Tender Overview

Organization: Indian Army (Department Of Military Affairs) seeking supply of goods at Sri Ganganagar, Rajasthan (335771). The BOQ lists 129 items, though item-specific data is not disclosed. The contract scope covers Only supply of Goods with an optional quantity variation of up to 25% during contract execution. Delivery timing is tied to the original delivery order, with extended time calculated by a defined formula, ensuring bidders account for potential volume fluctuations. This tender emphasizes price-inclusive scope and strict adherence to delivery windows, while withholding itemized specs in the provided data.

  • Location: Sri Ganganagar, Rajasthan
  • Quantity/Items: 129 total items in BOQ (data not itemized)
  • Estimated Value: Not disclosed
  • Purchase Scope: Only supply of goods; no services included
  • Option Clause: 25% quantity variation; extended delivery period logic applies
  • Delivery Roles: Delivery commence from last date of original DO; time extension formula applied

Technical Specifications & Requirements

  • No technical specifications provided in tender data; bidders should prepare for generic goods-supply compliance
  • BOQ indicates 129 items but item-level data is not disclosed; bidders must assume broad goods category and ensure compliant documentation
  • Scope requires price to include all costs; no separate services or installation requirements noted
  • Delivery timelines hinge on original DO date and applied option-quantity rules; plan buffers for potential extension
  • Emphasize bid readiness with robust logistics, storage, and quality assurance practices to meet Army standards

Terms & Eligibility

  • EMD amount not disclosed in the tender data; confirm exact amount and payment method in final tender documents
  • Option Clause allows ±25% quantity change during contract at contracted rates
  • Delivery: timing based on last date of original DO; extended delivery computed as (additional quantity/original quantity) × original period, min 30 days
  • Bid Scope: price must include all cost components; only supply of goods
  • Ensure readiness for compliance with Army procurement policies and document submissions; itemized specs not provided

Key Specifications

  • Total BOQ items: 129

  • Product/Category: Goods Supply (no service/installation data)

  • Delivery terms: from last date of original delivery order

  • Option: quantity variation up to 25% during contract

  • Price: bid price to include all cost components

Terms & Conditions

  • Option clause permits up to 25% quantity variation at contracted rates

  • Delivery schedule linked to original delivery order date with extended time rules

  • Price bid must cover all costs; no separate service components

Important Clauses

Delivery Terms

Delivery begins from the last date of the original delivery order; extension calculated as (additional quantity/original quantity) × original delivery period, with a minimum of 30 days

Scope of Supply

Bid price to include all cost components; only supply of Goods, no installation or services

Option Clause

Purchaser may increase/decrease quantity up to 25% during contract execution at the contracted rates

Bidder Eligibility

  • Proven experience in delivering goods-supply contracts to government or defense entities

  • Financial stability demonstrated by annual turnover sufficient to support procurement scope

  • Ability to meet timely delivery and compliance with government procurement terms

Tender Data

Bid Details

Quantity

8152

Category

LV2 ICVS 4720720409046 765 07 13 HOSE 10230476

Bid Type

Two Packet Bid

Bid Validity

180 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

Yes

Startup Exemption/Relaxation

Yes

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Delivery Details

Max Delivery Days

15

Delivery Locations

1

Delivery Cities

Sri Ganganagar

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
-Sri GanganagarSri Ganganagar--615-

Authority Records

MINISTRY OF DEFENCEMILITARY AFFAIRS DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 4

GeM-Bidding-9834289.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Authority & Contact

Organization

Indian Army

Office Name

Not disclosed yet

Grievance Contact

[email protected]

Bill of Quantities (BOQ) 129 Items Sign in for GEM prices

#1

LV2 ICVS 4720720409046 765 07 13 HOSE 10230476

LV2 ICVS 4720720409046 765 07 13 HOSE 10230476

6 pieces Delivery: 15 days
#2

LV2 ICVS 4720720260274 765 05 24 HOSE 10230496

LV2 ICVS 4720720260274 765 05 24 HOSE 10230496

2 pieces Delivery: 15 days
#3

LV2 ICVS 4720720260287 765 78 717 HOSE NON METALLIC 10235776

LV2 ICVS 4720720260287 765 78 717 HOSE NON METALLIC 10235776

4 pieces Delivery: 15 days
#4

LV2 ICVS 4720720260237 765 05 726 HOSE NONMETALLIC 10236419

LV2 ICVS 4720720260237 765 05 726 HOSE NONMETALLIC 10236419

2 pieces Delivery: 15 days
#5

LV2 ICVS 765 05 369 CANVAS COVER

LV2 ICVS 765 05 369 CANVAS COVER

2 pieces Delivery: 15 days
#6

LV2 ICVS 5330 014024 700 40 260 06 GASKET 10274947

LV2 ICVS 5330 014024 700 40 260 06 GASKET 10274947

14 pieces Delivery: 15 days
#7

LV2 ICVS 5330720114245 700 40 260 19 GASKET 10275460

LV2 ICVS 5330720114245 700 40 260 19 GASKET 10275460

2 pieces Delivery: 15 days
#8

LV2 ICVS 5330720365256 765 06 311 GASKET SPECIAL 10274346

LV2 ICVS 5330720365256 765 06 311 GASKET SPECIAL 10274346

2 pieces Delivery: 15 days
#9

LV2 ICVS 5330 380692 765 06 842 765 06 842K SEALING RING

LV2 ICVS 5330 380692 765 06 842 765 06 842K SEALING RING

4 pieces Delivery: 15 days
#10

LV2 ICVS 730 04 225 GASKET

LV2 ICVS 730 04 225 GASKET

8 pieces Delivery: 15 days
#11

LV2 ICVS 5330 019129 765 06 135 GASKET 10235238

LV2 ICVS 5330 019129 765 06 135 GASKET 10235238

4 pieces Delivery: 15 days
#12

LV2 ICVS 5330720234184 765 08 928 765 08 928K GASKET

LV2 ICVS 5330720234184 765 08 928 765 08 928K GASKET

4 pieces Delivery: 15 days
#13

LV2 ICVS 765 08 1014 GASKET

LV2 ICVS 765 08 1014 GASKET

2 pieces Delivery: 15 days
#14

LV2 ICVS 5315720113846 765 10 1009 GASKET 10230395

LV2 ICVS 5315720113846 765 10 1009 GASKET 10230395

2 pieces Delivery: 15 days
#15

LV2 ICVS 5330 396446 765 10 1170 GASKET 10262759

LV2 ICVS 5330 396446 765 10 1170 GASKET 10262759

2 pieces Delivery: 15 days
#16

LV2 ICVS 5330009176 765 10 1380 GASKET

LV2 ICVS 5330009176 765 10 1380 GASKET

2 pieces Delivery: 15 days
#17

LV2 ICVS 5330720234642 775 36 25 RING

LV2 ICVS 5330720234642 775 36 25 RING

6 pieces Delivery: 15 days
#18

LV2 ICVS 5330720115872 765 31 13 RING SEALING TOROIDAL 10233878

LV2 ICVS 5330720115872 765 31 13 RING SEALING TOROIDAL 10233878

6 pieces Delivery: 15 days
#19

LV2 ICVS 5331720324411 765 12 801 RING 10256228

LV2 ICVS 5331720324411 765 12 801 RING 10256228

2 pieces Delivery: 15 days
#20

LV2 ICVS 5340720271322 765 17 29 BOOT 10231339

LV2 ICVS 5340720271322 765 17 29 BOOT 10231339

2 pieces Delivery: 15 days
#21

LV2 ICVS 5340720270538 765 17 46 BOOT 10230666

LV2 ICVS 5340720270538 765 17 46 BOOT 10230666

8 pieces Delivery: 15 days
#22

LV2 ICVS 5330720115634 765 31 71 SEAL PLAIN 10279892

LV2 ICVS 5330720115634 765 31 71 SEAL PLAIN 10279892

4 pieces Delivery: 15 days
#23

LV2 ICVS 5340 013718 765 33 40 RING SEALING TOROIDAL 10233910

LV2 ICVS 5340 013718 765 33 40 RING SEALING TOROIDAL 10233910

28 pieces Delivery: 15 days
#24

LV2 ICVS 2520720466477 CQA ICV SET 038 CUP SPRING

LV2 ICVS 2520720466477 CQA ICV SET 038 CUP SPRING

4 pieces Delivery: 15 days
#25

LV2 ICVS 700 40 123 GASKET

LV2 ICVS 700 40 123 GASKET

24 pieces Delivery: 15 days
#26

LV2 ICVS 5331720321380 765 33 6 RING SEALING TOROIDAL 10235694

LV2 ICVS 5331720321380 765 33 6 RING SEALING TOROIDAL 10235694

24 pieces Delivery: 15 days
#27

LV2 ICVS 765 33 54 RING SEALING TORIDIAL

LV2 ICVS 765 33 54 RING SEALING TORIDIAL

40 pieces Delivery: 15 days
#28

LV2 ICVS 5330397585 CQA ICV SET 025 CUP SPRING CONSISTING OF 10233620

LV2 ICVS 5330397585 CQA ICV SET 025 CUP SPRING CONSISTING OF 10233620

48 pieces Delivery: 15 days
#29

LV2 ICVS 5330397587 CQA ICV SET 027 CUP SPRING CONSISTING

LV2 ICVS 5330397587 CQA ICV SET 027 CUP SPRING CONSISTING

48 pieces Delivery: 15 days
#30

LV2 ICVS 765 38 242 GASKET

LV2 ICVS 765 38 242 GASKET

10 pieces Delivery: 15 days
#31

LV2 RCV 675 42 SB129 BOLT

LV2 RCV 675 42 SB129 BOLT

2 pieces Delivery: 15 days
#32

Z21 GED 765 42 70 CAP

Z21 GED 765 42 70 CAP

2 pieces Delivery: 15 days
#33

LV2 ICVS 5330720170662 765 50 SB658 PACKING 10233758

LV2 ICVS 5330720170662 765 50 SB658 PACKING 10233758

2 pieces Delivery: 15 days
#34

LV2 ICVS 3030720153540 765 50 SB951 BELT 10256424

LV2 ICVS 3030720153540 765 50 SB951 BELT 10256424

4 pieces Delivery: 15 days
#35

LV2 ICVS 5330720115450 765 50 878 GASKET 765 50 878 10233495

LV2 ICVS 5330720115450 765 50 878 GASKET 765 50 878 10233495

2 pieces Delivery: 15 days
#36

LV2 ICVS 5340720368156 765 50 1552 BUFFER 10230278

LV2 ICVS 5340720368156 765 50 1552 BUFFER 10230278

4 pieces Delivery: 15 days
#37

LV2 ICVS 5340720424972 765 50 1553 BUFFER 10233930

LV2 ICVS 5340720424972 765 50 1553 BUFFER 10233930

4 pieces Delivery: 15 days
#38

LV2 ICVS 5340014823 765 50 1963 MOUNT RESILENT 10283248

LV2 ICVS 5340014823 765 50 1963 MOUNT RESILENT 10283248

4 pieces Delivery: 15 days
#39

LV2 ICVS 765 50 2582 GASKET

LV2 ICVS 765 50 2582 GASKET

2 pieces Delivery: 15 days
#40

LV2 ICVS 765 50 2597 GASKET

LV2 ICVS 765 50 2597 GASKET

2 pieces Delivery: 15 days
#41

LV2 ICVS 765 50 2962 GASKET

LV2 ICVS 765 50 2962 GASKET

18 pieces Delivery: 15 days
#42

LV2 ICVS 730 50 366 GASKET

LV2 ICVS 730 50 366 GASKET

2 pieces Delivery: 15 days
#43

LV2 ICVS 5340720270537 765 50 SB599 HOSE 10233357

LV2 ICVS 5340720270537 765 50 SB599 HOSE 10233357

6 pieces Delivery: 15 days
#44

LV2 ICVS 5340720270536 765 50 SB600 HOSE 10233668

LV2 ICVS 5340720270536 765 50 SB600 HOSE 10233668

2 pieces Delivery: 15 days
#45

LV2 RCV 5340015314 765 51 46 BUMPER 10233386

LV2 RCV 5340015314 765 51 46 BUMPER 10233386

4 pieces Delivery: 15 days
#46

N1 675 51 153 COVER

N1 675 51 153 COVER

10 pieces Delivery: 15 days
#47

N1 1005560419 COVER ASSEMBLY

N1 1005560419 COVER ASSEMBLY

2 pieces Delivery: 15 days
#48

V5 RUS 675 53 SB 147 HOSE

V5 RUS 675 53 SB 147 HOSE

2 pieces Delivery: 15 days
#49

V5 RUS 775 36 25 RING

V5 RUS 775 36 25 RING

2 pieces Delivery: 15 days
#50

LV2 ICVS 700 40 260 1 GASKET

LV2 ICVS 700 40 260 1 GASKET

2 pieces Delivery: 15 days
#51

LV2 ICVS 700 40 260 08 GASKET

LV2 ICVS 700 40 260 08 GASKET

4 pieces Delivery: 15 days
#52

LV2 ICVS 765 55 130 OIL SEAL

LV2 ICVS 765 55 130 OIL SEAL

2 pieces Delivery: 15 days
#53

LV2 ICVS 675 54 157 GASKET

LV2 ICVS 675 54 157 GASKET

2 pieces Delivery: 15 days
#54

V5 765 56 26 RING

V5 765 56 26 RING

2 pieces Delivery: 15 days
#55

LV2 RCV 765 56 52 SHOCK ABSORBER

LV2 RCV 765 56 52 SHOCK ABSORBER

6 pieces Delivery: 15 days
#56

V5 765 56 92 GASKET

V5 765 56 92 GASKET

2 pieces Delivery: 15 days
#57

V5 765 56 93 GASKET

V5 765 56 93 GASKET

2 pieces Delivery: 15 days
#58

V5 765 56 105 GASKET

V5 765 56 105 GASKET

4 pieces Delivery: 15 days
#59

V5 765 66 204 RING

V5 765 66 204 RING

2 pieces Delivery: 15 days
#60

V5 RUS 765 66 226 PACKING

V5 RUS 765 66 226 PACKING

4 pieces Delivery: 15 days
#61

V5 765 56 46 GASKET

V5 765 56 46 GASKET

2 pieces Delivery: 15 days
#62

V5 765 56 59 OIL SEAL

V5 765 56 59 OIL SEAL

2 pieces Delivery: 15 days
#63

V5 RUS 7654 66 SB 106 CLEANER

V5 RUS 7654 66 SB 106 CLEANER

22 pieces Delivery: 15 days
#64

V5 765 66 193 GASKET

V5 765 66 193 GASKET

6 pieces Delivery: 15 days
#65

K9 BMP NBC 765 71 341 END PIECE

K9 BMP NBC 765 71 341 END PIECE

16 pieces Delivery: 15 days
#66

K9 BMP NBC 765 71 556 END PIECE

K9 BMP NBC 765 71 556 END PIECE

2 pieces Delivery: 15 days
#67

K9 BMP NBC 765 71 910 GASKET

K9 BMP NBC 765 71 910 GASKET

2 pieces Delivery: 15 days
#68

K9 BMP NBC 675 71 235 GASKET

K9 BMP NBC 675 71 235 GASKET

2 pieces Delivery: 15 days
#69

K9 BMP NBC 765 71 283 SEALING GASKET

K9 BMP NBC 765 71 283 SEALING GASKET

2 pieces Delivery: 15 days
#70

K9 BMP NBC 675 71 307 GASKET

K9 BMP NBC 675 71 307 GASKET

2 pieces Delivery: 15 days
#71

K9 BMP NBC 675 71 342 HOSE

K9 BMP NBC 675 71 342 HOSE

2 pieces Delivery: 15 days
#72

LV1 ICVS 5330720319169 GASKET

LV1 ICVS 5330720319169 GASKET

2 pieces Delivery: 15 days
#73

LV1 ICVS 5330400001910 NBC COVER GASKET

LV1 ICVS 5330400001910 NBC COVER GASKET

2 pieces Delivery: 15 days
#74

LV1 ICVS 765 50 1410 GASKET

LV1 ICVS 765 50 1410 GASKET

2 pieces Delivery: 15 days
#75

LV1 ICVS 5330720116654 GASKET

LV1 ICVS 5330720116654 GASKET

2 pieces Delivery: 15 days
#76

LV1 ICVS 5330127001631 GASKET

LV1 ICVS 5330127001631 GASKET

2 pieces Delivery: 15 days
#77

LV1 ICVS 765 46 228 GASKET SPECIAL

LV1 ICVS 765 46 228 GASKET SPECIAL

12 pieces Delivery: 15 days
#78

LV1 ICVS 765 46 352 GASKET SPECIAL

LV1 ICVS 765 46 352 GASKET SPECIAL

4 pieces Delivery: 15 days
#79

LV1 ICVS 765 17 619 BUSHING SLEEVE

LV1 ICVS 765 17 619 BUSHING SLEEVE

6 pieces Delivery: 15 days
#80

LV1 ICVS 765 17 349 BOOT DUST MOISURE SEAL

LV1 ICVS 765 17 349 BOOT DUST MOISURE SEAL

4 pieces Delivery: 15 days
#81

LV1 ICVS 765 17 368 GASKET

LV1 ICVS 765 17 368 GASKET

2 pieces Delivery: 15 days
#82

LV1 ICVS 765 17 427 GASKET

LV1 ICVS 765 17 427 GASKET

2 pieces Delivery: 15 days
#83

LV1 ICVS 765 49 55 FRAME

LV1 ICVS 765 49 55 FRAME

2 pieces Delivery: 15 days
#84

LV1 ICVS 765 82 193 GASKET

LV1 ICVS 765 82 193 GASKET

12 pieces Delivery: 15 days
#85

LV1 ICVS 765 38 81 GASKET

LV1 ICVS 765 38 81 GASKET

12 pieces Delivery: 15 days
#86

K9 BMP NBC 765 71 1463 GASKET

K9 BMP NBC 765 71 1463 GASKET

2 pieces Delivery: 15 days
#87

LV4 RCV 675 51SB 126 MANTLE COVER

LV4 RCV 675 51SB 126 MANTLE COVER

2 pieces Delivery: 15 days
#88

K9 BMP NBC 765 71 362 GASKET

K9 BMP NBC 765 71 362 GASKET

10 pieces Delivery: 15 days
#89

LV4 RCV 8305 003777 PACKING

LV4 RCV 8305 003777 PACKING

4 pieces Delivery: 15 days
#90

Z1 MISC 765 86 23 GASKET

Z1 MISC 765 86 23 GASKET

2 pieces Delivery: 15 days
#91

LV1 R72 675 71 225 1 GASKET

LV1 R72 675 71 225 1 GASKET

2 pieces Delivery: 15 days
#92

K9 BMP NBC 675 71 224 GASKET

K9 BMP NBC 675 71 224 GASKET

2 pieces Delivery: 15 days
#93

V5 MISC AU8 634 173 GASKET

V5 MISC AU8 634 173 GASKET

4 pieces Delivery: 15 days
#94

K9 BMP NBC 765 71 144 GASKET

K9 BMP NBC 765 71 144 GASKET

2 pieces Delivery: 15 days
#95

K9 BMP NBC 765 71 1428 GASKET

K9 BMP NBC 765 71 1428 GASKET

2 pieces Delivery: 15 days
#96

LV2 ICVS 765 58 216 CASING FLEXIBLE SHAFT ASSY

LV2 ICVS 765 58 216 CASING FLEXIBLE SHAFT ASSY

2 pieces Delivery: 15 days
#97

LV2 ICVS 675 58 132 PACKING

LV2 ICVS 675 58 132 PACKING

2 pieces Delivery: 15 days
#98

LV2 ICVS 765 78 SB724 HOSE

LV2 ICVS 765 78 SB724 HOSE

4 pieces Delivery: 15 days
#99

LV2 ICVS 765 78 66 ADOPTOR ELBOW PIPE

LV2 ICVS 765 78 66 ADOPTOR ELBOW PIPE

4 pieces Delivery: 15 days
#100

LV2 ICVS 765 78 1406 SEALING RING

LV2 ICVS 765 78 1406 SEALING RING

2 pieces Delivery: 15 days
#101

LV2 ICVS 765 82 SB394 HOSE ASSY

LV2 ICVS 765 82 SB394 HOSE ASSY

4 pieces Delivery: 15 days
#102

K9 730 87 88 GASKET

K9 730 87 88 GASKET

4 pieces Delivery: 15 days
#103

K9 BMP FF 274026220163 RUBBER HOSE

K9 BMP FF 274026220163 RUBBER HOSE

2 pieces Delivery: 15 days
#104

K9 BMP FF 3053 005 003 83 HOSE CLAMP

K9 BMP FF 3053 005 003 83 HOSE CLAMP

4 pieces Delivery: 15 days
#105

Z6 MISC 730 82 219 RUBBER END PIECE

Z6 MISC 730 82 219 RUBBER END PIECE

4 pieces Delivery: 15 days
#106

LV2 RCV 775 97 11 OR 54 26 390 2 BOOT RUBBER

LV2 RCV 775 97 11 OR 54 26 390 2 BOOT RUBBER

6 pieces Delivery: 15 days
#107

Z6 240 54 47 OR SMS18 BOOT RUBBER RUBBER END PIECE

Z6 240 54 47 OR SMS18 BOOT RUBBER RUBBER END PIECE

12 pieces Delivery: 15 days
#108

Z6 5310 024682 GASKET WASHER FLATE

Z6 5310 024682 GASKET WASHER FLATE

4 pieces Delivery: 15 days
#109

Z6 MISC 775 97 11 BOOT RUBBER

Z6 MISC 775 97 11 BOOT RUBBER

12 pieces Delivery: 15 days
#110

LV2ICVS 765 10 SB521 PACKING ASSY

LV2ICVS 765 10 SB521 PACKING ASSY

2 pieces Delivery: 15 days
#111

LV2ICVS 765 10 SB522 PACKING PERFOMED

LV2ICVS 765 10 SB522 PACKING PERFOMED

2 pieces Delivery: 15 days
#112

LV2ICVS 765 10 948 HOSE

LV2ICVS 765 10 948 HOSE

2 pieces Delivery: 15 days
#113

LV2ICVS 765 10 1079 GASKET SPECIAL

LV2ICVS 765 10 1079 GASKET SPECIAL

2 pieces Delivery: 15 days
#114

LV2ICVS 765 10 1823 RETAINER PACKING

LV2ICVS 765 10 1823 RETAINER PACKING

2 pieces Delivery: 15 days
#115

LV2ICVS 765 10 1579 PIPE ASSY

LV2ICVS 765 10 1579 PIPE ASSY

4 pieces Delivery: 15 days
#116

LV2ICVS 765 10 747 GASKET

LV2ICVS 765 10 747 GASKET

2 pieces Delivery: 15 days
#117

LV2ICVS 765 10 2381 GASKET

LV2ICVS 765 10 2381 GASKET

4 pieces Delivery: 15 days
#118

LV2ICVS 765 10 1408 GASKET

LV2ICVS 765 10 1408 GASKET

2 pieces Delivery: 15 days
#119

LV2ICVS 765 10 1121 GASKET

LV2ICVS 765 10 1121 GASKET

2 pieces Delivery: 15 days
#120

LV2 ICVS 4720002838 40U18 1 3 13 HOSE 18MM DIA 5 MM THICKNESS 10235671

LV2 ICVS 4720002838 40U18 1 3 13 HOSE 18MM DIA 5 MM THICKNESS 10235671

940 mm Delivery: 15 days
#121

LV2 RCV 40U12 1 POINT 3 13 10 HOSE 12 MM DIA 4 MM THICKNESS 10235314

LV2 RCV 40U12 1 POINT 3 13 10 HOSE 12 MM DIA 4 MM THICKNESS 10235314

820 mm Delivery: 15 days
#122

LV2RCV 40U16 1 3 13 HOSE 100 MM 16 MM DIA 5 MM THICKNESS

LV2RCV 40U16 1 3 13 HOSE 100 MM 16 MM DIA 5 MM THICKNESS

60 mm Delivery: 15 days
#123

LV2 RCV 40U18 0 POINT7 7 HOSE 18MM DIA X 5MM THK 10239134

LV2 RCV 40U18 0 POINT7 7 HOSE 18MM DIA X 5MM THK 10239134

60 mm Delivery: 15 days
#124

LV2 RCV 4720002801 40U 22 1 3 13 HOSE 22 MM DIA 5 MM THICKNESS

LV2 RCV 4720002801 40U 22 1 3 13 HOSE 22 MM DIA 5 MM THICKNESS

420 mm Delivery: 15 days
#125

LV2 ICVS 4720002802 40U25 1 POINT 3 13 HOSE 25 MM DIA 5 6 MM THICKNESS 10235837

LV2 ICVS 4720002802 40U25 1 POINT 3 13 HOSE 25 MM DIA 5 6 MM THICKNESS 10235837

540 mm Delivery: 15 days
#126

LV2 ICVS 40U32 0 POINT7 7 OBLIQUE1 HOSE 32MM DIA X 4POINT5MM THICKNESS 10239176

LV2 ICVS 40U32 0 POINT7 7 OBLIQUE1 HOSE 32MM DIA X 4POINT5MM THICKNESS 10239176

600 mm Delivery: 15 days
#127

LV2 ICVS 40U42 1 POINT 3 13 HOSE 42MM DIA X 7MM 1 POINT 00 10 POINT 5M 10238131

LV2 ICVS 40U42 1 POINT 3 13 HOSE 42MM DIA X 7MM 1 POINT 00 10 POINT 5M 10238131

2,100 mm Delivery: 15 days
#128

LV2 ICVS 40U42 0 3 HOSE TY005 6016 80

LV2 ICVS 40U42 0 3 HOSE TY005 6016 80

1,140 mm Delivery: 15 days
#129

LV2 ICVS 40U90 0 POINT 1 1 HOSE 90MM DIA 4 5 MM THK 10257778

LV2 ICVS 40U90 0 POINT 1 1 HOSE 90MM DIA 4 5 MM THK 10257778

800 mm Delivery: 15 days

Categories 22

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

GST Registration

2

Permanent Account Number (PAN)

3

Experience certificates for prior goods-supply projects

4

Financial statements / turnover evidence

5

