Bid Publish Date
20-Aug-2026, 10:14 am
Bid End Date
31-Aug-2026, 11:00 am
Location
Progress
RAIndian Army invites bids for Material and Labour for testing, Supply and fixing in replacement of HT, Supply and fixing in replacement, Supply and fixing in replacement of HRC, Supply and fixing in replacement of Aluminium, Supply and fixing in replacement of 11KV, Supply and fixing in replacement of, Supply and fixing Cable jointing kit, Supply and fixing Cable jointing kit for 11 kV, Excavation in trenches not, Returning filling in including, Removing excavated material from, Sand cushioning 8 cm before, Supply and Fixing Unreinforced in JAMMU, JAMMU & KASHMIR. Quantity: 386. Submission Deadline: 31-08-2026 11: 00: 00. Submit your proposal before the deadline.
These are the final prices after the reverse auction event. Prices may be lower than initial bids.
| Rank | Seller | Final Price | Item |
|---|---|---|---|
| L1 | GARIMA TRADER(MSE,MII) Under PMA Winner | ₹5,85,000 | Item Categories : Material and Labour for testing,Supply and fixing in replacement of HT,Supply and fixing in replace |
| L2 | M/S HANS RAJ BUILDERS (MSE) Under PMA | ₹6,70,000 | Item Categories : Material and Labour for testing,Supply and fixing in replacement of HT,Supply and fixing in replace |
| L3 | SUNNY GUPTA (MSE,MII) Under PMA | ₹6,73,200 | Item Categories : Material and Labour for testing,Supply and fixing in replacement of HT,Supply and fixing in replace |
🎉 L1 Winner
GARIMA TRADER(MSE,MII) Under PMA
Final Price: ₹5,85,000
Start
15-Sep-2026, 12:00 pm
End
16-Sep-2026, 12:00 pm
Duration: 24 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
Quantity
386
Category
Material and Labour for testing
Bid Type
Two Packet Bid
Bid Validity
60 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
50% Lowest Priced Technically Qualified Bidders
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
2
Past Performance
50 %
Experience Required
2 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Material and Labour for testing , Supply and fixing in replacement of HT , Supply and fixing in replacement , Supply and fixing in replacement of HRC , Supply and fixing in replacement of Aluminium , Supply and fixing in replacement of 11KV , Supply and fixing in replacement of , Supply and fixing Cable jointing kit , Supply and fixing Cable jointing kit for 11 kV , Excavation in trenches not , Returning filling in including , Removing excavated material from , Sand cushioning 8 cm before , Supply and Fixing Unreinforced
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
2
Pre-Bid Date
18-08-2026 10:00:00
Pre-Bid Venue
GARRISON ENGINEER (AIR FORCE) JAMMU, J&K 180003, CONT NO 9697030227
Max Delivery Days
45
Delivery Locations
1
Delivery Cities
Jammu
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Jammu | Jammu | - | - | 2 | 45 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Material and Labour for testing
Material and Labour for testing of faulty HT cable by using HT high voltage fault locating machine and finding the fault and to be repaired the same including all T and P as required on site complete all as directed.
Supply and fixing in replacement of HT
Supply and fixing in replacement of HT underground cable XLPE insulated PVC bedded galvanised steel strip or wire armoured electric power cables heavy duty with earthed stranded aluminium conductor 11000 volts grade cross sectional area 150 sqmm 3 core laid in duct trenchalong pole etc including making connection complete all as specified
Supply and fixing in replacement
Supply and fixing in replacement of complete fuse trip mechanism suitable for On load Break switch 3 phase 630A
Supply and fixing in replacement of HRC
Supply and fixing in replacement of HRC Fuses with tripping striker pin 11KV Suitable Amps
Supply and fixing in replacement of Aluminium
Supply and fixing in replacement of Aluminium Busbar 50 x 12mm Suitable rating 3P air insulated with colour coded RYB Heat shrinkable sleeves
Supply and fixing in replacement of 11KV
Supply and fixing in replacement of 11KV VCB CT
Supply and fixing in replacement of
Supply and fixing in replacement of 11KV VCB PT
Supply and fixing Cable jointing kit
Supply and fixing Cable jointing kit for 11 KV Earthed grade cable for out door end termination cold shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 150 sq mm complete all as specified
Supply and fixing Cable jointing kit for 11 kV
Supply and fixing Cable jointing kit for 11 kV earthed grade cable for straight through joint heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 150 sq mm complete
Excavation in trenches not
