Open Tender for Removing the calandria of the Evaporator and installing and fitting a new calandria of 650 m square in SAHARANPUR, UTTAR PRADESH

Bid Publish Date

03-Jul-2026, 9:52 am

Bid End Date

18-Jul-2026, 10:00 am

Value

₹14,55,152

Progress

Issue03-Jul-2026, 9:52 am
AwardPending
Explore all 4 tabs to view complete tender details

Quantity

6469

Category

Removing the calandria of the Evaporator and installing and fitting a new calandria of 650 m square heating surface and installing all the pipe lines valves and accessories in their place

Bid Type

Two Packet Bid

Categories 82

A tender has been published for N/a Removing the calandria of the Evaporator and installing and fitting a new calandria of 650 m square in SAHARANPUR, UTTAR PRADESH. Quantity: 6469 by. Submission Deadline: 18-07-2026 10: 00: 00. Check eligibility and apply.

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

No

Authority Records

UTTAR PRADESH COOPERATIVE SUGAR FACTORIES FEDERATION LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 6

GeM-Bidding-9529487.pdf

Main Document

Other Documents

OTHER

BOQ Document

BOQ

BOQ Document

BOQ

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Past Similar Tenders (Historical Results)

5 found

Thermal Evaporation System

Indian Institute Of Technology (iit)

DURG, CHHATTISGARH

Posted: 20 January 2026
Closed: 10 February 2026
GEM

Indian Navy Evaporative Cooler Tender Raigad Maharashtra 2025 - BIS/ISI Compliance, GST Terms

Indian Navy

RAIGAD, MAHARASHTRA

Posted: 5 December 2025
Closed: 15 December 2025
GEM

Rotary Evaporator

National Institute Of Pharmaceutical Education And Research (niper) - Ahmedabad

GANDHI NAGAR, GUJARAT

Posted: 14 August 2025
Closed: 4 September 2025
GEM

Contract Bidding Open For CALENDRIA OF EVAPORATOR BODY in JALANDHAR, PUNJAB

Department of Cooperation

JALANDHAR, PUNJAB

Posted: 17 June 2026
Closed: 8 July 2026
EPROCURE

Rotatory Evaporator

National Fertilizers Limited (nfl)

RUPNAGAR, PUNJAB

Posted: 11 November 2025
Closed: 2 December 2025
GEM

Bill of Quantities (BOQ) 58 Items Sign in for GEM prices

#1

Removing the calandria of the Evaporator and installing and fitting a new calandria of 650 m square heating surface and installing all the pipe lines valves and accessories in their place

Clarification and evaporator

1 nos Delivery: 120 days
#2

Replacing an old and worn out Grand Consultant Juice Plaza condensate syrup bottle with an 8 10 mm MSC plate by connecting all connections.

Clarification and evaporator

1 nos Delivery: 120 days
#3

The worn out umbrella plate in the Vapor Cell Semi Concentrator was removed and the plate was repaired and replaced with plastic

Clarification and evaporator

1 nos Delivery: 120 days
#4

Replacing the umbrella in the Wide Body Vapor Cell Semi Concentrator with a dated and 6 8 mm MSC plate and conducting a trial.

Clarification and evaporator

1 nos Delivery: 120 days
#5

Removing the neck selvage of the quad body semi container and replacing it with a new 8 10 mm MS plate and testing it.

Clarification and evaporator

1 nos Delivery: 120 days
#6

Removing the neck selvage of the quad body semi container and repairing it with the provided plate and testing it.

Clarification and evaporator

1 nos Delivery: 120 days
#7

Cutting out the weakened roof of the quad body and replacing it with a 12mm plate provided and testing it.

Clarification and evaporator

10 sq mtr Delivery: 120 days
#8

Cutting out the weakened part of the semi capacitor vapor cell quad body cell and replacing it with a 10 12mm plate provided and testing it for a satisfactory leak proofing test.

Clarification and evaporator

60 sq mtr Delivery: 120 days
#9

Removal of the weak part of the exhaust pipeline going to the semi condenser vapor shell and fitting a new 800 mm diameter pipeline using the provided 8 10 mm plate in its place.

Clarification and evaporator

10 mtr Delivery: 120 days
#10

Cutting out the worn partition plates of the top and bottom headers of the juice heater and replacing them with the provided 8 10 mm plate arranging for fitting the rubber strip

Clarification and evaporator

2 mtr Delivery: 120 days
#11

Installing and strengthening the umbrella fitted to the vapor shell semiconductor quad body and conducting a satisfactory trial.

Clarification and evaporator

2 per body Delivery: 120 days
#12

Removing the weak intermediate first vapor second vapor pipes of the quad bodies and constructing new ones with a diameter of 500 650 mm using an 8 10 mm plate and conducting a satisfactory trial.

Clarification and evaporator

10 mtr Delivery: 120 days
#13

Removing the weakened intermediate first vapor second vapor pipes of the quad bodies and installing new ones with a diameter of 700 850 mm from 8 10 mm plates and conducting a satisfactory trial.

