Power Grid Corporation Of India Limited Handling and Transport Tender Balipara Assam 400kV D/C Quad Line Lump Sum 2026

Bid Publish Date

10-Oct-2026, 5:42 pm

Bid End Date

26-Oct-2026, 11:00 am

EMD

₹22,000

Value

₹13,02,720

Progress

Issue10-Oct-2026, 5:42 pm
AwardPending

Key Highlights

  • • 60% Minimum Local Content requirement for eligibility
  • • 25% quantity/contract duration variation allowed by buyer
  • • Non-divisible lumpsum service contract for 400KV tower material segregation and transport
  • • Completion period fixed at 4 months from award

Tender Overview

Power Grid Corporation Of India Limited seeks a lumpsum service contract for segregation of tower materials including transportation, shifting, and complete set assembly as per inventory norms for the 400KV D/C Balipara-Bongaigaon-III & IV (Quad) Line at Balipara Sub-Station, Assam. Estimated value is ₹11,04,000 (likely excluding GST) with an EMD of ₹22,000. Completion is defined as 4 months. This non-divisible scope emphasizes local content requirements (60% minimum) and adherence to the Owner’s Works & Procurement Policy as posted on PowerGrid’s site. The contract allows a potential scope/quantity increase up to 25% under the lump-sum framework with mutual consent, ensuring adaptability to field realities.

Technical Specifications & Requirements

  • No detailed product specs published; scope centers on logistics and material handling for 400KV tower components and related inventory segregation.
  • Key scope items include: segregation of tower materials, transportation, shifting, and assembling per inventory norms for the specified Balipara–Bongaigaon corridor.
  • Completion deadline: 4 months from award.
  • Non-divisible contract with 60% minimum local content (MII/MSC equivalent); references to GEM/POWERGRID Works & Procurement Policy and Procedure (Vol-I & Vol-II) on official site.
  • Economic details: Estimated cost ₹11,04,000 (excluding GST); EMD ₹22,000.
  • Bidders should prepare for a single-stage, single-envelope process under category-based bidding, with ATC specifics provided in the tender text.

Terms, Conditions & Eligibility

  • 25% scope/duration flexibility allowed at contract issue and subsequently up to 25% with consent.
  • Non-divisible contract term; no applicability of e-RA; not applicable for integrity pact.
  • Minimum Local Content 60%; MII purchase preference noted per policy.
  • EMD: ₹22,000; delivery/completion: 4 months; payment terms aligned to lump-sum completion milestones.
  • Documentation aligns with PowerGrid policy; bidders must reference Works & Procurement Policy on www.powergrid.in; no additional contractual claims based on policy excerpts.

Key Specifications

  • Scope: segregation and transport of 400KV D/C Balipara-Bongaigaon-III & IV tower materials

  • Location: Balipara Sub-Station, Assam

  • Completion: 4 months

  • Estimated Cost: ₹11,04,000 (excluding GST)

  • EMD: ₹22,000

  • Local content: minimum 60%

  • Contract type: non-divisible lumpsum.

  • Policy reference: PowerGrid Works & Procurement Policy Vol-I & Vol-II

Terms & Conditions

  • 25% scope/duration adjustment allowed at contract issue and within agreement

  • Non-divisible lumpsum service contract for tower material handling

  • 60% minimum local content required for eligibility

Important Clauses

Payment Terms

Lumpsum payment upon completion with milestones per award; no detailed schedule provided in data.

Delivery Schedule

Completion within 4 months from date of award; extensions subject to approval within 25% scope change.

Penalties/Liquidated Damages

Not explicitly stated in available data; penalties likely governed by PowerGrid policy and contract terms.

Bidder Eligibility

  • Proven experience in similar tower material segregation and transport projects

  • Demonstrated ability to meet 60% local content requirement

  • Financial capability to take on a ₹11,04,000 scope excluding GST

Advertisement

Tender Data

Bid Details

Quantity

1

Bid Type

Single Packet Bid

Bid Validity

180 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Tech Clarification Time

4 Days

Preference & Exemptions

EMD Required

Yes

MII Compliance

Yes

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

Yes (Arbitration clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 Arbitration should not be routinely included in contracts

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Service

Bid To RA

No

Bid To RA Enabled

No

Item Category

Handling and Transport on Lumpsum Basis - as per Gem bid

Advisory Bank

State Bank of India

ePBG Percentage

5%

ePBG Duration (Months)

7

Payment Timelines

Payments shall be made to the Seller within 30 days of issue of service delivery acceptance certificate (SDAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Delivery Locations

1

Delivery Cities

Sonitpur

Delivery Pincodes

784103

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Dhruba Narayan Sarmah784103,Power Grid Corporation Of India Limited,APCOMP. SCHEME, 400/220/132 KV BALIPARA SUBSTATION, POWERGRID, PO/PS: CHARDUAR, DIST:SONITPUR, ASSAM-784103SonitpurAssam784103Project / Lumpsum Based--

Authority Records

MINISTRY OF POWERPOWER GRID CORPORATION OF INDIA LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 10

GeM-Bidding-9951370.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Office Name

Corporate Office Gurgaon

Grievance Contact

[email protected]

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

GST Registration Certificate

2

Permanent Account Number (PAN) Card

3

Experience Certificates for similar tower material segregation and transport projects

4

Financial Statements (last 2-3 years)

5

EMD document (payment receipt or bank guarantee)

6

Technical bid documents demonstrating capability for lumpsum logistics

7

OEM authorizations or supplier qualifications if required by terms

8

Any local content certificates or declarations as per policy

Frequently Asked Questions

Key insights about ASSAM tender market

How to bid for Power Grid logistics tender in Balipara Assam 2026

Bidders should review the Works & Procurement Policy on PowerGrid’s website, prepare a lumpsum offer for segregation and transport of 400KV tower materials, ensure 60% local content, submit EMD ₹22,000, and complete within 4 months. The single-stage, single-envelope process requires category-based bids with all required documents.

What documents are required for PowerGrid Assam transport tender 2026

Prepare GST registration, PAN, 2-3 years financials, experience certificates for similar projects, EMD receipt or bank guarantee, technical bid documents showing capability for lumpsum logistics, and OEM authorizations if applicable, plus any local content certificates as per policy.

What are the eligibility criteria for 400KV tower materials transport tender Balipara

Eligible bidders must demonstrate experience in tower material segregation and transport, meet the 60% minimum local content requirement, possess financial stability with prior similar project values, and comply with PowerGrid’s policy references available on www.powergrid.in.

What is the EMD for the Power Grid transport contract in Assam 2026

The EMD amount is ₹22,000. Bidders should attach payment proof or a bank guarantee as per tender guidelines; ensure readiness to submit with the technical bid to participate in the single-stage process.

What is the completion timeline for the Balipara–Bongaigaon line tender

The completion period is 4 months from the date of contract award. Proposals may include up to a 25% scope/duration increase with mutual consent; any extension must remain within this limit.

Which region and line are covered by this Power Grid tender 2026

The tender covers the Balipara–Bongaigaon-III & IV Quad Line at the Balipara Sub-Station in Assam; scope includes segregation and transport of tower materials per inventory norms.

What is the estimated contract value for the Assam logistics tender

Estimated cost is ₹11,04,000 excluding GST; bidders should factor this into their lumpsum bid, along with the EMD and local content requirements, for a compliant submission.

Are there any special policy references bidders must follow for PowerGrid

Yes, bidders must review the PowerGrid Works & Procurement Policy and Procedure Vol-I & Vol-II on the official website; these policies govern eligibility, bids, and contractual rights, and must be acknowledged during submission.