EMD payment proof (if specified in final terms)

6

Technical bid documents demonstrating capability to supply goods

7

OEM authorizations or supplier affiliations (if required)

8

Any prior contract performance certificates

Frequently Asked Questions

Key insights about RAJASTHAN tender market

How to bid on Indian Army goods supply tender in Sri Ganganagar 2026

Bidders should prepare GST, PAN, experience certificates, and financial statements; submit a bid covering all costs. The tender allows a 25% quantity variation at contracted rates, with delivery timing from the original DO date and a minimum 30-day extension. Ensure documentation aligns with government procurement rules.

What documents are required for the Indian Army procurement in Rajasthan

Required documents include GST registration, PAN, experience certificates for similar goods-supply projects, financial statements, and proof of EMD payment if applicable. Technical bid documents and OEM authorizations may be requested. Provide these with the bid to demonstrate capability and compliance.

What are the delivery terms for the 129-item goods tender in Sri Ganganagar

Delivery starts from the last date of the original delivery order. If quantities are increased, the extended delivery period is calculated as (additional quantity/original quantity) × original period, with a minimum of 30 days. Ensure planning buffers for potential extensions during execution.

What is the scope of supply for the Indian Army tender in Rajasthan

The scope is strictly 'Only supply of Goods' with all costs included in the bid price. There are no installation or service components specified; bidders must ensure raw-material and logistics readiness to deliver by the specified timelines.

How does the 25% quantity extension clause affect bidding for the Army tender

Bid quantities may be increased or decreased by up to 25% at contracted rates. Delivery timelines may extend accordingly, calculated by the provided formula, ensuring bidders plan scalable production and logistics to accommodate potential order fluctuations.

What are the eligibility criteria for defense goods supply tenders in Rajasthan

Eligible bidders should demonstrate prior government/defense sector experience, adequate financial strength, and capability to supply goods across the 129-item catalog. Maintain compliance with procurement terms, maintain quality standards, and be prepared for rigorous documentation checks.

What documentation proves compliance with Indian Army procurement terms in Sri Ganganagar

Submit GST, PAN, experience certificates, financial statements, and any applicable OEM authorizations. Include technical bid documents and proof of EMD if required. Documentation must clearly show capability to supply goods in the specified location within the delivery window.

When is the bid submission window for the Sri Ganganagar goods tender 2026