Clarification and evaporator

20 mtr Delivery: 120 days
#14

Dismantle fabricate and erect a 600 800 mm band and conduct a satisfactory trial.

Clarification and evaporator

2 nos Delivery: 120 days
#15

Dismantle fabricate and erect a 900 1100 mm band and conduct a satisfactory trial.

Clarification and evaporator

2 nos Delivery: 120 days
#16

Remove the steam valve from the juice heater and install a new right angle valve size 400 500 mm with the corresponding pipe connection modifications and conduct a trial.

Clarification and evaporator

2 nos Delivery: 120 days
#17

Cut and remove the double beat valve from the juice heater and install a new double beat valve size 8 diameter and conduct a trial

Clarification and evaporator

2 nos Delivery: 120 days
#18

Remove the intermediate coolers from the film type sulfur furnaces and install them using the provided pipe plate and conduct a trial.

Clarification and evaporator

2 nos Delivery: 120 days
#19

Install the sublimation pipes from the Satvik type sulfur furnaces using the provided pipe or a new one and conduct a trial.

Clarification and evaporator

2 nos Delivery: 120 days
#20

Remove the empty filtrate bottle from the vacuum filter and install a new filtrate bottle using an 8 10 mm MS plate and conduct a trial. Make all connections and conduct a trial.

Clarification and evaporator

2 nos Delivery: 120 days
#21

Removing the filtrate bottle plate of the vacuum filter and repairing it with the provided plate and giving it a trial.

Clarification and evaporator

1 nos Delivery: 120 days
#22

Removing the filtrate plate of the vacuum filter tray and repairing it with the provided plate.

Clarification and evaporator

1 nos Delivery: 120 days
#23

Cutting and removing the neck shell of the lime slaker at the lime station and replacing it with a new one using the provided plate and giving it a trial.

Clarification and evaporator

1 nos Delivery: 120 days
#24

Creating the melter from the Satvik Sulfur Furnace with a new 8 10 mm plate and giving it a satisfactory trial by installing the steam coil.

Clarification and evaporator

2 nos Delivery: 120 days
#25

Removing the worn out coils in the melters of the Satvik Sulfur Furnace replacing them with new ones and conducting hydraulic testing and giving a satisfactory trial.

Clarification and evaporator

2 per coil Delivery: 120 days
#26

Removing the worn out plates of the vacuum filter condensers replacing them with new ones and giving a satisfactory trial

Clarification and evaporator

2 nos Delivery: 120 days
#27

Removing the damaged weak steam coils in the film tine sulfur melters replacing them with new ones and conducting hydraulic testing and giving a satisfactory trial

Clarification and evaporator

2 nos Delivery: 120 days
#28

Renovate and install a new SO2 chamber inside the coolers of the Satvik Sulfur Furnace and conduct a trial.

Clarification and evaporator

2 nos Delivery: 120 days
#29

Remove the old corroded SO2 gas line at the sulfur furnace station and install the new seamless MS line with flanges tightening the joints and bolts

Clarification and evaporator

60 mtr Delivery: 120 days
#30

Remove the grooved plate of the mud mixture on the vacuum filter and repair it with the new plate provided

Clarification and evaporator

1 nos Delivery: 120 days
#31

Remove the grooved plate of the filtrate tank located below the vacuum filter install the plate provided and perform a trial.

Clarification and evaporator

1 nos Delivery: 120 days
#32

Repairing the weak parts of juice and mud with dry box of clarifier and making all the connections.

Clarification and evaporator

1 nos Delivery: 120 days
#33

Patch the weak shell of the burning chamber of the film type sulfur furnace with the plate provided for a length of approximately 5 feet from the bottom and give a satisfactory trial.

Clarification and evaporator

1 nos Delivery: 120 days
#34

Patch the weak and rotten platforms of both vacuum filters with a new burner from the provided plate.

Clarification and evaporator

5 per ton Delivery: 120 days
#35

Removing the SO2 chamber inside the last cooler of the film type sulfur furnace and installing a new one using the provided 10 mm MS plate and making all connections.

Clarification and evaporator

1 nos Delivery: 120 days
#36

Repairing the damaged clear juice bottles near the clear juice pumps and making all the connections and giving satisfactory trial.

Clarification and evaporator

1 nos Delivery: 120 days
#37

Cut out and remove all rotten mud scrapers inside the door clarifier and install the provided plates and belts according to size and give a satisfactory trial.

Clarification and evaporator

68 nos Delivery: 120 days
#38

Coat and remove the weak mud boot plates in each compartment of the clarifier and install the provided new plates.

Clarification and evaporator

2 nos Delivery: 120 days
#39

Repairing the weak parts of the agitator fitted on the vacuum filter and giving satisfactory trial.

Clarification and evaporator

1 nos Delivery: 120 days
#40

Removing the screw conveyor that had been skewed inside the mud mixture and installing a new one using the provided new plate and pipe and giving it a trial.

