Bid Publish Date
01-Sep-2026, 10:15 pm
Bid End Date
22-Sep-2026, 5:00 pm
Location
Progress
Bhilai Steel Plant, a unit of Steel Authority of India Limited, invites bids for refractory management of BF cast house runners at BSP No.7, DURG, CHHATTISGARH. The procurement covers 27 material sets for refractory management and 2 initial installation sets using PCPF blocks with ACT charges, totaling 29 sets. The delivery schedule spans from 31.03.2027 to 31.12.2029, with separate windows for material repair (working lining) and installation, requiring BOM break-up and application charges from the selected bidder.
This tender emphasizes on-site installation using PCPF blocks and includes ACT (application charges) as a separate line item. The scope aggregates cast house refractory work, including repairs on working lining and subsequent initial installations, aligning with BSP’s maintenance plan for BF No. 7. The contract structure emphasizes BOM transparency and compliance with GEM/ATC attachments.
Total tendered quantity: 29 sets
Material sets: 27 for repair/working lining
Initial installation sets using PCPF block: 2
Material description: Refractory management of BF cast house runners
Material codes: UCS 71511000000004 (RMC) and 715110000000009 (ACT charges)
Delivery period windows: 31.03.2027, 31.03.2028, 31.03.2029, 31.12.2029
Break-up to be provided by bidder with BOM and ACT charges
Delivery windows and milestone dates require strict adherence
Bidder must provide BOM break-up and separate ACT charges
Review attached GEM ATC and drawings for compliance and penalties
Payment terms are defined in GEM ATC; ensure BOM and ACT charges are itemized separately and submitted with the bid
Delivery windows span from 31.03.2027 to 31.12.2029 with milestone-based scheduling; adherence is mandatory
Penalties, if any, are described in the GEM ATC and attached terms; bidders must consult the ATC for LD details
Experience in refractory management for blast furnaces or similar steel plant environments
Demonstrated ability to provide BOM break-up and separate ACT charges
Financial capacity to undertake multi-year delivery commitments up to 29 sets
Quantity
29
Category
Castable Along with PCPF Blocks for Initial Installation
Bid Type
Two Packet Bid
Bid Validity
90 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Castable Along with PCPF Blocks for Initial Installation , REFRACTORY MANAGEMENT OF CAST HOUSE RUNNER
Advisory Bank
State Bank of India
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
2
Delivery Locations
1
Delivery Cities
Durg
Delivery Pincodes
490001
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| SANJAY TIWARI | 490001,Refractory Stores, Bhilai Steel Plant. | Durg | Chhattisgarh | 490001 | - | 2 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
GST certificate
PAN card
Experience certificates related to refractory management or BF cast house work
Financial statements for capability demonstration
EMD/Security deposit as per GEM ATC (exact amount in ATC)
Technical bid documents showing BOM break-up and material details
OEM authorizations (if applicable) and service/support certificates
Drawings and terms in GEM & Buyer Added ATC attachments
Key insights about CHHATTISGARH tender market
Bidders must submit GST, PAN, experience certificates, and financials along with a BOM break-up and ACT charges. The tender covers 29 sets (27 material, 2 installation) with delivery windows up to 31.12.2029. Ensure BOM transparency and review GEM ATC for penalties and schedules.
Required docs include GST registration, PAN, experience certificates in BF refractory work, financial statements, EMD per ATC, technical bid with BOM, OEM authorizations (if applicable), and drawings/terms from GEM ATC attachments.
Delivery milestones include 2 initial installation sets using PCPF blocks by 31.03.2027 and subsequent refractory management deliveries by 31.03.2028, 31.03.2029, and ACT charges by 31.12.2029, with BOM break-up required.
While explicit standards are not listed in the data, bidders must refer to attached detailed terms and drawings in the GEM ATC and ensure compliance with project-specific requirements for BF cast house work.
The exact EMD amount is not disclosed here; bidders should consult GEM ATC to confirm the EMD value, submission method (DD/online), and validity period aligned with tender timelines.
Scope comprises 2 initial installation sets using PCPF blocks with ACT charges and 27 material sets for repair/working lining, totaling 29 sets with separate ACT charges as per BOM.
Detailed drawings and Buyer ATC terms are in the GEM portal attachments; bidders must download and study the complete Terms & Conditions, BOM format, and ACT clauses before submission.
Bidders must provide a line-item BOM showing material costs for 27 sets plus separate ACT charges for 2 installation sets, with quantifiable unit rates and delivery milestones as per the ATC attachments.