Progress
RAA tender has been published for Indian Army IP Bullet Camera 8MP with 50Mtr IR, NVR 8 Channel, NAS 6TB, 24 Port PoE Switch, 4 Port PoE Switch, OTE, 12 Core OFC, Cat 6 UTP Cable, Joint Enclosure, RJ-45 Connector, Pigtails 5 Mtrs, UTP Patch Cord 10 Mtr, UTP Patch Cord 3 Mtr, 55 Inch Display Panel, HDMI Cable 10Mtr, UPS 3KVA with 2Hrs Backup, UPS 1KVA, 6U Rack, Power Cable 3 Core 1. 5 Sqm 90 Mtr, Power Board, 12 Feet Pole, Accessories, Camera Instln and Earthing, Overhead OFC Laying with Splicing in SONITPUR, ASSAM. Quantity: 137 by. Submission Deadline: 23-07-2026 19: 00: 00. Check eligibility and apply.
These are the final prices after the reverse auction event. Prices may be lower than initial bids.
| Rank | Seller | Final Price | Item |
|---|---|---|---|
| L1 | NEXGEN INNOVATION(MSE,MII) Under PMA Winner | ₹8,57,000 | Item Categories : IP Bullet Camera 8MP with 50Mtr IR,NVR 8 Channel,NAS 6TB,24 Port PoE Switch,4 Port PoE Switch,OTE,1 |
| L2 | E-VISION INDIA PRIVATE LIMITED (MSE,MII) Under PMA | ₹8,61,900 | Item Categories : IP Bullet Camera 8MP with 50Mtr IR,NVR 8 Channel,NAS 6TB,24 Port PoE Switch,4 Port PoE Switch,OTE,1 |
🎉 L1 Winner
NEXGEN INNOVATION(MSE,MII) Under PMA
Final Price: ₹8,57,000
Start
18-Aug-2026, 12:00 pm
End
22-Aug-2026, 11:00 am
Duration: 95 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
Quantity
137
Category
IP Bullet Camera 8MP with 50Mtr IR
Bid Type
Two Packet Bid
Bid Validity
180 (Days)
Bid Type
Service
Evaluation
Total value wise evaluation
Inspection Required
No
RA Qualification Rule
H1-Highest Priced Bid Elimination
Tech Clarification Time
4 Days
EMD Required
Yes
MII Purchase Preference
Yes
MII Preference Band
L1+20%
MSE Purchase Preference
Yes
MSE Preference Band
L1+15%
MSE Exemption/Relaxation
Yes
Startup Exemption/Relaxation
Yes
Bid Splitting Applied
No
Min. Avg. Annual Turnover
4
OEM Avg. Turnover
4
Past Performance
50 %
Warranty Period
7 days
Experience Required
3 Year (s)
Arbitration Clause
No
Mediation Clause
No
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
IP Bullet Camera 8MP with 50Mtr IR , NVR 8 Channel , NAS 6TB , 24 Port PoE Switch , 4 Port PoE Switch , OTE , 12 Core OFC , Cat 6 UTP Cable , Joint Enclosure , RJ-45 Connector , Pigtails 5 Mtrs , UTP Patch Cord 10 Mtr , UTP Patch Cord 3 Mtr , 55 Inch Display Panel , HDMI Cable 10Mtr , UPS 3KVA with 2Hrs Backup , UPS 1KVA , 6U Rack , Power Cable 3 Core 1.5 Sqm 90 Mtr , Power Board , 12 Feet Pole, Accessories, Camera Instln and Earthing , Overhead OFC Laying with Splicing
Advisory Bank
State Bank of India
ePBG Percentage
3%
ePBG Duration (Months)
26
Max Delivery Days
30
Delivery Locations
1
Delivery Cities
Sonitpur
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| - | Sonitpur | Sonitpur | - | - | 6 | 30 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
IP Bullet Camera 8MP with 50Mtr IR
IP Bullet Camera 8MP with 50Mtr IR
NVR 8 Channel
NVR 8 Channel
NAS 6TB
NAS 6TB
