TenderDekho Logo
Closed GEM

Indian Army Leh Procurement 28-item Supply Bundle 2026 (ISD, Accessory, Electrical) - Department of Military Affairs

Bid Publish Date

10-Aug-2026, 8:43 pm

Bid End Date

21-Aug-2026, 9:00 pm

Progress

Issue10-Aug-2026, 8:43 pm
AwardPending

Key Highlights

  • Organization-specific brand or OEM requirements not disclosed in available data
  • Technical certifications or standards are not specified; ATC might contain applicable criteria
  • 25% quantity variation option during bidding and contract execution
  • Delivery timeline linked to last delivery order date with calculable extensions

Tender Overview

The Indian Army, Department of Military Affairs, seeks a 28-item supply bundle for delivery to Leh, Jammu & Kashmir (194101). The BOQ comprises items ranging from 50 W flood lights to server racks and office fittings, with no explicit technical specs disclosed. The tender includes an option clause permitting a ±25% quantity variation at contracted rates and a delivery window linked to the last delivery order. The competition hinges on supplier capacity to meet bulk procurement while honoring the extended delivery framework. Unique aspects include the mandatory adherence to the purchaser’s option clause and the absence of defined item specifications in the public data, signaling strict compliance upon bid submission.

Technical Specifications & Requirements

  • No explicit technical specifications are published in the tender data.
  • BOQ contains 28 items with unspecified quantities and units.
  • Option Clause: quantity may be increased/decreased by up to 25% of bid/contract quantity.
  • Delivery period: starts from the last date of the original delivery order; extended period follows the option exercise with a minimum extension of 30 days.
  • If original delivery is <30 days, the extension equals the original delivery period; otherwise, extension scales with the formula: (Increased quantity ÷ Original quantity) × Original delivery period.
  • The ATC document is uploaded by the buyer; no product-specific standards are listed in the accessible data.

Terms, Conditions & Eligibility

  • Quantity variation permitted up to 25% during contract execution.
  • Delivery timeline to be calculated per the option clause with a minimum extension of 30 days.
  • ATC terms are provided in an uploaded document; specific EMD, validation, or warranty requirements are not disclosed in the public data.
  • Bidders must comply with the option clause and adjust delivery accordingly.
  • No explicit EMD amount or payment terms are stated in the publicly available tender data; bidders should review the ATC document for exact conditions.

Key Specifications

  • Item names and categories derived from BOQ: 28 total items (specific names not disclosed)

  • Estimated value not disclosed; no item-level quantities published publicly

  • EMD: not specified in public data; to be confirmed in ATC

  • Experience: prior procurement of similar goods recommended (not specified)

  • Quality/ compliance: no explicit standards listed in data; ATC may specify

Terms & Conditions

  • Key term: 25% quantity variation allowed at contract; plan for adjustments

  • Key term: delivery period starts after original delivery order; extensions via option clause

  • Key term: ATC document uploaded by buyer; review for exact requirements and penalties

Important Clauses

Delivery Extension Clause

Extended delivery time calculated as (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days

Option to Increase/Decrease Quantities

Purchaser may adjust quantity up to 25% during contract and currency of contract at contracted rates

ATC Document Access

Buyer-uploaded ATC document governs specific terms, standards, and submission requirements

Bidder Eligibility

  • Experience in supplying 28-item bulk procurement with similar categories

  • Ability to meet 25% quantity variation within contract periods

  • Compliance with ATC terms and Leh, J&K delivery requirements

Authority & Contact

Organization

Indian Army

Office Name

Not disclosed yet

Grievance Contact

[email protected]

Tender Data

Bid Details

Quantity

841

Category

Cartridge 78A

Bid Type

Two Packet Bid

Bid Validity

30 (Days)

Bid Type

Service

Evaluation

Item wise evaluation

Inspection Required

No

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

No

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

Yes

Startup Exemption/Relaxation

Yes

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Item Category

Cartridge 78A , Dettol Handwash Refill , 6U Server Rack with Accessories , Extension Board 16 AMP , Router Wifi Stand , Distribution Panel with Industrial Socket and Plug , 50 W Flood Light , Fly Catcher , Room Heater , Step Ladder 4ft , Steel Locker Big , File Cabinet 4 Drawer , Rachet Wrench , Sliding Bar T Handle , Flex Board 4 x 4 with frame , Flex Board 6 x 6 with Frame , Spiral Binding Ring , File Cover Printed , MCB 30 AMP Double Pole , Airwick Refill Machine , Cartridge NPG 59 , File Cabinet , Bamboo 10 ft , Target Paper Fig 11 , Target Paper Fig 12 , Target Tin Sheet Fig 11 , Target Tin Sheet Fig 12 , Patch Paper 1 x 1 inch

Delivery Details

Max Delivery Days

25

Delivery Locations

1

Delivery Cities

Leh

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
-LehLeh--1025-

Authority Records

MINISTRY OF DEFENCEMILITARY AFFAIRS DEPARTMENTINDIAN ARMY

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 5

GeM-Bidding-9736653.pdf

Main Document

BOQ Document

BOQ

BOQ Document

BOQ

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Bill of Quantities (BOQ) 28 Items Sign in for GEM prices

