Bid Publish Date
17-Aug-2026, 12:25 pm
Bid End Date
28-Aug-2026, 1:00 pm
Location
Progress
The Indian Army, Department Of Military Affairs, invites bids for complete overhauling of FIP units across ALS and TATA platforms, including repair and replacement of kit supply pumps TD Piston and labour charges, MPV rotary pump overhaul with kit replacement, distributor head, gasket sets for STLN, in PoONCH, Jammu & Kashmir (PIN 185101). The procurement focuses on supply of goods with a scope limited to parts and services as described, with five BOQ items awaiting supplier pricing. The option clause allows up to 25% quantity variation during contract execution, at contracted rates, enabling flexible fulfillment of demand. Pre-dispatch inspection is mandatory, conducted at vendor premises or designated lab, with inspection fees borne by the buyer. Delivery timelines commence from the last date of the original delivery order; extension formula applies, minimum 30 days.
Option clause allows ±25% quantity adjustment at contracted rates
Pre-dispatch inspection mandatory with buyer/agency involvement
Scope limited to supply of overhaul kit components and associated gaskets
Payment terms are not explicitly stated; bidders should request clarity on milestone payments and any advance against supply of kits
Delivery period starts from the last date of the original delivery order; options may extend delivery time per formula with a minimum of 30 days
LD/penalties not specified; proposals should include risk-adjusted delivery penalties and performance bonds
Experience in supplying military overhaul kits or equivalent heavy-vehicle pump components
Demonstrated ability to supply pump kits, pistons, and gaskets compatible with ALS, TATA, and MPV systems
Financial capacity to support procurement and delivery under military contract
| S.No | Seller | Item | Date | Status |
|---|---|---|---|---|
| 1 | M/O ILLHUM ENTERPRISES Under PMA | - | 28-08-2026 12:55:23 | |
| 2 | MARATHON STORES Under PMA | - | 28-08-2026 12:56:54 | |
| 3 | MOMIN ENTERPRISES Under PMA | - | 18-08-2026 15:44:36 | |
| 4 | Ouraf Enterprises Under PMA | - | 20-08-2026 19:13:14 | |
| 5 | THE B.K ENTERPRISES Under PMA | - | 28-08-2026 12:34:59 |
| Rank | Seller | Price | Item |
|---|---|---|---|
| L1 | THE B.K ENTERPRISES(MSE)( MSE Social Category:General ) Under PMA | Item Categories : Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And la | |
| L2 | Ouraf Enterprises (MSE)( MSE Social Category:General ) Under PMA | Item Categories : Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And la | |
| L3 | MOMIN ENTERPRISES (MSE)( MSE Social Category:OBC ) Under PMA | Item Categories : Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And la | |
| L4 | M/O ILLHUM ENTERPRISES (MSE)( MSE Social Category:General ) Under PMA | Item Categories : Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And la | |
| L5 | MARATHON STORES (MSE)( MSE Social Category:General ) Under PMA | Item Categories : Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And la |
Quantity
5
Category
Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Past Performance
40 %
Warranty Period
1 years
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge , Complete Overhauling of FIP of TATA incl repairand replacem,ent of kit supplay pump TD Piston And labour charge , Complete Overhauling of Rotary pump of MPV incll repairand replacem,ent of kit supplay pump TD Piston And labour charge , Distributor head , Gasket set os STLN
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Poonch
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Poonch | Poonch | - | - | 1 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge
Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge
Complete Overhauling of FIP of TATA incl repairand replacem,ent of kit supplay pump TD Piston And labour charge
Complete Overhauling of FIP of TATA incl repairand replacem,ent of kit supplay pump TD Piston And labour charge
Complete Overhauling of Rotary pump of MPV incll repairand replacem,ent of kit supplay pump TD Piston And labour charge
Complete Overhauling of Rotary pump of MPV incll repairand replacem,ent of kit supplay pump TD Piston And labour charge
Distributor head
Distributor head
Gasket set os STLN
Gasket set os STLN
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge | Complete Overhauling of FIP of ALS incl repairand replacem,ent of kit supplay pump TD Piston And labour charge | 1 | job | [email protected] | 15 | |
| 2 | Complete Overhauling of FIP of TATA incl repairand replacem,ent of kit supplay pump TD Piston And labour charge | Complete Overhauling of FIP of TATA incl repairand replacem,ent of kit supplay pump TD Piston And labour charge | 1 | job | [email protected] | 15 | |
| 3 | Complete Overhauling of Rotary pump of MPV incll repairand replacem,ent of kit supplay pump TD Piston And labour charge | Complete Overhauling of Rotary pump of MPV incll repairand replacem,ent of kit supplay pump TD Piston And labour charge | 1 | job | [email protected] | 15 | |
| 4 | Distributor head | Distributor head | 1 | job | [email protected] | 15 | |
| 5 | Gasket set os STLN | Gasket set os STLN | 1 | job | [email protected] | 15 |
GST certificate
Permanent Account Number (PAN) card
Experience certificates for similar overhaul kit supply
Financial statements (demonstrating financial standing)
EMD/Security deposit documentation (as applicable by organization terms)
Technical bid documents and specifications compliance
OEM authorization/authorizations for supplied pump kits and gaskets
Any relevant quality/certification documents (as applicable)
Key insights about JAMMU AND KASHMIR tender market
Bidders should prepare standard bidder documents (GST, PAN, financials), verify OEM authorizations, and submit technical compliance for FIP overhaul components. Ensure pre-dispatch inspection readiness and confirm capability to supply ALS, TATA, and MPV pump kits with TD Piston and gaskets. Include ensure delivery within contract period and option clause readiness.
Required submissions include GST certificate, PAN, experience certificates for similar kit supplies, financial statements, EMD/Security details, technical bid documents, and OEM authorizations. Ensure documents reflect capability to supply ALS, TATA, MPV components and gasket sets for STLN.
Scope covers supply of overhaul kits and related components: TD Piston pump assemblies, kit replacements, labour on overhaul, distributor head, gasket sets for STLN, and MPV rotary pump parts. Service is limited to component supply; no full-service overhaul contract described.
Pre-dispatch inspection is mandatory, conducted at seller premises or designated lab. Buyer bears external testing charges; in-house testing is provided by seller at no charge. Seller must notify buyer with readiness; inspection window is seven days from notice to avoid delays.
The purchaser may increase or decrease ordered quantity up to 25% at contracted rates. If exercised during extended delivery, the extra time is calculated as (Additional quantity / Original quantity) × Original delivery period, with a minimum of 30 days.
No explicit standards are listed in the tender data. Bidders should reference applicable IS/ISO standards and ensure components are compatible with ALS, TATA, and MPV systems, while aligning with military procurement expectations.
Delivery begins from the last date of the original delivery order. If the option clause is exercised, additional time is calculated by the formula, with a minimum extension of 30 days to accommodate increased quantity.
Specific payment terms are not stated in the data. bidders should seek explicit terms during bid clarification, including any milestone payments, advance, or performance-based payments aligned with delivery milestones.