Bid Publish Date
10-Sep-2026, 1:40 pm
Bid End Date
21-Sep-2026, 2:00 pm
Location
Progress
Bharat Heavy Electricals Limited invites bids for ERW PIPE with multiple OD and wall thickness configurations under API5LGRB, including 219.10x4.00, 406.40x4.80, 273.10x4.00, 273.10x6.40, 457.00x4.80, 660.00x6.40, and 914.40x10.00, through an unpriced bid framework. The tender encompasses 7 items, with quantities and exact specifications not disclosed in the snippet, and emphasizes delivery options via the option clause. This procurement is managed by the Department of Heavy Industry, with focus on standard ERW pipe production aligned to API5LGRB. The contract allows quantity adjustments up to 25% during and after award, at contracted rates, and requires compliance with GST and vendor documentation norms.
ERW PIPE OD 219.10X4.00 API5LGRB
ERW PIPE OD 406.40X4.80 API5LGRB
ERW PIPE OD 273.10X4.00 API5LGRB
ERW PIPE OD 273.10X6.40 API5LGRB
ERW PIPE OD 457.00X4.80 API5LGRB
ERW PIPE OD 660.00X6.40 API5LGRB
ERW PIPE OD 914.40X10.00 API5LGRB
Unpriced bid framework for all items
Quantity adjustment up to 25% both pre- and post-award
GST payable by bidder with reimbursement as actuals or lower quoted rate
PAN, GSTIN, cancelled cheque, and EFT mandate required with bid
Contractor remains liable for subcontracted work; no assignment without consent
Termination rights for material breach or delivery failure
GST handling by bidder; reimbursement as actuals or lower quoted rate; no specific payment schedule provided
Delivery period tied to last date of original delivery order; option-based extension mechanics with minimum 30 days
Termination for non-delivery or defective material; no explicit LD rate provided in data
Must comply with GST and tax documentation
Submit PAN, GSTIN, cancelled cheque, and EFT mandate
No sub-contracting without Buyer consent; joint liability retained
Quantity
615
Category
2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
1 - 159383000000 - ERW PIPE OD 219.10X4.00 API5LGRB - as per unpriced bid , 2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid , 3 - 159386010000 - ERW PIPE OD 273.10X4.00 API5LGRB - as per unpriced bid , 4 - 159386020000 - ERW PIPE OD 273.10X6.40 API5LGRB - as per unpriced bid , 5 - 159386070000 - ERW PIPE OD 457.00X4.80 API5LGRB - as per unpriced bid , 6 - 159386150000 - ERW PIPE OD 660.00X6.40 API5LGRB - as per unpriced bid , 7 - 159386370000 - ERW PIPE OD 914.40X10.00 AP15LGRB - as per unpriced bid
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
90
Delivery Locations
1
Delivery Cities
Visakhapatanam
Delivery Pincodes
530012
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Purusottam Marndi | 530012,Bharat Heavy Electricals Limited Heavy Plates and Vessels Plant (A Government of India Enterprise) Visakhapatnam 530012 (AP), India. | Visakhapatanam | Andhra Pradesh | 530012 | 75 | 90 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
1 - 159383000000 - ERW PIPE OD 219.10X4.00 API5LGRB - as per unpriced bid
1 - 159383000000 - ERW PIPE OD 219.10X4.00 API5LGRB - as per unpriced bid
2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid
2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid
3 - 159386010000 - ERW PIPE OD 273.10X4.00 API5LGRB - as per unpriced bid
3 - 159386010000 - ERW PIPE OD 273.10X4.00 API5LGRB - as per unpriced bid
4 - 159386020000 - ERW PIPE OD 273.10X6.40 API5LGRB - as per unpriced bid
4 - 159386020000 - ERW PIPE OD 273.10X6.40 API5LGRB - as per unpriced bid
5 - 159386070000 - ERW PIPE OD 457.00X4.80 API5LGRB - as per unpriced bid
5 - 159386070000 - ERW PIPE OD 457.00X4.80 API5LGRB - as per unpriced bid
6 - 159386150000 - ERW PIPE OD 660.00X6.40 API5LGRB - as per unpriced bid
