Timelines depend on award terms; bidders should prepare scheduling buffers for on-site commissioning and potential training sessions.
The certificate confirms the hardware/software package lacks embedded malicious code that could damage equipment or compromise data. Failure to provide this certificate may render the bid non-compliant or rejected.
Data sheets must be uploaded with bid documents and must precisely reflect offered specifications. Any mismatch between the data sheet and actual product parameters can lead to bid rejection during technical evaluation.