NTPC Limited invites supply of Tapered Roller Bearing - 9220/9285 Cup & Cone type with SS cage, for a total of 14 units. Estimated value listed as ₹200,000.00. Location is currently not disclosed, and the procurement focuses on the supply of goods only. The accepted brands should be reputable equivalents to NTN, SKF, Timken, Austin, NBC. Key differentiator includes mandatory ISO 9001 certification for bidder or OEM. Tender emphasizes material traceability via Material Test Certificates and supplier eligibility through standard documentation. Unique clause allows a ±25% quantity variation under option and extended delivery time with a calculated formula.
Option to adjust quantity by ±25% at contract and during execution with formula-based delivery extension
Mandatory Material Test Certificate and ISO 9001 certification for bidder or OEM
Supply of 9220/9285 Cup & Cone tapered roller bearings with SS cage; 14 units
Payment terms not explicitly stated; ensure to confirm with procurement; standard practice may apply after delivery and inspection
Delivery period linked to option clause; additional time = (increased quantity / original quantity) × original delivery period, minimum 30 days
Not explicitly listed; penalties to be defined in contract based on delivery/compliance failures; ensure compliance with Material Test Certificate acceptance
ISO 9001 certification in bidder OR OEM
Experience supplying tapered roller bearings to large-scale projects
GSTIN active and PAN card submitted; EFT mandate and cancelled cheque available
Quantity
14
Bid Type
Single Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Tapered Roller Bearing (V2) Conforming to IS 12102 (Q3)
Payment Timelines
Payments shall be made to the Seller within 40 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Patna
Delivery Pincodes
803213
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Aditya Anand | 803213,NTPC Barh Super Thermal Power Project, PO- NTPC Campus Barh, Distt- Patna,State-Bihar | Patna | Bihar | 803213 | 14 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
02-Nov-2026, 6:30 am
Opening Date
03-Nov-2026, 6:30 am
Discover companies most likely to bid on this tender
PAN Card
GSTIN
Cancelled Cheque
EFT Mandate certified by Bank
Material Test Certificates
ISO 9001 certificate (bidder or OEM)
OEM authorization (if manufacturer is not bidder)
Company financial statements (as required by tender)
Any additional certificates requested in ATC/Corrigendum
Key insights about BIHAR tender market
Bidders must meet ISO 9001 certification requirements for bidder or OEM, submit PAN, GSTIN, cancelled cheque, and EFT mandate. Include Material Test Certificates with every supply and comply with the ±25% option quantity clause. Delivery terms hinge on the option clause and the minimum 30 days extension rule.
Submit PAN, GSTIN, Cancelled Cheque, and EFT Mandate; attach Material Test Certificates; provide ISO 9001 certification (bidder or OEM) and any OEM authorizations. Include company financials if requested and ensure upload of ATC documents.
Bearings required are 9220/9285 Cup & Cone with SS cage. Quantity is 14 nos. Brands acceptable are NTN, SKF, Timken, Austin, NBC or equivalents. Documentation requires Material Test Certificates and ISO 9001 compliant suppliers.
Delivery time follows an option clause permitting ±25% quantity adjustment. Additional time is calculated as (Increased quantity / Original quantity) × Original delivery period, with a minimum of 30 days; extension possible up to the original delivery period.
Items carry a warranty of 12 months from commissioning or 18 months from supply, whichever occurs earlier. Material Test Certificates must accompany each supply; buyer laboratory results govern acceptance and any non-conformity penalties.
Preferred brands include NTN, SKF, Timken, Austin, NBC or reputed equivalents. Bidder must demonstrate capability to supply compatible cup & cone bearings with SS cage as specified.
Estimated value is ₹200,000.00 for a total of 14 units of tapered roller bearings (9220/9285 Cup & Cone) with SS cage; ensure quote includes all costs as scope is goods supply only.
Provide a valid ISO 9001 certificate for either the bidder or the OEM offering the bearings. Documentation should be verifiable and up-to-date; ensure certificate scope covers bearing manufacturing or supply processes.