Progress
Organization: Indian Army (Department Of Military Affairs). Product category: MS Sheet procurement. Estimated value / EMD: not disclosed. Location: project location not specified; sample delivery to unit location. Scope: basic MS sheet supply with option to adjust quantity up to 25% during contract, at contracted rates. Key differentiator: mandatory OEM and GST certifications; sample submission at unit site. Tender emphasizes adherence to option clause timing and delivery calculations starting from the last date of original delivery order. Unique aspects: ATC clauses mandate supplier compliance with GST and OEM certifications; bidder must accommodate sample verification at purchaser site.
Option quantity adjustment up to 25% during and within contract
Delivery period based on original delivery order date; sample required at unit site
GST and OEM certifications are mandatory for bidder eligibility
Not disclosed in data; bidders must comply with standard government procurement payment terms and ATC guidance
Delivery starts from the last date of original delivery order; additional time calculated as (increase/original) × original period, minimum 30 days
Not specified in data; advisable to review ATC for LD provisions and performance bonds
Must provide GST registration and valid OEM certification
Capacity to manage up to 25% quantity variation within contract term
Compliance with standard government procurement terms and ATC clauses
Quantity
2
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Past Performance
20 %
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
MS Sheet
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
Kohima
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Kohima | Kohima | - | - | 2 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
GST certificate
OEM certificate
Sample submission documentation (delivery at unit location)
Bid commitment demonstrating ability to handle 25% quantity variation
Any standard bid submission documents as required by ATC
Key insights about NAGALAND tender market
Bidders must submit GST and OEM certificates, along with sample delivery documentation to the unit location. The bid should reflect the 25% quantity variation option and comply with ATC requirements, including delivery timelines and sample verification. Prepare standard bid documents and security, if applicable.
Required documents include GST certificate, OEM certificate, sample submission documentation, and proof of ability to handle 25% quantity variation. Also include any standard financial statements and bid seals as per ATC guidelines for government tenders.
Delivery begins after the last date of the original delivery order. If quantity increases, the extended time equals (increase/original) × original period, with a minimum of 30 days. The purchaser may extend this period up to the original delivery period.
Mandatory certifications include GST certificate and OEM certificate. Ensure supplier has these certificates before submission and that they cover the MS Sheet category of procurement.
The purchaser can adjust quantity by up to 25% of bid quantity during placement and during currency. Ensure pricing remains contracted rates and include 25% contingency in planning.
The seller must provide a sample at the unit location as per purchaser requirements. Ensure scheduling aligns with procurement timelines and prepare sample packaging accordingly.
OEM certification validates original equipment manufacturer legitimacy for MS Sheet products. This is a mandatory eligibility criterion; lack of OEM certification would render the bid non-compliant for bid submission.
Penalties or liquidated damages may apply as per ATC terms. Since LD details are not specified, bidders should expect potential penalties and should ensure adequate contingency planning for delivery deadlines.