Excavation in trenches not exc 1.5 metres wide and not exc1.5 metres deep for pipe line foundation of poles stays taking out and laying of cables etc in any type of soil getting out and levelling of bottom surface to required level all as specified
Returning filling in including
Returning filling in including spreading leveling watering and well ramming in layers not exc 25 cm thick all as specified
Removing excavated material from
Removing excavated material from site to a distance not exc 50 metres away and depositing where directed not exc 1.5 metres from the starting point all as directed
Sand cushioning 8 cm before
Sand cushioning 8 cm before laying HT LT underground cable in trenches and 15 cm after the cable is laid and all as specified and directed
Supply and Fixing Unreinforced
Supply and Fixing Unreinforced precast concrete cable cover class HV type-1 size 300 X 180 X 40mm complete
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Material and Labour for testing | Material and Labour for testing of faulty HT cable by using HT high voltage fault locating machine and finding the fault and to be repaired the same including all T and P as required on site complete all as directed. | 2 | each job | consignee@geafjmu | 45 | |
| 2 | Supply and fixing in replacement of HT | Supply and fixing in replacement of HT underground cable XLPE insulated PVC bedded galvanised steel strip or wire armoured electric power cables heavy duty with earthed stranded aluminium conductor 11000 volts grade cross sectional area 150 sqmm 3 core laid in duct trenchalong pole etc including making connection complete all as specified | 60 | rm | consignee@geafjmu | 45 | |
| 3 | Supply and fixing in replacement | Supply and fixing in replacement of complete fuse trip mechanism suitable for On load Break switch 3 phase 630A | 1 | each job | consignee@geafjmu | 45 | |
| 4 | Supply and fixing in replacement of HRC | Supply and fixing in replacement of HRC Fuses with tripping striker pin 11KV Suitable Amps | 1 | each job | consignee@geafjmu | 45 | |
| 5 | Supply and fixing in replacement of Aluminium | Supply and fixing in replacement of Aluminium Busbar 50 x 12mm Suitable rating 3P air insulated with colour coded RYB Heat shrinkable sleeves | 1 | each job | consignee@geafjmu | 45 | |
| 6 | Supply and fixing in replacement of 11KV | Supply and fixing in replacement of 11KV VCB CT | 3 | each | consignee@geafjmu | 45 | |
| 7 | Supply and fixing in replacement of | Supply and fixing in replacement of 11KV VCB PT | 3 | each | consignee@geafjmu | 45 | |
| 8 | Supply and fixing Cable jointing kit | Supply and fixing Cable jointing kit for 11 KV Earthed grade cable for out door end termination cold shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured Al conductor cable of size 150 sq mm complete all as specified | 3 | each | consignee@geafjmu | 45 | |
| 9 | Supply and fixing Cable jointing kit for 11 kV | Supply and fixing Cable jointing kit for 11 kV earthed grade cable for straight through joint heat shrink type joint complete with jointing material and accessories suitable for 3 core XLPE armoured aluminium conductor cable of size 150 sq mm complete | 2 | each | consignee@geafjmu | 45 | |
| 10 | Excavation in trenches not | Excavation in trenches not exc 1.5 metres wide and not exc1.5 metres deep for pipe line foundation of poles stays taking out and laying of cables etc in any type of soil getting out and levelling of bottom surface to required level all as specified | 14 | cum | consignee@geafjmu | 45 | |
| 11 | Returning filling in including | Returning filling in including spreading leveling watering and well ramming in layers not exc 25 cm thick all as specified | 10 | cum | consignee@geafjmu | 45 | |
| 12 | Removing excavated material from | Removing excavated material from site to a distance not exc 50 metres away and depositing where directed not exc 1.5 metres from the starting point all as directed | 5 | cum | consignee@geafjmu | 45 | |
| 13 | Sand cushioning 8 cm before | Sand cushioning 8 cm before laying HT LT underground cable in trenches and 15 cm after the cable is laid and all as specified and directed | 4 | cum | consignee@geafjmu | 45 | |
| 14 | Supply and Fixing Unreinforced | Supply and Fixing Unreinforced precast concrete cable cover class HV type-1 size 300 X 180 X 40mm complete | 277 | each | consignee@geafjmu | 46 |
Experience Criteria
Past Performance
Bidder Turnover
Certificate (Requested in ATC) *In case any bidder is seeking exemption from Experience / Turnover Criteria
the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer