Bharat Heavy Electricals Limited Spring Hanger Package Tender Raigarh Chhattisgarh 2026 NTPC Lara & Singrauli

Bid Publish Date

28-Apr-2026, 10:01 am

Bid End Date

01-Jun-2026, 11:00 am

Generate Docs

Progress

RA
Issue28-Apr-2026, 10:01 am
Corrigendum25-May-2026
Reverse Auction21-Aug-2026, 11:00 am
Award04-Sep-2026, 3:17 am

Key Highlights

  • • Option Clause: +25% quantity variation during and after contract at contracted rates
  • • Mandatory Detailed Design Drawings approval within 7 days of award; modification list provided in 7 days
  • • GST reimbursement based on actuals or applicable rate (whichever is lower) up to quoted GST
  • • Data Sheet upload required; strict matching with technical parameters to avoid rejection

Tender Overview

The Procuring Organization is Bharat Heavy Electricals Limited (BHEL), seeking the Spring Hanger Package (SGIP) for the NTPC Lara and NTPC Singrauli projects, Raigarh, CHHATTISGARH. The scope focuses on supplying hangers and related assemblies for power project implementations. The tender references a flexible quantity clause allowing up to 25% quantity variation and possible extension at contracted rates, highlighting scope agility for large-scale boiler/FGD equipment installations. A key differentiator is the mandatory design validation step with Buyer approval prior to fabrication. The absence of BOQ items suggests a bundled package requiring comprehensive Data Sheet alignment to technical parameters and seamless integration with approved drawings. Unique delivery-time mechanics apply when approvals lag, and GST treatment is percentage-based by actuals or applicable rate, capped by quoted GST. This procurement requires vendor onboarding documents, and on-time delivery per extended periods if the option clause is exercised.

Technical Specifications & Requirements

Although explicit technical specs are not disclosed, the tender demands: submission of a Data Sheet matching offered products to the Buyer’s required parameters; adherence to the approved Detailed Design Drawings; and supply as per Buyer-approved drawings with communicated modifications. The pre-fabrication design validation within 7 days of contract award is essential; failure to obtain approval or mismatch in technical parameters risks bid rejection. The terms also specify electronic data submission for vendor code creation and essential GST/PAN documentation preparation.

Terms, Conditions & Eligibility

Key terms include: an option clause permitting ±25% quantity variation during and after contract award; delivery timelines anchored to the last date of original delivery order, with extended periods calculated by a defined formula and minimum 30 days; GST treatment on actuals at Buyer’s discretion; mandatory submission of PAN, GSTIN, Cancelled Cheque, and EFT Mandate; data sheet alignment; and termination rights if Material delivery or material terms are breached. BHEL retains rights to adjust delivery if Buyer delays approval of drawings, and penalties are implied through contract termination for non-compliance.

Key Specifications

  • Product: Spring Hanger Package (SGIP) for NTPC Lara & NTPC Singrauli

  • Delivery: Last date of original delivery order plus option-driven extension rules

  • Quality/Documentation: Data Sheet must align with offered product parameters

  • Drawings: Detailed Design Drawings to be approved within 7 days of contract award

  • GST: Reimbursement as actuals or applicable rate, whichever is lower, up to quoted GST%

Terms & Conditions

  • Option Clause allowing ±25% quantity variation during contract performance

  • 7-day window for design drawings submission and Buyer approval response

  • GST treatment guided by actuals or lower applicable rate; contractual cap on GST

  • Mandatory regulatory documents for vendor code creation (PAN, GSTIN, EFT)

Important Clauses

Payment Terms

GST reimbursement tied to actuals or applicable rate; payment terms not explicitly stated beyond GST handling

Delivery Schedule

Delivery period begins from last date of original delivery order; extended period calculated by (additional quantity/original quantity) × original delivery period, minimum 30 days

Penalties/Liquidated Damages

Not explicitly stated; termination clause available if material terms not met or delivery inability persists

Bidder Eligibility

  • Experience supplying SGIP components or similar spring hanger assemblies for major power projects

  • Valid PAN and GST Registration; ability to furnish EFT mandate and bank certification

  • Capability to submit Data Sheet alignment with Buyer-approved drawings

Advertisement

Contract / Result Documents 1

Please sign in or create an account to view contract details and download result documents.

