TenderDekho Logo
Closed GEM

Rashtriya Ispat Nigam Limited Roller Assembly for Apron Feeder Tender Vizag Andhra Pradesh 2026

Bid Publish Date

17-Aug-2026, 12:58 pm

Bid End Date

28-Aug-2026, 12:00 pm

Progress

Issue17-Aug-2026, 12:58 pm
AwardPending

Key Highlights

  • Organizational: Rashtriya Ispat Nigam Limited (RINL) Vizag Steel Plant
  • Product scope: Roller Assembly for Apron Feeder (Ore) and Apron Feeder (Coal)
  • Quantity flexibility: ±25% at contract placement and during currency
  • Delivery: No explicit deadline; deviations not accepted as per ATC

Tender Overview

Rashtriya Ispat Nigam Limited (RINL), operating the Vizag Steel Plant in Visakhapatnam, Andhra Pradesh, invites bids for ROLLER ASSEMBLY FOR APRON FEEDER (ORE) AND COAL. The procurement covers the supply and manufacture of two distinct feeder roller assemblies, with the Purchaser retaining the right to adjust quantity by up to 25% at contract placement and during currency. Bidders must follow the GCC and Detailed Terms available on the VSP site; inspection and acceptance will align with the bid offer. The project relies on a Technical Specification attached as Tec6/18. Communication channel: [email protected].

Technical Specifications & Requirements

  • Product/Service: ROLLER ASSEMBLY FOR APRON FEEDER (ORE) and ROLLER ASSEMBLY FOR APRON FEEDER (COAL)
  • Technical Reference: Manufactured and supplied strictly as per Tec6/18 Technical Specification attached to the bid
  • Quantity Consideration: No BOQ items listed; Purchaser reserves right to modify quantity up to ±25% at contract award and during contract currency
  • Quality/Conformance: Inspections/acceptance per the bidder’s offer and parameters finalized during technical clarifications; deviations in delivery period are not entertained
  • Contractual Framework: Governed by GCC for supply and Detailed Terms & Conditions; no scope changes accepted without formal amendment
  • Communication & Documentation: All tender communications should follow the provided email channel; adherence to authenticity declarations is required
  • Delivery & Installation: Not explicitly stated; subject to terms in the GCC and ATC attached to the tender

Terms, Conditions & Eligibility

  • Bid Terms: Offers binding with no deviations in delivery period; bidder must accept any approved quantity adjustments within ±25%
  • Contract Foreclosure: Purchaser may foreclose the contract with 30 days’ advance notice; no damages claimed by supplier
  • Authenticity Undertaking: Bidder must submit Annexure-1 authenticity certificate; sign each page of the submission
  • Non-Collusive Declaration: Submit Annexure-2 the Non-Collusive Tendering Certificate
  • Holdings & Access: Bids from bidders under certain material groups or Centrally Blocked lists will be rejected
  • GCC & ATC Compliance: Tender treated as fully accepted unless deviations are explicitly stated; no scope change requests
  • Contact & Clarifications: For bid-related inquiries use the specified Vizag Steel contact email; ensure technical specs are aligned with Tec6/18
  • Delivery/Inspection: Inspection and acceptance aligned to the offer and agreed parameters during technical evaluation

Key Specifications

  • Procurement: Roller Assembly for Apron Feeder (Ore) and Apron Feeder (Coal)

  • Technical baseline: Tec6/18 specification attached to bid

  • Quantity clause: 0 BOQ items; quantity may vary by ±25%

  • Quality/Inspection: In-line with offer and technical clarifications

  • Contract framework: GCC + Detailed Terms; no scope change without amendment

Terms & Conditions

  • Delivery period deviations not allowed; strict adherence required

  • Quantity may be increased/decreased by up to 25% at placement and during currency

  • Authenticity and non-collusion declarations are mandatory

  • GCC governs the procurement; bid acceptance implies compliance with all ATC

Important Clauses

Payment Terms

Not specified in available data; payment terms to be as per GCC and bid offer

Delivery Schedule

No explicit delivery deadline provided; deviations not acceptable per ATC

Penalties/Liquidated Damages

Not detailed; penalties to be as per GCC and contract terms

Bidder Eligibility

  • Experience in supplying roller assemblies for apron feeders or similar equipment

  • Demonstrated financial stability and turnover as per GCC

  • Compliance with Tec6/18 and applicable OEM authorizations

Authority & Contact

Office Name

Visakhapatnam Steel Plant

Grievance Contact

[email protected]

Tender Data

Bid Details

Quantity

64

Category

ROLLER ASSEMBLY FOR APRON FEEDER (ORE)

Bid Type

Two Packet Bid

Bid Validity

120 (Days)

Bid Type

Service

Evaluation

Item wise evaluation

Inspection Required

No

RA Qualification Rule

H1-Highest Priced Bid Elimination

Tech Clarification Time

2 Days

Preference & Exemptions

EMD Required

No

MII Purchase Preference

Yes

MII Preference Band

L1+20%

MSE Purchase Preference

Yes

MSE Preference Band

L1+15%

MSE Exemption/Relaxation

No

Startup Exemption/Relaxation

No

Bid Splitting Applied

No

Requirements

Arbitration Clause

No

Mediation Clause

No

Additional Tender Data

Commercial Details

Tender Category

Goods

Bid To RA

No

Bid To RA Enabled

Yes

Item Category

ROLLER ASSEMBLY FOR APRON FEEDER (ORE) , TOP SUPPORT ROLLER ASSEMBLY FOR APRON FEEDER (COAL)

Payment Timelines

Payments shall be made to the Seller within 21 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)

Delivery Details

Max Delivery Days

120

Delivery Locations

1

Delivery Cities

Visakhapatanam

Delivery Pincodes

530031

Delivery Locations

ConsigneeAddressCityStatePincodeQuantityDelivery DaysAdditional Requirement
Chikkala Madhu Sudana Rao530031,CENTRAL STORES BUILDING VISAKHAPATNAM STEEL PLANTVisakhapatanamAndhra Pradesh53003132120-

Authority Records

MINISTRY OF STEELRASHTRIYA ISPAT NIGAM LIMITED

BID & GeM Expert Consultancy

End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.

Bid Preparation GeM Registration Document Filing

Free consultation · 24h response

Documents 9

GeM-Bidding-9723186.pdf

Main Document

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

Other Documents

OTHER

GEM General Terms and Conditions Document

GEM_GENERAL_TERMS_AND_CONDITIONS

Categories 2

Required Documents

1

GST registration certificate

2

Permanent Account Number (PAN) card

3

Experience certificates for similar roller assemblies

4

Financial statements / turnover proof

5

EMD/Security deposit documentation (as applicable)

6

Technical bid documents confirming Tec6/18 compliance

7

OEM authorization / dealership certificates (if applicable)

8

Annexure-1 authenticity undertaking

9

Annexure-2 Non-Collusive Tendering Certificate

Frequently Asked Questions

Key insights about ANDHRA PRADESH tender market

How to bid for apron feeder roller assembly tender in Visakhapatnam?

Bidders must submit GST, PAN, experience certificates, financials, EMD, and technical documents, plus Annexure-1 authenticity and Annexure-2 non-collusive certificates. Ensure Tec6/18 compliance and GCC adherence. Use the Vizag Steel contact email for queries and attach OEM authorizations if applicable.

What documents are required for RINL apron feeder tender submission 2026?

Required documents include GST certificate, PAN, experience certificates for similar rollers, financial statements, EMD documentation, technical bid aligned with Tec6/18, and OEM authorizations when applicable; Annexures 1 and 2 must be signed and submitted with the bid.

What standards apply to the roller assemblies for apron feeders Vizag?

Bids must conform to the Tec6/18 specification in the tender and GCC; and any OEM certifications or authorizations required by the supplier must be attached; inspection will follow the supplier offer parameters finalized during technical clarification.

When can quantities be adjusted for the apron feeder roller contract?

The purchaser may increase or decrease the ordered quantity by up to 25% at the time of contract placement and during the currency of the contract; suppliers must accept adjusted quantities within contracted rates.

What is the contact method for bid clarifications on this tender?

All queries should be directed via email to [email protected]; ensure inquiry references Tec6/18 and GCC terms; responses may influence technical evaluation and acceptance criteria.

Are deviations in delivery periods allowed for this apron feeder tender?

No. The ATC specifies that offers with deviation in delivery period will not be considered; bidders must propose compliant delivery timelines aligned with the GCC and technical specification.

What happens if the contract is foreclosed by the buyer early?

The purchaser may foreclose the contract with 30 days advance notice; the supplier cannot claim damages for early termination; bid terms should plan for potential exit scenarios.