TenderDekho Logo
GEM

GEM Procurement Solan Himachal Pradesh ISO 9001 Goods Tender 2025

Bid Publish Date

04-Dec-2025, 5:55 pm

Bid End Date

15-Dec-2025, 6:00 pm

Progress

RA
Issue04-Dec-2025, 5:55 pm
Reverse AuctionCompleted
AwardCompleted
Explore all 3 tabs to view complete tender details

Quantity

925

Key Highlights

  • ISO 9001 certification mandatory for bidder or OEM
  • BIS license and type test certificates required
  • Material Test Certificate to be supplied with goods
  • Up to 25% quantity variation during contract and at time of order
  • GST advised; refund based on actuals or lowest applicable rate
  • EFT mandate and cancelled cheque must accompany bid
  • Supply, installation, testing and commissioning scope included
  • Turnover as per last three years specified in bid document

Categories 44

Tender Overview

The procurement is issued through GEM for a project in Solan, Himachal Pradesh (171102), seeking Supply Installation Testing and Commissioning of Goods across a bundle of 15 items. While exact quantities and item specifics are not disclosed, bidders must ensure ISO 9001 certification for offerors or OEMs, and provide BIS licence, type test certificates, and related approvals. The contract allows a flexible quantity variation up to 25% of the bid quantity at the time of order and during the contract currency, at contracted rates, with a minimum delivery extension of 30 days. The scope emphasizes a comprehensive supply and integration deliverable, not merely a purchase. This tender emphasizes compliance, certification, and robust post-award performance, with a requirement for material testing to be conducted by the buyer’s lab. The location and basic legal terms indicate a government-backed procurement environment with strict certificate documentation and turnover compliance.

Technical Specifications & Requirements

  • Standards & Certifications: ISO 9001 (bidder or OEM must hold), BIS license, Type test certificates, and other specified product certificates as per bid document.
  • Quality/Testing: Material Test Certificate to accompany supply; buyer lab to perform acceptance testing.
  • Documents Required: PAN, GSTIN, cancelled cheque, EFT mandate; ensure upload of all cited certificates along with bid.
  • Scope of Supply: Includes supply, installation, testing, and commissioning of goods; all costs included in bid price.
  • GST & Turnover: GST advisement by bidder; turnover as per last three years as laid out in the bid document.
  • Quantity Flexibility: Up to 25% increase in order quantity; delivery timeline linked to last delivery order date with minimum 30 days extension.
  • Delivery Location: Solan district; installation and commissioning aligned with government procurement timelines.
  • Documentation & Compliance: Ensure OEM authorizations and any product-specific certifications.

Terms, Conditions & Eligibility

  • EMD/Financial Standing: No explicit EMD amount stated here; ensure financial viability and no liquidation or bankruptcy filings; provide undertaking as required.
  • Delivery & Payment: Original delivery period plus extension rules; payment terms not specified here and will be clarified in contract.
  • GST & Tax: Bidder bears GST applicability; reimbursement aligned to actuals or allowed rate.
  • Documentation: Submit PAN, GSTIN, cancelled cheque, EFT mandate; all required certificates as per bid document.
  • Turnover: Minimum average annual turnover over the last three years must meet the value described in the bid document; provide audited statements.
  • Quality Assurance: ISO 9001 certification is mandatory for bidder or OEM; material tests influence acceptance; non-submission leads to rejection.
  • Option Clause: Variation in quantity up to 25% at contracted rates; schedule adjusted per formula with minimum 30 days.

