Progress
RABharat Heavy Electricals Limited invites bids for the stator transport frame (237 series), identified by Material No: TG9712391213, Specification: TG6648, Rev 00, and Drawing No: D11391231 437, Rev 01. Quantity: 1 unit. Location details are not specified in the data. The scope is strictly supply of goods with adherence to the exact drawing, specification, and size. A distinctive feature is the explicit requirement for the item to be delivered per the given specification and quantity, with a formal acceptance path via buyer’s lab testing. The contract includes a 12-month warranty and both pre-dispatch and post-receipt inspection options. Include a material test certificate with the supply. BHEL reserves options related to contract execution and quantity fluctuations up to 25%. This tender emphasizes exact component matching and inspection-based acceptance, with specified drawing references as non-negotiables.
Option Clause: quantity may increase up to 25% during contract at contracted rates
Inspection regime: pre-dispatch and post-receipt inspections by buyer
Warranty: 12-month period; acceptance contingent on lab test results
Documents: PAN, GSTIN, Cancelled cheque, EFT Mandate; MSTC/GEM submission norms
Delivery: not explicitly defined; size/drawing must be exact per TG9712391213
Bank guarantees may be required for milestones; exact payment terms not specified in available data
Delivery period not explicitly stated; option clause allows up to 25% quantity variation at contracted rates
Not specified in provided data; standard GEM terms may apply if delays occur
Capability to supply exact stator transport frame per BHEL TG9712391213 with TG6648 Rev 00 and drawing D11391231 437 Rev 01
Ability to pass Material Test Certificate and buyer lab acceptance
Compliance with GST registration, PAN, and EFT mandate documentation
These are the final prices after the reverse auction event. Prices may be lower than initial bids.
| Rank | Seller | Final Price | Item |
|---|---|---|---|
| L1 | R.K. ENGINEERING WORKS(MSE,MII) Under PMA Winner | ₹7,04,250 | Item Categories : Stator transport frame (237 series) |
| L2 | BROWN'S HI-TECH STRUCTURES PVT LTD (MSE,MII) Under PMA | ₹7,05,043 | Item Categories : Stator transport frame (237 series) |
| L3 | M/S SRI POOJA ENGINEERING WORKS (MSE,MII) Under PMA | ₹7,05,750 | Item Categories : Stator transport frame (237 series) |
| L4 | TRIOMECH ENGG PVT LTD (MSE,MII) Under PMA | ₹7,11,864 | Item Categories : Stator transport frame (237 series) |
| L5 | M/S SRI SAI FABRICATORS & ENGINEERING WORKS (MSE,MII) Under PMA | ₹8,91,648 | Item Categories : Stator transport frame (237 series) |
🎉 L1 Winner
R.K. ENGINEERING WORKS(MSE,MII) Under PMA
Final Price: ₹7,04,250
Please sign in or create an account to view contract details and download result documents.
Start
25-Sep-2026, 12:00 pm
End
26-Sep-2026, 12:00 pm
Duration: 24 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
3 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Warranty Period
1 years
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Stator transport frame (237 series)
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
56
Delivery Locations
1
Delivery Cities
Sangareddy
Delivery Pincodes
502032
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Sisir Kanta Mishra | 502032,BHEL , HPEP , Ramachandrapuram | Sangareddy | Telangana | 502032 | 1 | 56 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
PAN Card copy
GSTIN copy
Cancelled cheque copy
EFT Mandate certificate (bank certified)
Material Test Certificate
Any drawings/specification conformance documents
OEM authorizations if applicable (not specified)
Key insights about TELANGANA tender market
Bidders must submit PAN Card, GSTIN, Cancelled Cheque, and EFT Mandate certified by their bank. Also attach Material Test Certificate and drawings conformance documents. Ensure GST invoice is uploaded on GeM with GST portal payment proof during invoicing.
The purchaser may increase or decrease quantity by up to 25% at contracted rates. Delivery timelines extend proportionally from the last date of the original order, with a minimum extension of 30 days, and may be applied during currency period.
Item must meet TG9712391213, with Specification TG6648 Rev 00 and Drawing D11391231 437 Rev 01. Supplied parts must align precisely with these references, including size and quantity, for acceptance.
Both pre-dispatch inspection at seller premises (if ATC requires) and post-receipt inspection at the consignee site are mandated. The buyer’s lab tests will determine acceptance based on Material Test Certificate results.
The contract specifies a 12-month warranty from the date of supply. Any non-conformity discovered within this period must be addressed under warranty terms, with potential replacement or repair.
Submit a valid EFT Mandate certified by the bank, along with a cancelled cheque and PAN/GST certificates. Ensure all banking details match corporate records to avoid payment delays.
Strict adherence to TG6648 Rev 00 and Drawing D11391231 437 Rev 01 is required. Material Test Certificate must accompany the supply, and lab results will drive acceptance by the buyer.
Acceptance relies on the buyer’s lab test results from the Material Test Certificate. Post-dispatch inspection and pre-dispatch checks (per ATC) influence acceptance, with final decision based on conformance to drawing and specs.