TenderDekho Logo
Closed GEM

Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited Obra BTPS Mills Strengthening Tender 2026 Lucknow UP - Repair & Maintenance Phase-2 2607918

Bid Publish Date

02-Nov-2026, 6:29 pm

Bid End Date

24-Nov-2026, 5:00 pm

Value

₹26,07,918

Progress

Issue02-Nov-2026, 6:29 pm
Corrigendum09-Nov-2026
AwardPending

Tender Overview

Organization: Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), Lucknow. Procured service involves Repair, Maintenance, and Installation for the Strengthening of Mills (Phase-2) of Obra Thermal Power Plant units 9C, 9D, 10C, 10D, 11C & 11D (3x200 MW units). Location: Sonbhadra, Uttar Pradesh (231205). Estimated Value: ₹2,607,918.00. Scope includes field service, installation support, and associated maintenance tasks for milling systems at Obra BTPS. Tender features a 25% option clause for quantity or duration variation at contract execution. This procurement targets experienced service providers capable of executing plant mill-strengthening work within defined timelines, with a potential scope expansion up to a quarter of original value subject to consent. The absence of a BOQ indicates a broad service envelope with emphasis on technical capability and project management. Unique aspect: work aligned with Phase-2 upgrade across multiple 200 MW units at Obra BTPS, under the Energy Department, Uttar Pradesh.

Technical Specifications & Requirements

  • Category: Repair, Maintenance, and Installation of Plant/Systems/Equipments (Version 2) – Thermal Power Plant Mills
  • Scope: Phase-2 strengthening across 9C/9D/10C/10D/11C/11D mills for 3x200 MW units
  • Standards/Compliance: Not specified in available data; bidders should prepare to demonstrate plant overhaul capabilities and safety compliance.
  • Delivery/Installation: Not defined; bidders should propose implementation plan and resource allocation.
  • Experience: Required capability to perform milling equipment strengthening in a thermal power plant environment; no explicit years stated.
  • Pricing/Value: Estimated value ₹2,607,918; 25% scope variation permitted with consent.
  • Delivery Location: Obra Thermal Power Station, Sonbhadra, UP; entry and site procedures to be followed.
  • Documentation: Submit evidence of prior similar projects and safety clearances.

Terms, Conditions & Eligibility

  • EMD: Not specified in data; bidders should confirm prior to bid submission.
  • Quantity/Scope Variation: Up to 25% increase in contract quantity or duration; lumpsum contracts allow scope/value increase with service provider consent.
  • Delivery Timeline: Not explicitly defined; bidders to propose schedule aligned with Obra BTPS timelines.
  • Payment Terms: Not detailed; bidders should seek clarity on milestone-based payments.
  • Documents: GST certificate, PAN, Experience certificates, Financial statements, prior project testimonials, OEM authorizations, technical bids, safety/compliance documents.
  • Other Clauses: ATC document exists; bidders should review uploaded terms for any site- or vendor-specific conditions.

Key Specifications

  • Product/Service: Repair, Maintenance, and Installation of Plant/Systems/Equipments (Version 2) - Thermal Power Plant Mills

  • Units: 9C, 9D, 10C, 10D, 11C, 11D across Obra BTPS (3x200 MW units)

  • Estimated Value: ₹2,607,918

  • Scope Variation: Up to 25% increase in quantity/duration with consent

  • Delivery/Installation: Not specified; require bidder-proposed schedule

  • Standards/Certifications: Not specified in data; show mill-strengthening capability and safety compliance

  • Experience: Demonstrate ability to perform milling system strengthening in thermal plants

Terms & Conditions

  • 25% scope/quantity variation permitted at contract issue

  • Delivery timeline to be defined by bidder with site compliance

  • EMD and documentary submissions to be clarified via ATC and tender terms

Important Clauses

Payment Terms

Not specified in available data; bidders must obtain explicit terms from ATC and LOA.

Delivery Schedule

Not specified; bidders should propose phased delivery aligned with Obra BTPS maintenance windows.

Penalties/Liquidated Damages

Not specified; verify LD provisions in ATC/contract documents.