Key Specifications

  • ISO 9001 certified bidder or OEM

  • Material Test Certificate to accompany supply

  • BIS licence and type test certificates

  • Supply, installation, testing, commissioning included

  • 25% quantity variation rights

Terms & Conditions

  • 25% quantity variation allowed during contract with minimum 30 days extension

  • Mandatory ISO 9001 certification for bidder or OEM

  • Material Test Certificate to be submitted with supply

Important Clauses

Payment Terms

GST payable/reimbursable as actuals or as per applicable rate; exact payment terms to be defined in contract

Delivery Schedule

Delivery period commences from last date of original delivery order; extension rules apply with minimum 30 days; option quantity may extend during currency

Penalties/Liquidated Damages

Not specified here; penalties to be defined in the contract per delivery non-compliance

Bidder Eligibility

  • Not under liquidation or bankruptcy; provide undertaking

  • Turnover as specified in bid document (last three years)

  • ISO 9001 certification for bidder or OEM

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Authority Records

MINISTRY OF DEFENCEMILITARY AFFAIRS DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 4

GeM-Bidding-8650474.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 15 Items Sign in for GEM prices

#1

Dismantling and taking down of concrete of any description and in any position complete

Dismantling and taking down of concrete of any description and in any position complete

3 cum Delivery: 120 days
#2

M and L for PCC 1 column 4 column 8 type D2 40mm graded stone agg

M and L for PCC 1 column 4 column 8 type D2 40mm graded stone agg

3 cum Delivery: 120 days
#3

M and L for PCC 1 column 2 column 4 type B1 using 20mm graded stone aggregate in coping and the like including weathering slightly rounded angles

M and L for PCC 1 column 2 column 4 type B1 using 20mm graded stone aggregate in coping and the like including weathering slightly rounded angles

1 cum Delivery: 120 days
#4

Disconnecting of HT LT cables earth strips of declared BER transformers

Disconnecting of HT LT cables earth strips of declared BER transformers

3 each job Delivery: 120 days
#5

S and F of outdoor Non sealed type Mineral oil Distribution Transformer Step down Copper wound having Primary side voltage at 11 KV 3Phase

S and F of outdoor Non sealed type Mineral oil Distribution Transformer Step down Copper wound having Primary side voltage at 11 KV 3Phase

1 each Delivery: 120 days
#6

433 Volts at 50 Hz frequency of capacity 250 KVA

433 Volts at 50 Hz frequency of capacity 250 KVA

1 each Delivery: 120 days
#7

433 Volts at 50 Hz frequency of capacity 75 KVA

433 Volts at 50 Hz frequency of capacity 75 KVA

1 each Delivery: 120 days
#8

M and L for earthing complete with GI earth plate as electrode of size 600x600x6mm thick

M and L for earthing complete with GI earth plate as electrode of size 600x600x6mm thick

6 each set Delivery: 120 days
#9

M and L of chemical earthing complete with 50 mm dia copper pipe filled with chemical sulphate

M and L of chemical earthing complete with 50 mm dia copper pipe filled with chemical sulphate

6 each set Delivery: 120 days
#10

Material and labour for GI earth strip of size 32x6mm thick

Material and labour for GI earth strip of size 32x6mm thick

100 rm Delivery: 120 days
#11

Material and labour for Copper earth strip of size 20x3mm thick

Material and labour for Copper earth strip of size 20x3mm thick

100 rm Delivery: 120 days
#12

Dismantling taking out carefully old UG cable from trenches after disconnecting from OH conductors

Dismantling taking out carefully old UG cable from trenches after disconnecting from OH conductors

180 rm Delivery: 120 days
#16

Taking down of existing unsv HDPE pipe of size 90mm outer dia from existing locations

Taking down of existing unsv HDPE pipe of size 90mm outer dia from existing locations

170 rm Delivery: 120 days
#17

M and L for replacement double walled corrugated HDPE duct pipe of 90mm outer dia

M and L for replacement double walled corrugated HDPE duct pipe of 90mm outer dia

110 rm Delivery: 120 days
#18

M and L for replacement double walled corrugated HDPE duct pipe of 50mm outer dia complete

M and L for replacement double walled corrugated HDPE duct pipe of 50mm outer dia complete

60 rm Delivery: 120 days

Required Documents

1

PAN Card copy

2

GSTIN copy

3

Cancelled cheque copy

4

EFT mandate certified by bank

5

ISO 9001 certificate (bidder or OEM)

6

BIS licence and type test certificates

7

Material Test Certificate

8

Audited financial statements for last three years

9

Experience certificates demonstrating capability for supply/installation/commissioning

10

OEM authorizations (if applicable)

11

Any other certificates as per Product Specification in bid document

Reverse Auction Schedule

Completed

Start

19-Dec-2025, 7:00 pm

End

20-Dec-2025, 7:00 pm

Duration: 24 hours

Reverse Auction Document

✅ RA concluded. Check financial results for final rankings.

