Progress
RAA tender has been published for Indian Army 2MP PTZ Camera, 2MP Bullet Camera, IP Camera with Allied Accessories, NVR 64 Channel, Surveillance HDD 8TB, 8 Port High POE Switch, Cat-6 Cable, RJ 45 with Gang Box, Core Rack 27U, Online UPS, Edge Switch Racks, Fiber Cable, LIU, Fiber Pigtails, Fiber Patch Cords, SFP Fiber Modules, Poles, Fibre Laying, PVC Conduit, I and C UTP Laying, PDU Power Setup, Fiber Splicing, Underground Digging, Active Installation in PANCHKULA, HARYANA. Quantity: 6667 by. Submission Deadline: 29-09-2026 14: 00: 00. Check eligibility and apply.
Start
19-Oct-2026, 8:00 pm
End
21-Oct-2026, 9:00 am
Duration: 37 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
Quantity
6667
Category
2MP PTZ Camera
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
50% Lowest Priced Technically Qualified Bidders
Tech Clarification Time
2 Days
EMD Required
Yes
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Past Performance
50 %
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
2MP PTZ Camera , 2MP Bullet Camera , IP Camera with Allied Accessories , NVR 64 Channel , Surveillance HDD 8TB , 8 Port High POE Switch , Cat-6 Cable , RJ 45 with Gang Box , Core Rack 27U , Online UPS , Edge Switch Racks , Fiber Cable , LIU , Fiber Pigtails , Fiber Patch Cords , SFP Fiber Modules , Poles , Fibre Laying , PVC Conduit , I and C UTP Laying , PDU Power Setup , Fiber Splicing , Underground Digging , Active Installation
Advisory Bank
State Bank of India
ePBG Percentage
5%
ePBG Duration (Months)
24
Pre-Bid Date
21-09-2026 13:00:00
Pre-Bid Venue
118 Engineer Regiment c/o 56 APO
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
Panchkula
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Panchkula | Panchkula | - | - | 2 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
2MP PTZ Camera
2MP PTZ Camera as per technical specification ser no 1
2MP Bullet Camera
2MP Bullet Camera as per technical specification ser no 2
IP Camera with Allied Accessories
IP Camera with Allied Accessories as per technical specification ser no 3
NVR 64 Channel
NVR 64 Channel as per technical specification ser no 4
Surveillance HDD 8TB
Surveillance HDD 8TB as per technical specification ser no 5
8 Port High POE Switch
8 Port High POE Switch as per technical specification ser no 6
Cat-6 Cable
Cat-6 Cable as per technical specification ser no 7
RJ 45 with Gang Box
RJ 45 with Gang Box as per technical specification ser no 8
Core Rack 27U
Core Rack 27U as per technical specification ser no 9
Online UPS
Online UPS as per technical specification ser no 10
Edge Switch Racks
Edge Switch Racks as per technical specification ser no 11
Fiber Cable
Fiber Cable as per technical specification ser no 12
LIU
LIU as per technical specification ser no 13
Fiber Pigtails
Fiber Pigtails as per technical specification ser no 14
Fiber Patch Cords
Fiber Patch Cords as per technical specification ser no 15
SFP Fiber Modules
SFP Fiber Modules as per technical specification ser no 16
Poles
Poles as per technical specification ser no 17
Fibre Laying
Fibre Laying as per technical specification ser no 18
PVC Conduit
PVC Conduit as per technical specification ser no 19
I and C UTP Laying
I and C UTP Laying as per technical specification ser no 20
PDU Power Setup
PDU Power Setup as per technical specification ser no 21
Fiber Splicing
Fiber Splicing as per technical specification ser no 22
Underground Digging
Underground Digging as per technical specification ser no 23
Active Installation
Active Installation as per technical specification ser no 24
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | 2MP PTZ Camera | 2MP PTZ Camera as per technical specification ser no 1 | 2 | nos | kartik@118 | 30 | |
| 2 | 2MP Bullet Camera | 2MP Bullet Camera as per technical specification ser no 2 | 8 | nos | kartik@118 | 30 | |
| 3 | IP Camera with Allied Accessories | IP Camera with Allied Accessories as per technical specification ser no 3 | 21 | nos | kartik@118 | 30 | |
| 4 | NVR 64 Channel | NVR 64 Channel as per technical specification ser no 4 | 1 | nos | kartik@118 | 30 | |
| 5 | Surveillance HDD 8TB | Surveillance HDD 8TB as per technical specification ser no 5 | 1 | nos | kartik@118 | 30 | |
| 6 | 8 Port High POE Switch | 8 Port High POE Switch as per technical specification ser no 6 | 6 | nos | kartik@118 | 30 | |
| 7 | Cat-6 Cable | Cat-6 Cable as per technical specification ser no 7 | 2,450 | mtr | kartik@118 | 30 | |
| 8 | RJ 45 with Gang Box | RJ 45 with Gang Box as per technical specification ser no 8 | 27 | nos | kartik@118 | 30 | |
| 9 | Core Rack 27U | Core Rack 27U as per technical specification ser no 9 | 1 | nos | kartik@118 | 30 | |
| 10 | Online UPS | Online UPS as per technical specification ser no 10 | 1 | nos | kartik@118 | 30 | |
| 11 | Edge Switch Racks | Edge Switch Racks as per technical specification ser no 11 | 3 | nos | kartik@118 | 30 | |
| 12 | Fiber Cable | Fiber Cable as per technical specification ser no 12 | 500 | mtr | kartik@118 | 30 | |
| 13 | LIU | LIU as per technical specification ser no 13 | 3 | nos | kartik@118 | 30 | |
| 14 | Fiber Pigtails | Fiber Pigtails as per technical specification ser no 14 | 36 | nos | kartik@118 | 30 | |
| 15 | Fiber Patch Cords | Fiber Patch Cords as per technical specification ser no 15 | 6 | nos | kartik@118 | 30 | |
| 16 | SFP Fiber Modules | SFP Fiber Modules as per technical specification ser no 16 | 8 | nos | kartik@118 | 30 | |
| 17 | Poles | Poles as per technical specification ser no 17 | 2 | nos | kartik@118 | 30 | |
| 18 | Fibre Laying | Fibre Laying as per technical specification ser no 18 | 500 | mtr | kartik@118 | 30 | |
| 19 | PVC Conduit | PVC Conduit as per technical specification ser no 19 | 500 | mtr | kartik@118 | 30 | |
| 20 | I and C UTP Laying | I and C UTP Laying as per technical specification ser no 20 | 2,400 | mtr | kartik@118 | 30 | |
| 21 | PDU Power Setup | PDU Power Setup as per technical specification ser no 21 | 4 | wk | kartik@118 | 30 | |
| 22 | Fiber Splicing | Fiber Splicing as per technical specification ser no 22 | 36 | wk | kartik@118 | 30 | |
| 23 | Underground Digging | Underground Digging as per technical specification ser no 23 | 150 | wk | kartik@118 | 30 | |