RAIndian Army invites bids for multiple electrical supplies in Leh, Jammu & Kashmir (194101), including XLPE Cable up to 1.1 kV (IS 7098 Part 1), MCCB conforming to IS/IEC 60947 Part 2, Cable Joint Kits for up to 33 kV (V2), and LED luminaires per IS 10322 Part 5. The procurement scope appears to cover both power distribution and lighting components with OEM approvals and post-award compliance. The package requires specified make approvals, GST & financial disclosures, and performance guarantees. A 2% completion guarantee from the L1 bidder is mandated prior to contract placement. The clause allows quantity variations up to 25% and specifies option-based delivery extensions. Unique requirements include CRAC/completion certificates and OEM authorization.
XLPE Cable up to 1.1 kV: IS 7098 Part 1, ISI likely
MCCB: IS/IEC 60947 Part 2, conformity required
Cable Joint Kit: suitable for cables up to 33 kV, V2 rating
LED Road & Street Light: IS 10322 Part 5, Section 3
LED Recessed Ceiling Light: IS 10322 Part 5, Section 2
PVC insulated copper cable: IS 694, circular sheathed
Make approval and OEM authorization required for all items
CRAC/Completion certificates for similar products
Quantity may vary +/-25% with extended delivery period as per option clause
2% of bid amount as completion guarantee required before contract placement
OEM authorizations and HQs/E-in-C make approvals are mandatory
2% completion guarantee before contract placement; no explicit milestone payments stated
Option clause allows up to 25% quantity variation; extended delivery period calculation with a minimum of 30 days
Not explicitly stated beyond risk of non-completion and guaranteed completion; LD applied per contract terms
Make approval for offered items from Comd HQs/E-in-C branch
Not blacklisted by any Government agency (affidavit within 3 months)
GST registration and latest FY return (2024-25) submitted
Bid-specific OEM authorization certificates provided
CRAC/completion certificates of similar products submitted
Start
07-Nov-2026, 7:00 pm
End
09-Nov-2026, 7:00 pm
Duration: 48 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
Quantity
5074
Category
XLPE Cable for Working Voltage up to and Including 1.1 KV Marked To IS 7098 (Part 1)
Bid Type
Two Packet Bid
Bid Validity
30 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
2 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Min. Avg. Annual Turnover
83
Past Performance
10 %
Experience Required
1 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
XLPE Cable for Working Voltage up to and Including 1.1 KV Marked To IS 7098 (Part 1) (Q2) , Moulded Case Circuit Breakers (MCCB) Conforming To IS/IEC 60947 (Part 2) (Q2) , Cable Joint Kit Suitable for Cables Up to and Including 33 kV (V2) (Q3) , LED Luminaire For Road And Street Lights Conforming To IS 10322 (Part 5/Section 3) (V3) (Q2) , LED Luminaire (Recessed Luminaire) (Ceiling Light) Conforming To IS 10322 (Part 5/Section 2) (V4) (Q2) , PVC Insulated Copper Cable Single Core and Multi Core Circular Sheathed with Rigid Conductor (V2) ISI Marked To IS 694 (Q2)
Advisory Bank
State Bank of India
ePBG Percentage
3%
ePBG Duration (Months)
12
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
Leh
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Leh | Leh | - | - | 150 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
GEM_GENERAL_TERMS_AND_CONDITIONS
GST certificate for FY 2024-25
PAN card of bidder
Experience certificates for similar electrical equipment
Financial statements / turnover details
EMD submission proof (cash/DD/online)
Technical bid documents and BOM
OEM authorizations / Make in India certificates (if applicable)
Bid-specific OEM price list and make/model details
Affidavit on Rs 100 stamp paper declaring not blacklisted
Key insights about JAMMU AND KASHMIR tender market
Bidders must upload GST FY 2024-25 return, provide OEM authorization, and obtain Comd HQs/E-in-C make approval. Include 2% completion guarantee and CRAC/completion certificates. Ensure EMD is submitted before bid end date and follow option clause for quantity variation up to 25%.
Submit bid-specific OEM authorization certificates, GST return, identity PAN, last financial statements, experience certificates for similar projects, and EMD proof. Include CRAC/completion certificates for similar products and affidavit of not blacklisted on Rs 100 stamp paper.
Delivery time can extend if quantity increases by up to 25%. Extended period equals (increased quantity ÷ original quantity) × original delivery period, with a minimum of 30 days. Original period applies if the calculation yields less than 30 days.
Luminaires must conform to IS 10322 Part 5 (Road & Street Light, Section 3) and Part 5 (Section 2) for recessed ceiling lights. Bidders should provide OEM price lists and confirm ISI/ISI-related certification where applicable, plus vendor make approval from HQs.
An EMD proof must be submitted before bid end date; additionally a 2% of the offered amount completion guarantee is required prior to contract placement, refundable on successful completion. No explicit fixed EMD amount provided in data.
Cables must align with IS 7098 Part 1; MCCBs with IS/IEC 60947 Part 2. LED luminaires should comply with IS 10322 Part 5; PVC copper cables with IS 694. OEM authorizations and HQ approvals reinforce compliance.
The agency requires Comd HQs/E-in-C branch approval for makes/models offered. Bidders must upload the approval letter; otherwise, scanning disqualifies technically. Ensure all products are OEM-authorized and meet requested standards.
Eligibility includes non-blacklisted status via affidavit, valid GST registration, 2024-25 GST submission, make-approved OEM certifications, CRAC/completion certificates for similar items, and ability to submit OEM price lists and make/model details.