Technical Results

S.No Seller Item Date Status
1
INTIME COMMOTRADE PRIVATE LIMITED   Under PMA
Make : GRANDLAY CABLES Model : 3.5C X 400 SQMM GRANDLAY CABLE14-12-2025 21:24:42
2
K A TRADERS   Under PMA
Make : KEI Model : A2XFY15-12-2025 10:10:46
3
MIDSCOPE SUPPLIERS   Under PMA
Make : GRANDLAY CABLES Model : 3.5C X 400 SQMM GRANDLAY CABLE15-12-2025 10:20:14

Reverse Auction Results Final Prices

These are the final prices after the reverse auction event. Prices may be lower than initial bids.

Rank Seller Final Price Item
L1MIDSCOPE SUPPLIERS(MII)   Under PMA Winner ₹39,18,450Item Categories : XLPE Cable for Working Voltages up to and Including 1.1 KV as per IS 7098 (Part 1),XLPE Cable for W
L2INTIME COMMOTRADE PRIVATE LIMITED (MII)   Under PMA₹39,28,364Item Categories : XLPE Cable for Working Voltages up to and Including 1.1 KV as per IS 7098 (Part 1),XLPE Cable for W
L3K A TRADERS (MII)   Under PMA₹40,25,580Item Categories : XLPE Cable for Working Voltages up to and Including 1.1 KV as per IS 7098 (Part 1),XLPE Cable for W

🎉 L1 Winner

MIDSCOPE SUPPLIERS(MII)   Under PMA

Final Price: ₹39,18,450

Frequently Asked Questions

Key insights about HIMACHAL PRADESH tender market

What documents are required for the Solan ISO 9001 tender?

Bidders must submit PAN, GSTIN, cancelled cheque, EFT mandate, ISO 9001 certificate (bidder or OEM), BIS license with type test certificates, Material Test Certificate, and audited three-year turnover statements. Upload all cited certificates with the bid to avoid rejection.

How to handle 25% quantity variation in this tender in Solan?

The contract allows up to a 25% increase in bid quantity at contracted rates, with additional time calculated as (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days, and delivery extension possible during currency as per option clause.

What standards and certifications are mandatory for supply in HP tender?

Mandatory ISO 9001 certification for bidder or OEM, BIS licence with type test certificates, and Material Test Certificate. Acceptance hinges on buyer’s lab results, so ensure compliance and provide all certificates per product specification.

When does the delivery period start and how are extensions handled?

Delivery starts from the last date of the original delivery order. If the option clause is used, time extensions depend on the increased quantity and original period, with a minimum of 30 days, and may extend to the original period.

What is required for financial due diligence in this bid?

Provide minimum average turnover for the last three years as per bid document, supported by certified audited balance sheets. Confirm no liquidation or bankruptcy and submit an undertaking if applicable.

What testing and quality checks accompany the delivery?

A Material Test Certificate must accompany the supply; the buyer’s lab will perform acceptance tests, and results will determine item acceptance. Ensure all product-specific certificates are uploaded along with the bid.

What scope of work is included in the bid for Solan procurement?

Scope includes supply, installation, testing, and commissioning of goods. Ensure the bid covers all costs, complies with required standards, and includes post-installation support as per contract terms.

How to ensure GST compliance for this Himachal tender?

Bidder pays applicable GST; reimbursement is based on actuals or the lower eligible rate. Verify GST applicability during bid preparation and include GST calculations in the quotation.