Organization: Hindustan Petroleum Corporation Ltd. The procurement concerns a Vertiv UPS system under the scope of SC FOR VERTIV UPS SYSTEM. The tender allows a quantity variation up to 25% at contract; extension of delivery period follows a variable formula with a minimum 30 days. Location details are not disclosed; the requirement emphasizes UPS solutions, vendor capability, and ATC-compliant terms. The opportunity centers on supply and installation readiness with flexible quantities and adherence to delivery timing, at contracted rates. This tender emphasizes standard commercial flexibility and ATC-linked conditions that bidders must navigate to win HPCL procurement.
Product/service names: Vertiv UPS system (uninterruptible power supply)
Quantities: Not specified; quantity variation up to 25% permitted
ESTIMATED value: Not disclosed
Experience: Demonstrate capability to supply/commission UPS systems
Quality/standards: ATC terms to be followed; Vertiv OEM requirements
Delivery/installation: Per original delivery order with extension rules
Warranty/AMC: Not specified in data; refer to ATC
Quantity variation up to 25% during contract execution
Delivery extension rules with minimum 30 days timing
ATC compliance and OEM authorization required
Not specified in data; bidders should follow ATC guidance
Delivery starts from the last date of original order; extension rules apply with minimum 30 days
Not specified in data; ATC may contain LD terms
Demonstrated experience in supplying/commissioning UPS systems (Vertiv or equivalent)
OEM authorization for Vertiv UPS equipment or authorized distributor
Financial capability to handle contract fluctuations up to 25%
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
Yes (Mediation clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 mediation clause should not be routinely included in contracts and pre- litigation mediation can be taken up without any such clause also
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
SC FOR VERTIV UPS SYSTEM
Advisory Bank
ICICI
ePBG Percentage
5%
ePBG Duration (Months)
18
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
1095
Delivery Locations
1
Delivery Cities
Visakhapatanam
Delivery Pincodes
530011
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Banothu Sunil Kumar | 530011,HPCL, Visakh Refinery, PB No. 15, Malkapuram, Visakhapatnam-530011 | Visakhapatanam | Andhra Pradesh | 530011 | 1 | 1095 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
31-Aug-2026, 10:30 am
Opening Date
31-Aug-2026, 11:00 am
Extended Deadline
27-Aug-2026, 10:30 am
Opening Date
27-Aug-2026, 11:00 am
Extended Deadline
24-Aug-2026, 10:30 am
Opening Date
24-Aug-2026, 11:00 am
Extended Deadline
20-Aug-2026, 10:30 am
Opening Date
20-Aug-2026, 11:00 am
GST registration
PAN card
Experience certificates (similar UPS system supply/installation)
Financial statements (as required by ATC)
EMD/Security deposit documents (as specified in ATC)
Technical bid documents demonstrating Vertiv UPS capability
OEM authorization confirming Vertiv as OEM or authorized distributor
Any additional documents specified in Buyer Added ATC
Key insights about ANDHRA PRADESH tender market
Bidders must submit GST, PAN, and experience certificates, plus an EMD as per ATC. Ensure Vertiv OEM authorization is included and reference the uploaded ATC for warranties, delivery, and payment terms. Prepare technical bid showing Vertiv UPS capabilities and installation readiness; follow delivery extension rules and contract quantity variation.
Essential documents include GST certificate, PAN card, experience certificates for UPS supply/installation, financial statements, EMD/security deposit, OEM authorization for Vertiv, and technical compliance documents. ATC may mandate additional certifications; ensure all documents align with the bid format and HPCL guidelines.
Delivery can extend beyond the original period if the option clause is exercised, with the formula (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days. Extensions may continue up to the original delivery period under ATC terms.
Bidders must comply with Vertiv OEM requirements and any standards stated in the uploaded ATC. Expect IS/ISO alignment where applicable and warranty terms from ATC. Ensure Vertiv authorisation is provided and installation capability demonstrated.
The dataset does not specify a submission deadline. Bidders should consult the ATC document linked by the buyer and monitor HPCL tender portals for the exact closing date and bid submission instructions, ensuring timely submission of all required documents.
The EMD amount is not disclosed in the provided data. Bidders must refer to the ATC document for the exact EMD or bid security percentage, and prepare payment via the specified mode prior to bid submission.
Eligibility requires UPS supply/installation experience, Vertiv OEM authorization, financial capability to handle quantity fluctuations up to 25%, and compliance with ATC terms. Gather experience certificates, OEM authorizations, and financial documents to demonstrate capability.
Delivery terms specify commencement from the last date of the original delivery order, with possible extension as per option clause. Minimum extension period is 30 days; extended delivery may occur within contracted rates for increased quantity up to 25%.