The Indian Council Of Agricultural Research (ICAR), under the Department Of Agricultural Research And Education (DARE), seeks to procure HDPE irrigation pipes. The tender lacks published specifications and BOQ items, with the total quantity and estimated value not disclosed. The location is not specified in the available data. A key differentiator is the documented option clause allowing a ±25% quantity variation at contracted rates, impacting supply planning and pricing. Affected deliveries would commence from the last date of the original delivery order, with extension logic based on a formula tied to increased quantity. An ATC document has been uploaded for bidder reference.
Product/service: HDPE irrigation pipe
Estimated value: Not disclosed
Quantities: Not disclosed (quantity variation up to 25%)
Delivery: From last date of original delivery order; extended delivery time formula
Standards/Certification: Not specified in data; ATC doc may contain requirements
Brand/OEM: Not specified
Warranty/Support: Not specified
Option Clause permits ±25% quantity variation at contract rates
Delivery extension calculated as (Increased quantity ÷ Original quantity) × Original delivery period with min 30 days
ATC document governs additional terms and bidder compliance
Delivery starts after last date of original delivery order; extension time computed per option clause with minimum 30 days
Purchaser may increase or decrease quantity by up to 25% during contract and currency with contracted rates
Uploader has provided an ATC document; bidders must review for detailed terms and compliance
Submit GST registration and PAN as part of bid documents
Demonstrate ability to handle HDPE irrigation pipe procurement (if experience required in ATC)
Agree to quantity variation and delivery extension terms outlined in the ATC
Quantity
200
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
1
OEM Avg. Turnover
4
Past Performance
50 %
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
HDPE irrigation pipe
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Lucknow
Delivery Pincodes
226002
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Arvind Kumar Yadav | 226002,Raebareli Road, P.O. Dilkusha | Lucknow | Uttar Pradesh | 226002 | 200 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
17-Oct-2026, 12:30 pm
Opening Date
18-Oct-2026, 12:30 pm
GST registration certificate
PAN card
Experience certificates (if any for HDPE pipe supply)
Financial statements or turnover proof
EMD/Security deposit documents (if specified in ATC)
Technical bid documents and OEM authorizations (if required in ATC)
Any other documents required by the ATC file uploaded by the Buyer
Key insights about UTTAR PRADESH tender market
Bidders should review the ATC document uploaded by ICAR, ensure compliance with the quantity variation clause up to 25%, prepare GST, PAN, and financial documents, and await original delivery order dates to determine delivery timelines. The tender lacks published BOQ items, so confirm exact pipe specifications during contract finalization.
Mandatory documents include GST certificate, PAN, experience certificates for HDPE pipe supply (if applicable), financial statements, and EMD/Security as per ATC. Also include technical bid documents and OEM authorizations if required by the ATC file to demonstrate supplier capability.
Delivery begins from the last date of the original delivery order. If quantity increases, delivery time extends by (Increased quantity ÷ Original quantity) × Original delivery period, with a minimum extension of 30 days. Ensure compliance with the ATC for any additional conditions.
EMD details are not published in the available data. Bidders should verify the ATC document for any EMD amount or alternative security требования and ensure submission with the bid as specified by ICAR.
No explicit standards are listed in the data. The ATC document may specify requirements. Bidders should obtain any applicable certifications and verify if ISI/ISO or material grade standards apply once the ATC is reviewed.
Bidder pricing must accommodate a potential ±25% quantity change at contracted rates. Prepare pricing for base quantity and ensure flexibility in cost per unit. Delivery schedules will adjust as per the extension formula, affecting overall project timeline.
The available data does not specify dates. Bidders should monitor the ATC and procurement portal for the final award timeline; ensure readiness with complete documents and a compliant bid under ICAR procurement procedures.
The ATC will outline submission requirements, quantity variation rules, delivery extensions, and any special terms not in the basic tender. Bidders must review the ATC to ensure full compliance and align bids with ICAR procurement expectations.