Gujarat State Electricity Corporation Limited (GSECL), Vadodara, invites bids for a SUPER RESIST WEAR RESIST LINING COMPOUND. The procurement covers a single, supply-based requirement under the Energy and Petro Chemicals Department, with an option clause permitting up to a 25% quantity variation at contracted rates. Delivery timelines hinge on the original order date, with extension rules based on the option clause. The ATC specifies that material must align with Schedule-B and the buyer’s technical specifications. The absence of BOQ items suggests a single-line, product-specific supply contract, emphasizing compliance with buyer-added terms and final ATC. Key differentiators include flexible quantity handling and adherence to the Schedule-B framework.
Product: SUPER RESIST WEAR RESIST LINING COMPOUND
Quantity: adaptable via 25% variation clause
Delivery: extension formula = (additional quantity / original quantity) × original delivery period, minimum 30 days
Standards/ATC: Schedule-B alignment with final ATC governing technical specs
Documentation: follow Buyer Added ATC and Schedule-B requirements
Quantity may vary by up to 25% at contracted rates
Delivery period extensions governed by original delivery term with 30-day minimum
Material to be supplied per Schedule-B and final ATC terms
Payment terms to be specified in the contract/ATC; bidders should anticipate standard government settlement timelines aligned with Schedule-B and ATC.
Delivery period commences from the last date of original delivery order; quantity extensions possible as per option clause with minimum 30 days.
LD provisions to be detailed in ATC; bidders should review contract for LD rates and penalties.
Eligibility to supply wear resistant lining compounds in government procurement
Conformity with Schedule-B and local Gujarat electricity procurement requirements
Financial strength to meet tender performance and security deposits per ATC
Quantity
30
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
Tech Clarification Time
3 Days
EMD Required
No
MII Purchase Preference
No
MSE Purchase Preference
No
MSE Exemption/Relaxation
No
Startup Exemption/Relaxation
No
Bid Splitting Applied
No
Arbitration Clause
Yes (Arbitration clause document) as per DoE OM No.F.1/2/2024-PPD dated 03.06.2024 Arbitration should not be routinely included in contracts
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
T-6374_ SUPER RESIST WEAR RESIST LINING COMPOUND
Advisory Bank
Bank Of Baroda
ePBG Percentage
5%
ePBG Duration (Months)
4
Max Delivery Days
60
Delivery Locations
1
Delivery Cities
Tapi
Delivery Pincodes
394680
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Pallavkumar Maganbhai Solanki | 394680,GSECL UKAI TPS, UKAI DAM, DIST: TAPI | Tapi | Gujarat | 394680 | 30 | 60 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
OTHER
OTHER
OTHER
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Extended Deadline
26-Oct-2026, 9:30 am
Opening Date
27-Oct-2026, 9:30 am
Discover companies most likely to bid on this tender
GST registration certificate
Permanent Account Number (PAN) card
Experience certificates in similar wear-resistant lining material supply
Financial statements for last 2-3 financial years
Earnest Money Deposit (EMD) document as per ATC
Technical bid/technical compliance certificate
OEM authorisation or authorized dealership certificate (if required by ATC)
Schedule-B conformity statement and any specific test reports mentioned in ATC
Key insights about GUJARAT tender market
Bidders must submit all documents per ATC and Schedule-B, including GST, PAN, experience in similar lining materials, and EMD. Ensure compliance with the final ATC for technical specs and OEM authorizations if required. Delivery terms follow the 25% quantity variation clause and original delivery period rules.
Required submissions include GST certificate, PAN card, two financial statements, experience certificates for similar work, EMD document, technical compliance, and OEM authorization if called for by ATC. Schedule-B conformity statement and any test reports must be attached as per ATC.
Technical requirements are governed by Schedule-B and the final ATC. The product is a wear resistant lining compound; exact composition, tests, and performance metrics will be specified in the ATC. Suppliers must align to Schedule-B format and provide necessary test reports if demanded.
Delivery time can be extended for additional quantity up to 25% at contracted rates. The extension is calculated as (additional quantity ÷ original quantity) × original delivery period, with a mandatory minimum of 30 days.
ATC contains all buyer-specific terms, certification needs, and final technical requirements. It overrides general tender terms, mandates Schedule-B conformity, and may specify OEM authorizations and testing standards essential for bid qualification.
Payment terms will be defined within the contract/ATC; bidders should expect standard government settlement practices after delivery or completion milestones, with supporting documentation as required by ATC.