#1

Cartridge 78A

Cartridge 78A

10 nos Delivery: 25 days
#2

Dettol Handwash Refill

Dettol Handwash Refill

10 nos Delivery: 25 days
#3

6U Server Rack with Accessories

6U Server Rack with Accessories

2 set Delivery: 25 days
#4

Extension Board 16 AMP

Extension Board 16 AMP

5 nos Delivery: 25 days
#5

Router Wifi Stand

Router Wifi Stand

2 nos Delivery: 25 days
#6

Distribution Panel with Industrial Socket and Plug

Distribution Panel with Industrial Socket and Plug

1 set Delivery: 25 days
#7

50 W Flood Light

50 W Flood Light

5 nos Delivery: 25 days
#8

Fly Catcher

Fly Catcher

5 nos Delivery: 25 days
#9

Room Heater

Room Heater

4 nos Delivery: 25 days
#10

Step Ladder 4ft

Step Ladder 4ft

2 nos Delivery: 25 days
#11

Steel Locker Big

Steel Locker Big

1 nos Delivery: 25 days
#12

File Cabinet 4 Drawer

File Cabinet

4 nos Delivery: 25 days
#13

Rachet Wrench

Rachet Wrench

4 nos Delivery: 25 days
#14

Sliding Bar T Handle

Sliding Bar T Handle

4 nos Delivery: 25 days
#15

Flex Board 4 x 4 with frame

Flex Board 4 x 4

1 nos Delivery: 25 days
#16

Flex Board 6 x 6 with Frame

Flex Board 6 x 6

1 nos Delivery: 25 days
#17

Spiral Binding Ring

Spiral Binding Ring

1 pkt Delivery: 25 days
#18

File Cover Printed

File Cover Printed

200 nos Delivery: 25 days
#19

MCB 30 AMP Double Pole

MCB 30 AMP Double Pole

20 nos Delivery: 25 days
#20

Airwick Refill Machine

Airwick Refill Machine

2 nos Delivery: 25 days
#21

Cartridge NPG 59

Cartridge NPG 59

3 nos Delivery: 25 days
#22

File Cabinet

File Cabinet

4 nos Delivery: 25 days
#23

Bamboo 10 ft

Bamboo 10 ft

50 nos Delivery: 25 days
#24

Target Paper Fig 11

Target Paper Fig 11

100 nos Delivery: 25 days
#25

Target Paper Fig 12

Target Paper Fig 12

100 nos Delivery: 25 days
#26

Target Tin Sheet Fig 11

Target Tin Sheet Fig 11

100 nos Delivery: 25 days
#27

Target Tin Sheet Fig 12

Target Tin Sheet Fig 12

100 nos Delivery: 25 days
#28

Patch Paper 1 x 1 inch

Patch Paper 1 x 1 inch

100 nos Delivery: 25 days

Categories 28

Required Documents

1

GST registration certificate

2

PAN card

3

Experience certificates validating similar supply work

4

Financial statements (latest annual report or equivalent)

5

EMD/Security deposit documents as per ATC

6

Technical bid documents and compliance statements

7

OEM authorizations or authorized distributorships (where applicable)

Frequently Asked Questions

Key insights about JAMMU AND KASHMIR tender market

How to bid for Indian Army Leh procurement 28-item bundle in 2026?

Bidders should review the uploaded ATC for exact submission requirements, ensure GST, PAN, and experience certificates are ready, and prepare for a potential 25% quantity variation. Delivery terms hinge on the last delivery order date with a minimum 30-day extension, and compliance with any OEM authorizations is essential.

What documents are required for Army equipment tender in Leh?

Submit GST certificate, PAN card, experience certificates for similar supplies, financial statements, EMD/Security deposit per ATC, technical bid, and OEM authorizations where applicable. Ensure all documents align with bidder eligibility criteria and tender terms from the ATC.

What are the delivery terms for the Leh Army tender 2026?

Delivery starts from the last date of the original delivery order; with option exercise, extended duration uses the formula (Increased quantity ÷ Original quantity) × Original delivery period, minimum 30 days. Ensure readiness to scale up to 25% more quantity if required.

What is the 25% quantity variation clause in this Army tender?

The purchaser may increase or decrease the bid quantity by up to 25% at contracted rates during contract execution and currency, necessitating supplier readiness to adjust production or delivery accordingly.

What is required in the ATC document for this Leh bid?

ATC contains buyer-specific terms, conditions, and possible standards or penalties. Review it thoroughly to confirm item requirements, delivery schedules, quality requirements, and any warranty or compliance clauses before submission.

Are there any specific standards for the 28-item BOQ in Leh?

Public data shows no explicit standards; the ATC document will specify any required standards, certifications, or OEM constraints. Bidder must comply with those and ensure relevant certifications accompany the bid.

What is the expected submission timeline for Army Leh tender?

Exact dates are not disclosed in public data; bidders should rely on the ATC for submission deadlines and ensure timely response, with readiness to adjust quantities by up to 25% as per contract terms.

How to verify EMD requirements for this Army procurement in JK?

EMD information is not publicly listed; verify the exact amount and modality (DD/online) in the ATC, and prepare the security deposit accordingly to avoid disqualification during bid evaluation.