Bid Publish Date
26-Sep-2026, 3:48 pm
Bid End Date
09-Oct-2026, 4:00 pm
Location
Progress
NMDC Steel Limited invites bids for a plate-type heat exchanger (OEM-acceptable: Funke) for the exhauster of BPP, to be supplied at NMDC facilities in BASTAR, CHHATTISGARH. The scope is limited to the supply of goods with a single item list and no BOQ quantity given. Key terms include a 35-day delivery from PO, 30-day payment post receipt, and an option to adjust quantity by up to 25% during contract. The ATC emphasizes OEM authorization and non-acceptance of advance payment, along with a 0.5% weekly liquidated damages cap. Unique aspects include a strict acceptance plan (VIC + MT certificates) and adherence to GEM bid terms, with Funke as acceptable make.
Product: Plate-type heat exchanger for exhauster (BPP)
Acceptable makes: OEM Funke or authorized dealer with OEM certificate
Delivery: 35 days from PO issue
Payment: 100% within 30 days on receipt & acceptance
Inspection: Visual, MTC, fitment guarantee, site quantity verification
Penalties: 0.5% of basic order value per week, max 5% for delays
Scope: Only supply of goods; installation not included
Bid framework: Adheres to GEM bid terms and GTC
Delivery terms: 35 days from PO date with option quantity variation up to 25%
Payment: 100% within 30 days after receipt and acceptance; no advance
Authorisation: OEM Funke authorization mandatory; dealer-only bids rejected
100% payment within 30 days against receipt & acceptance of ordered items, with original/digitally signed invoices
Delivery within 35 days from Purchase Order date; extension methods via option clause with minimum 30 days
0.5% LD per week on basic order value for delayed delivery, capped at 5% of basic order value
OEM authorization from Funke or authorized dealer for Funke plate-type heat exchangers
Experience in supplying heat exchangers; prior similar projects preferred
GST registration and valid financial documents to demonstrate capability
Quantity
2
Bid Type
Single Packet Bid
Bid Validity
120 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
2 Days
EMD Required
No
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Heat exchanger
Payment Timelines
Payments shall be made to the Seller within 30 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
35
Delivery Locations
1
Delivery Cities
Raipur
Delivery Pincodes
494001
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mahendra Raud | 494001,NMDC STEEL LIMITED, C/o NMDC Iron & Steel Plant, Nagarnar, postbox no.2, Jagdalpur , Dist .Bastar, CG 494001 | Raipur | Chhattisgarh | 494001 | 2 | 35 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
09-Oct-2026, 10:30 am
Opening Date
10-Oct-2026, 10:30 am
GST registration
PAN card
OEM authorization certificate (Funke) or authorized dealer certificate
Technical specifications compliance document
Material Test Certificate (MTC)
Fitment Guarantee certificate
Invoice & delivery documents for payment processing
Proof of experience in supplying heat exchangers (similar equipment)
Key insights about CHHATTISGARH tender market
Bidders must submit GST registration, PAN, OEM authorization from Funke (or authorized dealer), MT certificate, fitment guarantee, and commercial invoices. Also provide proof of experience in supplying plate-type heat exchangers and site quantity verification documentation.
Delivery must occur within 35 days from PO date. The option clause allows up to 25% quantity variation with a delivery time calculation, minimum 30 days, and possible extension up to the original delivery period as per terms.
The bidder must accept 100% payment within 30 days after receipt and acceptance of ordered items, accompanied by valid original or digitally signed invoices, with no advance payment.
Liquidated damages are 0.5% of the basic order value per week or part thereof, not to exceed 5% of the basic order value for undelivered goods, calculated from the dispatch date.
Only Funke-branded heat exchangers, via OEM authorization or authorized dealer, are acceptable. Bids from unauthorized dealers will be rejected.
Acceptance relies on visual inspection, Material Test Certificate, fitment guarantee certificate, and site quantity verification, ensuring the item meets required standards before payment.