Reverse Auction Schedule

Completed

Start

21-Aug-2026, 11:00 am

End

22-Aug-2026, 11:00 am

Duration: 24 hours

Reverse Auction Document

✅ RA concluded. Check financial results for final rankings.

Tender Data

Bid Details

Quantity

1

Bid Type

Two Packet Bid

Bid Validity

90 (Days)

Bid Type

Service

Evaluation

Total value wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

3 Days

Requirements

Min. Avg. Annual Turnover

60

OEM Avg. Turnover

60

Past Performance

50 %

Experience Required

3 Year (s)

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

SUPPLY OF SPRING HANGER PKG (SGIP) for NTPC Lara & NTPC Singrauli projects

Authority Records

MINISTRY OF HEAVY INDUSTRIESHEAVY INDUSTRY DEPARTMENT

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 4

GeM-Bidding-9265157.pdf

Main Document

Other Documents

OTHER

Buyer uploaded ATC document

ATC

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Advertisement

Categories 2

Corrigendum Updates

3 Updates
#1

Update

25-May-2026

Extended Deadline

01-Jun-2026, 5:30 am

Opening Date

01-Jun-2026, 6:00 am

#2

Update

20-May-2026

Extended Deadline

25-May-2026, 5:30 am

Opening Date

25-May-2026, 6:00 am

#3

Update

11-May-2026

Extended Deadline

20-May-2026, 5:30 am

Opening Date

20-May-2026, 6:00 am

Required Documents

1

PAN Card copy

2

GSTIN copy

3

Cancelled cheque copy

4

EFT Mandate certified by bank

5

Data Sheet of offered products

6

OEM authorization (if applicable)

7

Proof of GST and organization credentials for vendor code creation

Frequently Asked Questions

Key insights about CHHATTISGARH tender market

How to bid for spring hanger package tender in Raigarh?

Bidders should prepare PAN, GSTIN, Cancelled Cheque, EFT Mandate, and Data Sheet while ensuring Data Sheet aligns with offered SGIP parameters. Submit within your vendor registration window and include Detailed Design Drawings within 7 days of contract award; ensure compliance with 25% quantity option and design approvals.

What documents are required for BHEL SGIP bid in Raigarh?

Submit PAN, GSTIN, Cancelled Cheque, EFT Mandate, Data Sheet of offered products, OEM authorizations if applicable, and organization credentials.Vendor code creation requires these documents; ensure GST is handled per actuals or lower rate as per tender terms.

What are the delivery terms for the SGIP package tender?

Delivery begins from the last date of the original delivery order; if the option clause is exercised, extended time is (additional quantity/original quantity) × original delivery period, with a minimum of 30 days. Buyer delays in drawing approval may extend the delivery period without LD.

What are the design drawing requirements for BHEL NTPC SGIP bid?

Successful bidder must submit Detailed Design Drawings within 7 days of award; Buyer approves or returns with a modification list within 7 days. Supply must follow approved drawings and any communicated modifications; delays in approval shift delivery timelines accordingly.

What is the GST treatment for this tender in Raigarh?

GST reimbursement is based on actuals or the applicable rate, whichever is lower, limited to the bidder's quoted GST percentage. Ensure accurate GST calculation and documentation during bid submission.

What qualifies as eligible experience for the SGIP tender in 2026?

Bidders should demonstrate prior experience supplying hangers or SGIP-related components for large power projects, with evidence in project references, data sheets, and compliance documents; ensure PAN/GST compliance and vendor code readiness.

How does the 25% quantity option affect bidding strategy in BHEL tender?

Plan for scalable production and procurement to cover up to 25% quantity variation; price quotes should accommodate potential changes, maintaining cadence with original delivery timelines and ensuring ability to extend delivery at contracted rates if orders increase.

What happens if drawings are delayed approval by the Buyer?

If Buyer delays approval, the delivery period is refixed accordingly, with no Liquidated Damages for the delay caused by Buyer; bidders should factor potential timeline shifts into project planning and cash flow.