Bid Publish Date
07-Sep-2026, 7:54 pm
Bid End Date
17-Sep-2026, 8:00 pm
Location
Progress
Organization: Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), Lucknow. Product category: Bare pump assembly, Complete Bowl Assembly of LP Pump (14M/4 stage), Complete Column & Shaft Assembly for LP Pump, Type-VT Pump (14M/3&4 stage, Drawing No. H-3455-C.S.D), Bearing retainer (Spider) for LP Pump. Location: Sonbhadra, Uttar Pradesh, 231205. Scope: Provision of LP pump components and associated assemblies for power generation equipment. Quantity/Value: Not disclosed in data; BOQ shows zero items. Key differentiator: ATC terms permit quantity variations up to 25% during contract and extended periods with contracted rates. Context: Governing energy department procurement requiring precise pump assemblies for VT/LP configurations.
Product: Bare pump assembly, LP Bowl assembly, LP Column & Shaft, VT Pump 14M/3&4 stage
Drawing reference: H-3455-C.S.D for VT PUMP configurations
Delivery flexibility: ±25% quantity under option clause; 30 days minimum additional delivery time
Engineering capability: High-precision machining for pump assemblies; alignment with railway/thermal plant standards if applicable
Documentation: ATC-guided terms and conditions; supplier must submit OEM authorizations
Option clause allows 25% quantity variation and potential price stability at contracted rates
Delivery timelines adjust with extended periods; minimum 30 days for added quantity
ATC document governs site-specific terms and submission requirements
Payment terms to be defined in ATC; verify with procurement and contract officer
Delivery starts from last date of original PO; option quantities must adhere to calculated timeline with minimum 30 days
LDs and remedies to be detailed in ATC; confirm failure-to-deliver penalties
Experience in supplying LP/VT pump assemblies or equivalent high-precision pump components
Demonstrated capability to handle 14M/3&4 stage VT pumps and associated bearing retainers
Valid GST registration and financial stability sufficient for government procurements
Quantity
3
Category
Bare pump assembly/Complete Bowl Assembly of LP PUMP (14M/4 stage)
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Bare pump assembly/Complete Bowl Assembly of LP PUMP (14M/4 stage) , Complete Column & Shaft Assembly for LP Pump, Type-VT PUMP (14M/3&4 stage, Drawing No. -H- 3455-C. S. D , Bearing retainer (Spider) for# LP Pump, Type- VT PUMP (14M/3&4 stage, Drawing No. -H-3455-C. S. D)
Max Delivery Days
120
Delivery Locations
1
Delivery Cities
Sonbhadra
Delivery Pincodes
231219
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Shatrughan Singh | 231219,Obra Thermal Power Plant | Sonbhadra | Uttar Pradesh | 231219 | 1 | 120 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
TECHNICAL
TECHNICAL
TECHNICAL
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
GST registration certificate
PAN card
Experience certificates for similar LP/VT pump component supply
Financial statements for last 2-3 years
EMD submission proof (as applicable in ATC)
Technical bid documents showing compliance with VT/LP pump drawings
OEM authorizations or authorized distributor letters
Key insights about UTTAR PRADESH tender market
To bid, review the ATC uploaded by the buyer, prepare OEM authorizations, and gather GST, PAN, financials, and experience certificates. Ensure compliance with VT pump drawings H-3455-C.S.D and submit technical bid documents with supplier qualifications and EMD per ATC guidance.
Required documents include GST registration, PAN, company financials, at least two prior similar supply certificates, OEM authorization, and technical compliance certificates showing VT 14M/3&4 stage capabilities, along with any ATC-specific attachments.
The contract may increase/decrease quantity up to 25% during placement and currency. Delivery time for additional quantity is calculated as (additional/original) × original period, with a minimum of 30 days.
Refer to Drawing No. H-3455-C.S.D for VT PUMP (14M/3&4 stage) configurations; ensure all components align with these specifications and meet precision tolerances required by UP energy procurement.
Payment terms are specified in the ATC and contract; bidders must confirm whether advance, milestone, or post-delivery payment applies and align with GST and tax invoicing requirements.
The ATC contains site-specific terms, delivery conditions, and submission requirements; bidders must view and comply with all clauses therein to qualify for the formal bid evaluation.
Bidders should demonstrate prior supply of LP/VT pump components or equivalent high-precision pump assemblies, with supporting certificates and references, plus financial stability and GST registration for government tenders.
Scope includes bare pump assemblies, complete bowl assemblies, LP column and shaft assemblies, VT pump (14M/3&4 stage), and bearing retainer (spider) compatible with H-3455-C.S.D drawings and related installation requirements.