Progress
The procurement involves the Panchayati Raj Department Bihar for a RO Plant with Genset and Trolley (Q3) to be delivered to Begusarai, Bihar 848201. The tender data lacks explicit quantities and a quoted value. Core elements include a flexible quantity clause (+/- 25%), and a delivery framework tied to the original delivery period with extensions. Pre-dispatch inspection is required, with inspection charges borne by the Buyer. Installation and commissioning, if within scope, occur at the buyer's designated site. The tender emphasizes compliance with contractual inspection protocols and the right to reject goods at consignee location post-delivery. A unique risk feature is the option clause governing quantity and delivery timelines across the contract duration. This tender targets suppliers familiar with government RO-procurement and on-site utility equipment deployment.
RO Plant with Genset and Trolley (Q3) – exact technical specs not provided in tender data
Pre-dispatch inspection requirement and associated costs borne by Buyer
Delivery address to be provided by Buyer; installation/commissioning if in scope
Option clause allows +/-25% quantity variation at contracted rates
Delivery period calculations include minimum 30 days extension
Delivery quantity may change by up to 25% during and after contract
Pre-dispatch inspection by Buyer or nominated agency; inspection fees on Buyer
Need to provide undertaking on financial standing; not under liquidation
Not specified in data; bidders should verify terms during bid submission
Delivery period begins from date of original delivery order; extension rules apply under option clause
Not stated; potential LDs would be defined in final contract; bidders should seek clarity during bid
Not under liquidation or bankruptcy; provide undertaking
Experience in supplying similar RO plants or government utility equipment
Financial solvency to meet bid requirements; provide financial statements
Quantity
1
Bid Type
Two Packet Bid
Bid Validity
105 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Min. Avg. Annual Turnover
3
Past Performance
20 %
Warranty Period
1 years
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
RO Plant with Genset and Trolley (Q3)
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Begusarai
Delivery Pincodes
851211
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Sharvan Kumar | 851211,PANCHAYAT OFFICE KATARMALA SOUTH | Begusarai | Bihar | 851211 | 1 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates for similar RO plant projects
Financial statements (audited if available)
Evidence of EMD/security deposit as applicable
Technical bid documents and compliance statements
OEM authorization or dealership/distribution certificates (if applicable)
Key insights about BIHAR tender market
Bidders must submit GST and PAN, along with experience certificates and financial statements. Ensure OEM authorization if required, and provide an undertaking on financial standing. The tender allows +/-25% quantity variation and includes pre-dispatch inspection at buyer's cost. Delivery terms hinge on the original order date with possible extensions.
Submit GST certificate, PAN card, experience certificates for similar RO projects, audited financial statements, EMD proof, technical bid and compliance statements, and OEM authorizations if applicable. Ensure all documents are aligned with terms and are uploaded with the bid.
Delivery begins from the original delivery order date; option clause allows a 25% quantity increase/decrease. If quantity changes, extended delivery time uses (Increased quantity ÷ Original quantity) × Original delivery period, with a 30-day minimum extension.
Pre-dispatch inspection is mandatory, conducted by Buyer/Consignee or nominated external agency. Fees are borne by the Buyer. The seller provides in-house testing facilities; the consignee reserves the right to reject on arrival despite prior inspection.
Bidders must avoid liquidation or bankruptcy; provide an undertaking. Demonstrated capability through prior RO plant or government procurement experience is required, along with financial stability documentation and relevant certifications as applicable to RO systems.
The tender data does not disclose the exact EMD amount. Bidders should verify EMD requirements during bid submission and prepare funds or an acceptable guarantee accordingly, ensuring compliance with state procurement norms.