Bidder Eligibility

  • Proven experience in milling system maintenance within thermal power plants

  • Capability to operate at Obra BTPS location with site access procedures

  • Financial capacity to manage projects near ₹2.6 million and potential 25% scope variation

Advertisement

Authority & Contact

Organization

Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (uprvunl) Lucknow

Office Name

Lucknow

Grievance Contact

[email protected]

Tender Data

Bid Details

Quantity

1

Bid Type

Two Packet Bid

Bid Validity

180 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

3 Days

Preference & Exemptions

EMD Required

Yes

MII Compliance

Yes

MSE Purchase Preference

No

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Min. Avg. Annual Turnover

26

Experience Required

5 Year (s)

Arbitration Clause

No

Mediation Clause

Yes (Mediation clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 mediation clause should not be routinely included in contracts and pre- litigation mediation can be taken up without any such clause also

Additional Tender Data

Commercial Details

Tender Category

Service

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

Repair, Maintenance, and Installation of Plant/ Systems/Equipments (Version 2) - Thermal Power Plant; Strengthening of Mills (Phase-2) of 9C, 9D, 10C, 10D, 11C &11D, 3X200 MW units of Obra BTPS; Service Provider

Advisory Bank

State Bank of India

Delivery Details

Delivery Locations

1

Delivery Cities

Sonbhadra

Delivery Pincodes

231219

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Rajeev Kumar Jha231219,Obra Thermal Power PlantSonbhadraUttar Pradesh231219Project / Lumpsum Based-Estimated Cost of Spare/Consumable s/Items on Reimbursement basis in Rs (please input 0 if not applicable) : 0

Authority Records

ENERGY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 9

GeM-Bidding-10116423.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Categories 5

Corrigendum Updates

1 Update
#1

Update

09-Nov-2026

Required Documents

1

GST Registration Certificate

2

Permanent Account Number (PAN) Card

3

Experience Certificates from similar phase-2 mill strengthening projects

4

Financial Statements (last 2-3 years)

5

EMD/Security Deposit documents (as applicable per final tender terms)

6

Technical Bid detailing methodology and resource plan

7

OEM Authorization / Vendor Authorization (if applicable)

8

Safety & Quality Certifications (as required by ATC)

Frequently Asked Questions

Key insights about UTTAR PRADESH tender market

How to bid for the Obra BTPS milling strengthening tender in UP 2026?

Submit the technical bid with evidence of prior phase-2 mill maintenance work, provide GST and PAN details, financial statements, and OEM authorizations. Review ATC for quantities, EMD requirements, and scope variation up to 25%. Prepare a project plan with site access and safety compliance.

What documents are required for UP government tender in Sonbhadra?

Required documents include GST certificate, PAN card, 2-3 years financial statements, experience certificates for similar work, technical bid, OEM authorizations, and safety certifications. Submit EMD documents as specified in ATC and ensure alignment with the scope of Obra BTPS Phase-2.

What standards or certifications are needed for Obra Mills maintenance bid 2026?

Demonstrate capability to perform milling system strengthening in a thermal plant; no explicit standards listed. Provide safety certifications, OEM authorizations, and prior ISI/ISO-adjacent quality assurances if available. Ensure compliance with site safety and commissioning procedures.

When is the delivery timeline required for the Obra Phase-2 project?

The tender data does not specify exact dates. Propose a phased delivery schedule aligned with Obra BTPS maintenance windows, with clear milestones and acceptance criteria in the technical bid.

What is the value and scope variation allowed in this tender?

Estimated value is ₹2,607,918. The buyer may increase contract quantity or duration by up to 25% at issue and after issuance with consent, including scope expansion for lumpsum contracts.

What are the key eligibility criteria for UP power plant maintenance bids?

Eligibility requires proven milling maintenance experience in thermal plants, ability to operate at Obra site, and financial capacity to manage the project plus required documents (GST, PAN, experience certificates, OEM authorizations).

What documents confirm bidder compliance for the Obra Mills tender?

Submit GST, PAN, experience certificates for similar projects, financial statements, EMD documentation, technical bid, and OEM authorizations; ATC may specify additional site-specific requirements and safety clearances.

How to verify EMD and payment terms for the Obra Phase-2 project?

EMD details are not explicitly specified in the data; confirm with the ATC. Payment terms require negotiation; expect milestone-based payments after delivery/completion and site acceptance as per contract terms.