Progress
The Indian Army, Department Of Military Affairs, seeks a SWARM category solution in Ranchi, Jharkhand. The scope covers Supply, Installation, Testing, Commissioning of Goods and Training of operators plus providing any required statutory clearances. A compulsory prebid meeting is scheduled for 18 Aug 2026 at the unit location in Ranchi. The contract allows up to 25% quantity variation at bid or during execution, with rates at contracted levels. The delivery timeline starts after the original delivery order date, with adjustments for extended periods. The tender emphasizes end-to-end supply chain, training within one week post-delivery, and replacement for damages during transit or training. The estimated value and EMD are not disclosed in the provided data.
Scope of supply includes: Supply, Installation, Testing, Commissioning, and Training
Delivery flexibility: up to 25% quantity variation at contract formation and during currency
Delivery time rules: new time = (Increased quantity / Original quantity) × Original delivery period; minimum 30 days
Training: troops’ training within one week of delivery; replacements for damages during training or transit
Location: unit in Ranchi, Jharkhand; prebid meeting at same location
EMD amount not disclosed; verify during bid submission
Option clause permits 25% quantity variation at any contract stage
Mandatory prebid meeting on 18 Aug 2026 at Ranchi unit location
All-inclusive bid price covering supply, installation, testing, commissioning, and training
Replacement policy for damages during transit or training
Mandatory prebid meeting on 18 August 2026 at the unit location in Ranchi; participation is compulsory for all bidders.
Buyer may increase/decrease quantity up to 25% at bid and during currency of contract; prices remain at contracted rates.
Delivery period adjusted per formula with a minimum of 30 days; training to troops within one week at no cost; replacements for in-transit or training damages.
Eligibility to participate requires compliance with compulsory prebid meeting and submission of all required documents
Proven experience in supplying SWARM or related defense systems
Financial capability evidenced by recent financial statements and solvency
Quantity
4
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Min. Avg. Annual Turnover
1
OEM Avg. Turnover
2
Past Performance
70 %
Experience Required
2 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
SWARM
Max Delivery Days
45
Delivery Locations
1
Delivery Cities
Ranchi
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Ranchi | Ranchi | - | - | 4 | 45 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar SWARM-related supplies
Financial statements/balance sheet for the last 2-3 years
EMD/Security deposit submission proof (as applicable by tender terms)
Technical bid documents demonstrating compliance with scope
OEM authorization letters (if applicable) and product compliance certificates
Any statutory clearances related to installation and commissioning
Key insights about JHARKHAND tender market
Bidders must attend the compulsory prebid meeting on 18 Aug 2026 at the Ranchi unit location, submit all required documents (GST, PAN, experience, financials, OEM authorizations), and provide an all-inclusive bid covering supply, installation, testing, commissioning, and training.
Required documents include GST certificate, PAN, 2-3 years financials, experience certificates for similar projects, EMD submission proof, technical bid demonstrating compliance, OEM authorizations, and any statutory clearances related to installation and commissioning.
Delivery timing follows the original delivery period with potential extension; additional time is calculated as (Increased quantity / Original quantity) × Original delivery period, minimum 30 days, with possible extension up to the original delivery period.
Scope includes Supply, Installation, Testing, Commissioning of SWARM goods, plus training of operators and providing any required statutory clearances; all costs must be included in the bid price.
ATC requires compulsory prebid, free post-delivery troop training within one week, and replacement of items damaged during transit or training, with all costs covered by the vendor.
Quantity variation up to 25% of bid quantity at the time of contract placement and permissible during currency of contract at contracted rates; bidders should plan for scalability.
The tender data does not list specific standards; bidders should reference ISI/ISO certifications and ensure compliance with supplier quality norms as applicable to defense procurements.