The Indian Army, Department Of Military Affairs, invites bids in Bangalore, Karnataka for a comprehensive gymnasium setup including a heavy duty dumbbell rack (cast iron construction), storage for 16 weight plates, and a frame to hold 8-10 pairs of dumbbells. The package covers sales, installation, testing and commissioning of the gym equipment, plus sports flooring mats (304x304 mm, 8mm thick), kerbs, corners, transportation, and line marking. Estimated value and EMD are not disclosed in the data, but the scope encompasses complete on-site delivery and handover to the Army. The purchase requires adherence to the purchaser’s option clause-quantity adjustments up to 25%, with delivery timelines linked to the original schedule. This tender emphasizes integrated facility setup rather than standalone equipment supply.
Dumbbell rack: heavy duty cast iron angles, holds 8-10 pairs of dumbbells
Weight plate storage: accommodates up to 16 weight plates
Matting: 304x304 mm, 8mm thick, flooring area up to 31x24 ft
Additional: kerbs, corners, transportation and line marking included in scope
Delivery/installation: complete Supply, Installation, Testing and Commissioning
Option to adjust quantity by up to 25%, with proportional delivery time changes
Bid price must cover supply, installation, testing and commissioning
Turnover and OEM turnover criteria required with valid financial certificates
Functional service centers required in consignee state for carry-in warranty
Documentation stack includes GST, PAN, financials, and OEM authorizations
Payment terms to be defined in bid; ensure sequence aligns with supply, installation, testing and commissioning milestones
Delivery operates from the last date of original delivery order; extended time applies with option clause calculations
Penalties to be clarified in final bid; standard Army procurement LDs may apply for delays
Three-year turnover criterion with audited finances or CA certificate
OEM turnover compliance for the primaries product category
Functional service center availability in each consignee state
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) |
|---|---|---|---|---|---|---|
| 1 | CL 1015 PEC Fly rear dent 100 kgs | CL 1015 PEC Fly rear dent 100 kgs | 1 | nos | aopctc1 | 15 |
| 2 | Rack Sturdy design Made from Heavy Duty Cast Iron angles Can hold upto 8 to 10 pairs of Dumbbell can store upto 16 weight plates and 4 | Rack Sturdy design Made from Heavy Duty Cast Iron angles Can hold upto 8 to 10 pairs of Dumbbell can store upto 16 weight plates and 4 | 1 | nos | aopctc1 | 15 |
| 3 | Economic PP Size of 304 8mm x 304 mm and thickness of 15 7mm L x W 31 X 24 ft sports flooring mat | Economic PP Size of 304 8mm x 304 mm and thickness of 15 7mm L x W 31 X 24 ft sports flooring mat | 744 | sqft | aopctc1 | 15 |
| 4 | Kerbs | Kerbs | 440 | sqft | aopctc1 | 15 |
| 5 | Corners | Corners | 4 | sqft | aopctc1 | 15 |
| 6 | Transportation and line marking | Transportation and line marking | 1 | ls | aopctc1 | 15 |
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Audited financial statements or CA certificate indicating turnover for the last three financial years
Experience certificates for similar gym equipment projects
OEM authorization letter for the offered product category
Technical bid documents and compliance certificates (if applicable)
Any site-specific installation or service capability certificates
Key insights about KARNATAKA tender market
To bid, prepare GST, PAN, auditor-certified turnover for last 3 years, and OEM authorization. Include detailed BOM for the dumbbell rack (8-10 pairs) and 16 plate storage, plus 304x304 mm mats (8 mm thick). Ensure supply, installation, testing, commissioning are included in the bid price and respect the 25% option clause.
Submit GST certificate, PAN, audited financials or CA certificate showing turnover, OEM authorization, experience certificates for gym equipment, technical bid, and installation capability documents. Include service center details in Karnataka for carry-in warranty, if applicable.
Dumbbell rack must use heavy duty cast iron angles and hold 8-10 pairs of dumbbells with space for 16 weight plates. Flooring mats are 304x304 mm, 8 mm thick, covering approximately 31x24 ft area; kerbs and corners to be supplied along with transportation and line marking.
Delivery timing follows the original delivery order with potential extension under the option clause; additional time is calculated as (increased quantity ÷ original quantity) × original delivery period, with a minimum of 30 days, per the buyer terms.
Bidder turnover must meet the minimum average annual turnover over the last three years as stated in the bid document, supported by audited balances or CA certificates. OEM turnover must also meet the same criterion; in bunch bids, the OEM of the highest bid value must comply.
Scope includes Supply, Installation, Testing and Commissioning of all gym equipment and flooring components, plus related kerbs, corners, transportation and line marking as part of a single consolidated bid package.
Bidders must provide evidence of a functional service center in the consignee state for carry-in warranty or confirm on-site warranty terms; ensure post-sale service and AMC arrangements align with Indian Army procurement standards.
The purchaser may adjust quantity by up to 25% at contract placement and during the currency of the contract. Delivery time extends accordingly based on the extended quantity calculation, with minimum extension set at 30 days.