6 - 159386150000 - ERW PIPE OD 660.00X6.40 API5LGRB - as per unpriced bid
7 - 159386370000 - ERW PIPE OD 914.40X10.00 AP15LGRB - as per unpriced bid
7 - 159386370000 - ERW PIPE OD 914.40X10.00 AP15LGRB - as per unpriced bid
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | 1 - 159383000000 - ERW PIPE OD 219.10X4.00 API5LGRB - as per unpriced bid | 1 - 159383000000 - ERW PIPE OD 219.10X4.00 API5LGRB - as per unpriced bid | 75 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 2 | 2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid | 2 - 159385040000 - ERW PIPE OD 406.40X4.80 API5LGRB - as per unpriced bid | 225 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 3 | 3 - 159386010000 - ERW PIPE OD 273.10X4.00 API5LGRB - as per unpriced bid | 3 - 159386010000 - ERW PIPE OD 273.10X4.00 API5LGRB - as per unpriced bid | 90 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 4 | 4 - 159386020000 - ERW PIPE OD 273.10X6.40 API5LGRB - as per unpriced bid | 4 - 159386020000 - ERW PIPE OD 273.10X6.40 API5LGRB - as per unpriced bid | 50 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 5 | 5 - 159386070000 - ERW PIPE OD 457.00X4.80 API5LGRB - as per unpriced bid | 5 - 159386070000 - ERW PIPE OD 457.00X4.80 API5LGRB - as per unpriced bid | 50 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 6 | 6 - 159386150000 - ERW PIPE OD 660.00X6.40 API5LGRB - as per unpriced bid | 6 - 159386150000 - ERW PIPE OD 660.00X6.40 API5LGRB - as per unpriced bid | 50 | mtrs | bhel.hpvp.consignee2 | 90 | |
| 7 | 7 - 159386370000 - ERW PIPE OD 914.40X10.00 AP15LGRB - as per unpriced bid | 7 - 159386370000 - ERW PIPE OD 914.40X10.00 AP15LGRB - as per unpriced bid | 75 | mtrs | bhel.hpvp.consignee2 | 90 |
Discover companies most likely to bid on this tender
PAN Card copy
GSTIN copy
Cancelled cheque copy
EFT Mandate copy certified by bank
GST/Tax compliance documents (as applicable)
Any vendor code creation documents per terms
Bidders must submit PAN, GSTIN, Cancelled Cheque, and EFT Mandate along with bid. Ensure GST is calculated correctly and note that quantities may vary up to 25% under the option clause. Delivery timelines depend on the original order and extended periods per clause.
Required documents include PAN Card, GSTIN, Cancelled Cheque, and EFT Mandate certified by bank. These must accompany the bid for vendor code creation, along with any GST-related compliance certificates and standard company registrations.
Technical scope covers seven OD/thickness configurations: 219.10x4.00, 406.40x4.80, 273.10x4.00, 273.10x6.40, 457.00x4.80, 660.00x6.40, 914.40x10.00 with API5LGRB designation; exact tolerances not disclosed in extract.
Delivery starts from the last date of the original delivery order. If options are exercised, additional time is calculated as (Extended quantity ÷ Original quantity) × Original delivery period, minimum 30 days; contract may extend up to original delivery period.
EMD amount is not disclosed in the available data; bidders should assume standard field practice and verify during bidder code creation and bid submission as per terms.
Buyer may terminate the contract by written notice for material non-compliance, inability to deliver within the stipulated period, or buyer-creditor related insolvency events; contract binds seller and any sub-contractors to joint liability.
GST is the bidder’s responsibility; reimbursement is either actual GST or quoted GST rate, whichever is lower, subject to the maximum bidder-provided percentage; no automatic guarantee of GST refunds beyond statutory rules.
The purchaser can increase/decrease quantities up to 25% during placement and currency; increases apply at contracted rates; extended delivery time follows the specified formula with a minimum 30 days.