Bharat Heavy Electricals Limited (BHEL) invites bids for SG9792091017_11 KW MOTOR IE3 (250 LPM LUBE SYSTEM), along with associated components: SG9792091025_ DRIVE END BEARING FOR 11KW MOTOR, SG9792091033_ NON DRIVE END BEARING FOR 11KW MOTOR, and SG9792091076_ TERMINAL BLOCK FOR 11KW IE3 MOTOR. The procurement is targeted for delivery to BHEL Hyderabad, RC Puram, Lingampally, Patancheru, Sangareddy 502032. The scope includes equipment components and ancillary items at contract rates with option to adjust quantities up to 25%. Pre-dispatch inspection is managed by BHEL/TPI; post-receipt inspection at the consignee site by BHEL. The awarding entity requires OEM warranty certificates at delivery and a robust after-sales support network across India. This tender emphasizes compliance with installation, commissioning, and serviceability expectations.
11 KW IE3 motor with 250 LPM lubricant system
Drive End Bearing for 11KW motor
Non-Drive End Bearing for 11KW motor
Terminal Block for 11KW IE3 motor
OEM warranty certificates required at delivery
Pre-dispatch/ Post-receipt inspection as per ATC
Delivery to BHEL Hyderabad with installation/commissioning if included
Delivery to BHEL Hyderabad; inspection by BHEL/TPI
Quantities may vary by 25% during/after contract
Warranty as per specifications; OEM certificates at delivery
Not specified in available data; bidders should await ATC for payment schedule and milestones
Delivery period extends from last date of original delivery order; minimum extension 30 days; quantity variation accommodated up to 25%
Not specified in provided data; contractual LD if any would be defined in ATC
Must provide PAN, GST, cancelled cheque, EFT mandate
OEM authorization for motor components
Experience in supplying 11 KW IE3 motors or related components
Quantity
34
Category
SG9792091017_ 11 KW MOTOR IE3 (250 LPM LUBE SYSTEM)
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
SG9792091017_ 11 KW MOTOR IE3 (250 LPM LUBE SYSTEM) , SG9792091025_ DRIVE END BEARING FOR 11KW MOTOR , SG9792091033_ NON DRIVE END BEARING FOR 11KW MOTOR , SG9792091076_ TERMINAL BLOCK FOR 11KW IE3 MOTOR
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
120
Delivery Locations
1
Delivery Cities
Sangareddy
Delivery Pincodes
502032
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mahendra Singh | 502032,SG Stores , Near 03 Annexe , BHEL HPEP , Ramachandrapuram | Sangareddy | Telangana | 502032 | 16 | 120 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
24-Oct-2026, 9:30 am
Opening Date
25-Oct-2026, 9:30 am
Discover companies most likely to bid on this tender
PAN card copy
GSTIN copy
Cancelled cheque copy
EFT mandate copy certified by bank
OEM authorization (for supplied components)
Technical compliance certificates
Experience certificates (relevant to motor components)
Financial statements
Any certificates requested in ATC
Key insights about TELANGANA tender market
Bidders should submit PAN, GST, cancelled cheque, EFT mandate, OEM authorizations, and technical compliance certificates. The contract allows up to 25% quantity variation and includes pre-dispatch and post-receipt inspections by nominated agencies. Ensure OEM warranty certificates are provided at delivery and delivery occurs at BHEL Hyderabad.
Required documents include PAN, GST, cancelled cheque, EFT mandate certified by bank, OEM authorization for motor components, technical compliance certificates, experience certificates, and financial statements. Ensure uploads match ATC requirements to avoid rejection of bid.
Pre-dispatch inspection by BHEL/TPI is possible if ATC selects it; post-receipt inspection is conducted at consignee site by BHEL. Ensure you comply with inspection schedules and provide necessary QA documentation and OEM warranties prior to delivery.
Delivery is to the BHEL Hyderabad address: RC Puram, Lingampally, Patancheru, Sangareddy 502032. Installation and commissioning, if in scope, will also occur there per contract terms.
Warranty must align with specifications from final acceptance or post-installation, with OEM warranty certificates submitted at delivery. The seller must guarantee rectification during the warranty period and provide India-wide service centers for after-sales support.
Quantity can increase/decrease by up to 25% with corresponding adjustment to delivery time. The formula is (Additional quantity / Original quantity) × Original delivery period, with a minimum extension of 30 days.
While the exact standards are not listed, components must be compatible with 11 KW IE3 motors and include OEM warranty and compliance certificates. Submit relevant certifications and ensure compatibility with IE3 efficiency class and motor accessories.
Eligibility includes: valid PAN and GST numbers, GST registration proof, bank details with EFT mandate, OEM authorizations for components, and demonstrated experience in supplying motor components and related accessories.