Indian Air Force has released a public tender for Server Type 1 1U 64 Core, Server Type 2 2U 48 Core, Server Type 3 1U 32 Core, Server Type 4 1U 32 Core, Server Type 5 1U 48 Core, Server Type 6 2U 48 Core, SAN Storage with product support for five years, Backup Solution Software and Hardware, SAN Switch, Scale Out NAS, Installation and Commissioning, Integration in WEST DELHI, DELHI. Quantity: 147. Submission Deadline: 27-08-2026 15: 00: 00. Download documents and apply online.
Quantity
147
Category
Server Type 1 1U 64 Core
Bid Type
Two Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
7 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Past Performance
80 %
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Server Type 1 1U 64 Core , Server Type 2 2U 48 Core , Server Type 3 1U 32 Core , Server Type 4 1U 32 Core , Server Type 5 1U 48 Core , Server Type 6 2U 48 Core , SAN Storage with product support for five years , Backup Solution Software and Hardware , SAN Switch , Scale Out NAS , Installation and Commissioning , Integration
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
62
Max Delivery Days
168
Delivery Locations
1
Delivery Cities
South West delhi
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | South West delhi | South West delhi | - | - | 37 | 168 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Server Type 1 1U 64 Core
2 X Intel Xeon 6 Performance 6737P, 2.9G, 32C/64T, 24GT/s,144 M cache, Turbo, (270 W) DDR5-6400 or higher with product support for five years
Server Type 2 2U 48 Core
2 X Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5 6400 or higher with product support for five years
Server Type 3 1U 32 Core
2 X Intel Xeon 6 Performance 6724P, 3.6G, 16C/32T, 24GT/s,72M cache, Turbo, (210 W) DDR5-6400 or higher with product support for five years
Server Type 4 1U 32 Core
2 x Intel Xeon 6 Performance 6517P, 3.2G, 16C/32T, 24GT/s,72M cache, Turbo, (190 W) DDR5-6400 or higher with product support for five years
Server Type 5 1U 48 Core
2 x Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5-6400 or higher with product support for five years
Server Type 6 2U 48 Core
2 x Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5-6400 with NVIDIA H200 NVL, PCIe, 450W, 141GB Passive or higher with product support for five years
SAN Storage with product support for five years
18 X 7.68TB NVMe SED NON-FIPS TLC SSD with dual drive protection with product support of 5 years
Backup Solution Software and Hardware
with minimum 1 PB logical capacity with product support for five years
SAN Switch
24 port 64Gb FC Switch with product support for five years
Scale Out NAS
SO NAS Node based with minimum 2 nodes to deliver 200 TB of usable capacity with product support for five years
Installation and Commissioning
Installation and Commissioning of hardware components in IAF Data Centers
Integration
Integration of IMMOLS Upgraded Application after successful installation and commissioning of Hardware Components in IAF data Centers
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Server Type 1 1U 64 Core | 2 X Intel Xeon 6 Performance 6737P, 2.9G, 32C/64T, 24GT/s,144 M cache, Turbo, (270 W) DDR5-6400 or higher with product support for five years | 37 | pieces | dimmols | 168 | |
| 2 | Server Type 2 2U 48 Core | 2 X Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5 6400 or higher with product support for five years | 8 | pieces | dimmols | 168 | |
| 3 | Server Type 3 1U 32 Core | 2 X Intel Xeon 6 Performance 6724P, 3.6G, 16C/32T, 24GT/s,72M cache, Turbo, (210 W) DDR5-6400 or higher with product support for five years | 35 | pieces | dimmols | 168 | |
| 4 | Server Type 4 1U 32 Core | 2 x Intel Xeon 6 Performance 6517P, 3.2G, 16C/32T, 24GT/s,72M cache, Turbo, (190 W) DDR5-6400 or higher with product support for five years | 5 | pieces | dimmols | 168 | |
| 5 | Server Type 5 1U 48 Core | 2 x Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5-6400 or higher with product support for five years | 30 | pieces | dimmols | 168 | |
| 6 | Server Type 6 2U 48 Core | 2 x Intel Xeon 6 Performance 6527P, 3.0G, 24C/48T, 24GT/s,144 M cache, Turbo, (255 W) DDR5-6400 with NVIDIA H200 NVL, PCIe, 450W, 141GB Passive or higher with product support for five years | 4 | pieces | dimmols | 168 | |
| 7 | SAN Storage with product support for five years | 18 X 7.68TB NVMe SED NON-FIPS TLC SSD with dual drive protection with product support of 5 years | 5 | pieces | dimmols | 168 | |
| 8 | Backup Solution Software and Hardware | with minimum 1 PB logical capacity with product support for five years | 5 | pieces | dimmols | 168 | |
| 9 | SAN Switch | 24 port 64Gb FC Switch with product support for five years | 14 | pieces | dimmols | 168 | |
| 10 | Scale Out NAS | SO NAS Node based with minimum 2 nodes to deliver 200 TB of usable capacity with product support for five years | 2 | pieces | dimmols | 168 | |
| 11 | Installation and Commissioning | Installation and Commissioning of hardware components in IAF Data Centers | 1 | each | dimmols | 196 | |
| 12 | Integration | Integration of IMMOLS Upgraded Application after successful installation and commissioning of Hardware Components in IAF data Centers | 1 | each | dimmols | 316 |
Extended Deadline
27-Aug-2026, 9:30 am
Opening Date