Clarification and evaporator

1 nos Delivery: 120 days
#41

Cutting out all the worn out weak cooling pipes and flanges of the coolers of the Satvik Sulphur Furnace and installing new flanges and cooling pipes using the provided pipe lines and plates

Clarification and evaporator

5 nos Delivery: 120 days
#42

Cutting out the worn out weak flanges of the coolers of the Sulphur Furnace and installing new flanges using the provided plate and giving it a satisfactory trial by welding Dia 1200 MS

Clarification and evaporator

2 nos Delivery: 120 days
#43

Cut and remove the weak corroded cross in the gas pipeline at the Sulphur Furnace Station and install the cross by making a new flange from the provided MS pipeline and plate

Clarification and evaporator

15 nos Delivery: 120 days
#44

Cut and remove the weak corroded header of the Sulphur Furnace and install it from the provided plate and pipeline and connect the nipples and give a satisfactory trial.

Clarification and evaporator

3 nos Delivery: 120 days
#45

Repairing the bagasse line leading to the mill installed above the vacuum filter station in the boiling house and conducting a satisfactory trial.

Clarification and evaporator

20 mtr Delivery: 120 days
#46

Remove the brass SS tubes from the quad and store them.

Clarification and evaporator

2,500 per tubes Delivery: 120 days
#47

Install the new brass SS tubes provided by the mill committee in the calandria expand them and conduct hydraulic testing of the calandria at a pressure of 4 kg cm2 and give a satisfactory trial

Clarification and evaporator

2,500 per tubes Delivery: 120 days
#48

a Dismantling old columns beam channels etc. b Manufacturing and installing new columns beam channels etc.

Clarification and evaporator

10 per ton Delivery: 120 days
#49

Removing the old corroded platform and replacing it with a new one

Clarification and evaporator

20 sq mtr Delivery: 120 days
#50

Installing 16 inch 18 inch manholes with blinds.

Clarification and evaporator

1 nos Delivery: 120 days
#51

Constructing a bed for the pump fitting the pump and motor and conducting a trial run of up to 20 HP.

Clarification and evaporator

20 per hp Delivery: 120 days
#52

Dismantling fabricating and erecting weak corroded pipe lines up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

972 p inch dia p mtr Delivery: 120 days
#53

Dismantling fabricating and erecting weak corroded tees up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

15 p inch dia p nos Delivery: 120 days
#54

Dismantling fabricating and erecting weak corroded nipples up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

16 p inch dia p nos Delivery: 120 days
#55

Dismantling fabricating and erecting a weak throated cross member up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

15 p inch dia p nos Delivery: 120 days
#56

Dismantling fabricating and erecting a weak throated band up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

25 p inch dia p nos Delivery: 120 days
#57

Dismantling fabricating and erecting a weak throated flange up to 12 and providing satisfactory leak proof trials.

Clarification and evaporator

30 p inch dia p nos Delivery: 120 days
#58

Dismantling fabricating and erecting a weak sloping reducer up to 12 and providing a satisfactory leak proof trial.

Clarification and evaporator

10 p inch dia p nos Delivery: 120 days

🤖 AI-Powered Bidder Prediction

Discover companies most likely to bid on this tender

Live AI
Historical Data

Required Documents

1

Experience Criteria

2

Certificate (Requested in ATC)

3

Additional Doc 1 (Requested in ATC)

4

Additional Doc 2 (Requested in ATC) *In case any bidder is seeking exemption from Experience / Turnover Criteria

5

the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer

Similar Tenders

5 found
Urgent

Invitation to Bid - Replacement of Old Evaporator 4th Body Vapour Catchall in TIRUVANNAMALAI, TAMIL NADU

Department of Sugar

📍 TIRUVANNAMALAI, TAMIL NADU

⏰ Deadline: 3 days left
🛒 Type: Works
View EPROCURE

The Fertilisers And Chemicals Travancore Limited Rotary Evaporator Tender Ernakulam Kerala 2026

The Fertilisers And Chemicals Travancore Limited

📍 ERNAKULAM, KERALA

EMD: ₹24,000
⏰ Deadline: 3 weeks left
🛒 Type: Goods
View GEM
Urgent

Open Tender for REPAIRS TO RCC STRUCTURES IN EVAPORATION SECTION in ERNAKULAM, KERALA

Hindustan Organic Chemicals Limited

📍 ERNAKULAM, KERALA

EMD: ₹29,200
⏰ Deadline: 2 days left
🛒 Type: Works
View EPROCURE
Urgent

Contract Bidding Open For OLD SET EVAPORATE CONDENSATE PUMP SPARE in TIRUVANNAMALAI, TAMIL NADU

Department of Sugar

📍 TIRUVANNAMALAI, TAMIL NADU

⏰ Deadline: 3 days left
🛒 Type: Goods
View EPROCURE
Urgent

Invitation to Bid - Carrying out Performance and Feasibility Study of Evaporator # D Stream towards performance optimization in TNPL Unit-I in KARUR, TAMIL NADU

Tamilnadu Newsprint and Papers Limited

📍 KARUR, TAMIL NADU

EMD: ₹5,000
⏰ Deadline: 6 days left
🛒 Type: Service
View EPROCURE