Aurangabad Government Tender for Insulation Tape & GI Preforated Cable - 30 Day Payment 1 Year Warranty 2026

Bid Publish Date

04-Sep-2026, 1:51 pm

Bid End Date

14-Sep-2026, 2:00 pm

Progress

Issue04-Sep-2026, 1:51 pm
AwardPending

Tender Overview

The tender, issued for the Aurangabad, Maharashtra region, seeks procurement of insulation tape and GI preforated cable under a single government inquiry hosted on the GEM platform. The contract allows a quantity fluctuation of up to 25%, with extended delivery time provisions calculated as (increased quantity ÷ original quantity) × original delivery period, minimum 30 days. A 30-day payment term is specified, and the OEM warranty must be supplied at delivery alongside service centre details for post-sale support. The item scope includes material conformity with the purchaser’s enquiry and ensures replacement for deviations. The bidder must acknowledge the 1-year warranty from final acceptance or after installation. The procurement includes installation, commissioning, training, and maintenance obligations. The organization requires a credible after-sales network in India to service the consignees.

Technical Specifications & Requirements

  • Material requirements: Insulation tape and GI preforated cable as per enquiry; only ANY STANDARD make acceptable if compliant with the purchase terms.
  • Deviation handling: any deviation must be clearly disclosed in the technical bid; non-conforming items will be rejected and deducted in final payment.
  • Delivery terms: delivery period to commence after the last order date; option to increase quantity up to 25% during contract with a minimum 30 days extended period.
  • Payment terms: 30 days; after-inspection deviations lead to material return and replacement.
  • Warranty: 1 year from final acceptance or after installation/testing; OEM warranty certificates must be provided at delivery; service centres must be listed.
  • Compliance: seal and sign on tender documents; non-compliance leads to disqualification.

Terms & Eligibility

  • Quantity variation rights: purchaser may adjust quantity by up to 25% during and after finalization for 6 months.
  • Payment: terms fixed at 30 days; no advance payment indicated.
  • Quality control: any deviation found during inspection triggers material return or deduction; OEM authorization and service coverage in India required.
  • Documentation: bidder must provide signed tender document, seal, and required technical bid disclosures; non-compliance results in disqualification.

Key Specifications

    • Product/service names: insulation tape; GI preforated cable
    • Quantity/scale: quantity variation up to 25% during contract
    • Estimated value: not disclosed
    • Standards/certifications: any STANDARD make acceptable; IS, BIS not specified
    • Delivery: from last date of original delivery order; extended delivery period minimum 30 days
    • Warranty: 1 year from final acceptance or post-installation testing
    • After-sales: installation, commissioning, training, troubleshooting, maintenance in India
    • Documentation: OEM warranty certificates to be submitted at delivery

Terms & Conditions

  • Quantity adjustment up to 25% during and after finalization for 6 months

  • 30-day payment terms after delivery with acceptance

  • OEM warranty certificates required at delivery with service center details

Important Clauses

Payment Terms

Payment to be released within 30 days of delivery/acceptance; no advance mentioned.

Delivery Schedule

Delivery period begins from the last date of original delivery order; option to extend for increased quantity with minimum 30 days added.

Penalties/Liquidated Damages

Deviation detected during inspection leads to return or deduction; non-compliance can disqualify bidder.

Bidder Eligibility

  • Experience in supplying insulation materials or cables to government entities

  • Financial stability evidenced by recent financial statements

  • Authorized to sell OEM insulation tape or GI preforated cables in India

Tender Data

Bid Details

Quantity

355

Bid Type

Service

Preference & Exemptions

EMD Required

No

MII Purchase Preference

No

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Warranty Period

1 years

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Delivery Details

Max Delivery Days

15

Delivery Locations

1

Delivery Cities

Aurangabad

Delivery Pincodes

431006

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
MOHANPRABHU M431006,H2,MIDC,ChikalthanaAurangabadMaharashtra4310069015-

Authority Records

MINISTRY OF HEAVY INDUSTRIESHEAVY INDUSTRY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 4

GeM-Bidding-9847577.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 18 Items Sign in for GEM prices

#1

AL. ARM. CABLE 3 CORE 2.5 SQ. MM

AL. ARM. CABLE 3 CORE 2.5 SQ. MM

90 mtr Delivery: 15 days
#2

3 POLE 16 AMP MCB WITH ENCLOSURE

3 POLE 16 AMP MCB WITH ENCLOSURE

3 nos Delivery: 15 days
#3

3 POLE 10 AMP MCB WITH ENCLOSURE

3 POLE 10 AMP MCB WITH ENCLOSURE

14 nos Delivery: 15 days
#4

GI PERFORATED CABLE TRAY SIZE 200 MM X 50 MM HT X 1.6 MM THICK

GI PERFORATED CABLE TRAY SIZE 200 MM X 50 MM HT X 1.6 MM THICK

30 mtr Delivery: 15 days
#5

GI PERFORATED CABLE TRAY SIZE 300 MM X 50 MM HT X 1.6 MM THICK

GI PERFORATED CABLE TRAY SIZE 300 MM X 50 MM HT X 1.6 MM THICK

24 mtr Delivery: 15 days
#6

GI STRIP WITH NUT BOLTS TO CONNECT TWO CABLE TRAYS.

GI STRIP WITH NUT BOLTS TO CONNECT TWO CABLE TRAYS.

40 mtr Delivery: 15 days
#7

GI 2 B CLASS PIPE

GI 2 B CLASS PIPE

18 mtr Delivery: 15 days
#8

C.I FRAME WITH COVER 300 X 300 MM FOR EARTHING PIT

C.I FRAME WITH COVER 300 X 300 MM FOR EARTHING PIT

3 nos Delivery: 15 days
#9

G.I EARTHING STRIP SIZE 25 X 3 MM

G.I EARTHING STRIP SIZE 25 X 3 MM

20 mtr Delivery: 15 days
#10

EARTHING POWDER

EARTHING POWDER

60 kgs Delivery: 15 days
#11

G.I EARTHING WIRE 14 SWG

G.I EARTHING WIRE 14 SWG

20 kgs Delivery: 15 days
#12

NYLON CABLE TIE 300 MM

NYLON CABLE TIE 300 MM

5 pkt Delivery: 15 days
#13

INSULATION TAPE RED

INSULATION TAPE RED

5 rolls Delivery: 15 days
#14

INSULATION TAPE YELLOW

INSULATION TAPE YELLOW

5 rolls Delivery: 15 days
#15

INSULATION TAPE BLUE

INSULATION TAPE BLUE

5 rolls Delivery: 15 days
#16

INSULATION TAPE BLACK

INSULATION TAPE BLACK

5 rolls Delivery: 15 days
#17

INSULATION TAPE GREEN

INSULATION TAPE GREEN

5 rolls Delivery: 15 days
#18

RED OXIDE 2 LIT CAN

RED OXIDE 2 LIT CAN

3 nos Delivery: 15 days

Categories 20

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

GST registration certificate

2

PAN card

3

Experience certificates showing prior supply of similar insulation materials or cables

4

Financial statements (audited, if available)

5

EMD/Security deposit details

6

Technical bid documents and compliance statements

7

OEM authorizations or authorized distributor certificates

8

Details of Service Centres and after-sales support network in India

Frequently Asked Questions

Key insights about MAHARASHTRA tender market

How to bid for insulation tape tender in Aurangabad?

Bidders should submit GST, PAN, experience certificates, and financials along with technical bid, OEM authorization, and OEM warranty documents. The contract allows up to 25% quantity variation and requires a 30-day payment term; ensure 1-year OEM warranty is included and installation support details are provided.

What documents are required for GI preforated cable bid in Maharashtra?

Required documents include GST certificate, PAN, company financial statements, experience certificates for similar cable supply, OEM authorization, technical bid with deviation disclosures, and OEM warranty certificates to be submitted at delivery; service centers in India must be listed.

What are the delivery terms for the Aurangabad tender?

Delivery begins after the last date of the original delivery order; quantity may be increased up to 25% during contract with extended delivery time, calculated as (increased quantity ÷ original quantity) × original period, minimum 30 days.

What is the warranty requirement for supplied insulation products?

A 1-year warranty is required from final acceptance or post-installation testing; OEM warranty certificates must accompany delivery, and service centers must be established in India to support after-sales service.

What conditions trigger material rejection in this tender?

Any deviation from enquiry specifications must be disclosed in the technical bid; undisclosed deviations lead to rejection and potential deduction from final payment if non-conforming.

Where can I find the payment terms and penalties for the bid?

The payment terms specify 30-day payment after delivery/acceptance; penalties apply for deviations found during inspection, including possible material return or deduction; ensure strict compliance in bid submissions.

What qualifies as eligible experience for this government tender?

Eligibility requires prior supply experience of insulation materials or cables to government entities, supported by relevant experience certificates and demonstrated financial capacity through audited statements or recent financials.

How to ensure compliance with the 25% quantity variation clause?

Bidder should acknowledge the purchaser's right to increase/decrease quantity by up to 25% during contract and extended period; plan inventory and production capacity to handle 25% fluctuations without penalties.