24 Port PoE Switch
24 Port PoE Switch
4 Port PoE Switch
4 Port PoE Switch
OTE
OTE
12 Core OFC
12 Core OFC
Cat 6 UTP Cable
Cat 6 UTP Cable
Joint Enclosure
Joint Enclosure
RJ-45 Connector
RJ-45 Connector
Pigtails 5 Mtrs
Pigtails 5 Mtrs
UTP Patch Cord 10 Mtr
UTP Patch Cord 10 Mtr
UTP Patch Cord 3 Mtr
UTP Patch Cord 3 Mtr
55 Inch Display Panel
55 Inch Display Panel
HDMI Cable 10Mtr
HDMI Cable 10Mtr
UPS 3KVA with 2Hrs Backup
UPS 3KVA with 2Hrs Backup
UPS 1KVA
UPS 1KVA
6U Rack
6U Rack
Power Cable 3 Core 1.5 Sqm 90 Mtr
Power Cable 3 Core 1.5 Sqm 90 Mtr
Power Board
Power Board
12 Feet Pole, Accessories, Camera Instln and Earthing
12 Feet Pole, Accessories, Camera Instln and Earthing
Overhead OFC Laying with Splicing
Overhead OFC Laying with Splicing
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | IP Bullet Camera 8MP with 50Mtr IR | IP Bullet Camera 8MP with 50Mtr IR | 6 | nos | tithwal@223 | 30 | |
| 2 | NVR 8 Channel | NVR 8 Channel | 1 | nos | tithwal@223 | 30 | |
| 3 | NAS 6TB | NAS 6TB | 1 | nos | tithwal@223 | 30 | |
| 4 | 24 Port PoE Switch | 24 Port PoE Switch | 2 | nos | tithwal@223 | 30 | |
| 5 | 4 Port PoE Switch | 4 Port PoE Switch | 6 | nos | tithwal@223 | 30 | |
| 6 | OTE | OTE | 6 | pair | tithwal@223 | 30 | |
| 7 | 12 Core OFC | 12 Core OFC | 2 | km | tithwal@223 | 30 | |
| 8 | Cat 6 UTP Cable | Cat 6 UTP Cable | 6 | roll | tithwal@223 | 30 | |
| 9 | Joint Enclosure | Joint Enclosure | 40 | nos | tithwal@223 | 30 | |
| 10 | RJ-45 Connector | RJ-45 Connector | 2 | box | tithwal@223 | 30 | |
| 11 | Pigtails 5 Mtrs | Pigtails 5 Mtrs | 12 | nos | tithwal@223 | 30 | |
| 12 | UTP Patch Cord 10 Mtr | UTP Patch Cord 10 Mtr | 6 | nos | tithwal@223 | 30 | |
| 13 | UTP Patch Cord 3 Mtr | UTP Patch Cord 3 Mtr | 6 | nos | tithwal@223 | 30 | |
| 14 | 55 Inch Display Panel | 55 Inch Display Panel | 1 | nos | tithwal@223 | 30 | |
| 15 | HDMI Cable 10Mtr | HDMI Cable 10Mtr | 2 | nos | tithwal@223 | 30 | |
| 16 | UPS 3KVA with 2Hrs Backup | UPS 3KVA with 2Hrs Backup | 1 | nos | tithwal@223 | 30 | |
| 17 | UPS 1KVA | UPS 1KVA | 6 | nos | tithwal@223 | 30 | |
| 18 | 6U Rack | 6U Rack | 1 | nos | tithwal@223 | 30 | |
| 19 | Power Cable 3 Core 1.5 Sqm 90 Mtr | Power Cable 3 Core 1.5 Sqm 90 Mtr | 12 | roll | tithwal@223 | 30 | |
| 20 | Power Board | Power Board | 10 | nos | tithwal@223 | 30 | |
| 21 | 12 Feet Pole, Accessories, Camera Instln and Earthing | 12 Feet Pole, Accessories, Camera Instln and Earthing | 6 | nos | tithwal@223 | 30 | |
| 22 | Overhead OFC Laying with Splicing | Overhead OFC Laying with Splicing | 2 | km | tithwal@223 | 30 |
Experience Criteria
Past Performance
Bidder Turnover
Certificate (Requested in ATC)
OEM Authorization Certificate
OEM Annual Turnover
Additional Doc 1 (Requested in ATC)
Compliance of BoQ specification and supporting document *In case any bidder is seeking exemption from Experience / Turnover Criteria
the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer