Bid Publish Date
26-Nov-2025, 10:39 am
Bid End Date
08-Dec-2025, 11:00 am
Location
Progress
RAQuantity
10
Category
Title1
Bid Type
Two Packet Bid
Indian Army invites bids for Title1, Title2, Title3, Title4, Title5, Title6, Title7, Title8, Title9, Title10 in SHIMLA, HIMACHAL PRADESH. Quantity: 10. Submission Deadline: 08-12-2025 11: 00: 00. Submit your proposal before the deadline.
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
Yes
Item Category
Title1 , Title2 , Title3 , Title4 , Title5 , Title6 , Title7 , Title8 , Title9 , Title10
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS
Title1
Disconnecting HT and LT supply taking down the defective transformer Indoor outdoor type from four pole two pole structure or lifting from the outdoor type foundation or taking out from sub station bldg using a crane of suitable capacity and slings ropes etc as required and shifting the same to civil workshop for repairs complete all as directed for transformer capacity 400 KVA
Title2
Shifting back the repaired transformer Indoor outdoor type from civil workshop to site reinstalling at original position and fixing properly on four pole two pole structure or outdoor type foundation or inside a sub station bldg using a crane of suitable capacity and slings ropes etc as required making HT LT side connections and testing for satisfactorily working complete all as directed for transformer of Capacity 400 KVA
Title3
Draining out transformer oil from the transformer and storing the same in suitable containers to be arranged by contractor without any extra cost opening the top cover and lifting up the core assembly carefully to check the condition of transformer windings and core retanking the same after repairing checking of leakage from transformer body and repairing welding works required for making transformer body leak proof refilling the transformer oil dully dehydrated and filtered dehydration and filteration to be paid separately and making all connections with HT LT side bushings refixing the top cover and testing the transformer with a suitable capacity insulation tester complete all as directed for transformer of Cap 400 KVA
Title4
M and L for rewinding of burnt out defective HT copper coils with new super enamelled heavy duty copper winding wires of size matching to the existing one including varnishing drying in a suitable oven and all insulating material such as cotton sleeves tapes etc and connections with bushing terminals complete all as specified and directed
Title5
All as per item No 4 above but LT copper coils complete all as specified and directed
Title6
M and L for painting the transformer tank from inside with two coats of zinc chromite after preparing the tank walls bottom top cover inner side by properly cleaning the surfaces oil free complete all as directed for transformer capacity 400 KVA
Title7
M and L for replacement of defective HT porcelain bushing of suitable size for transformer of cap 400 KVA including washers of good quality complete all as specified and directed
Title8
M and L for replacement of defective LT porcelain bushing of suitable size for transformer of cap 400 KVA including washers of good quality complete all as specified and directed
Title9
Dehydration and filteration of transformer oil for indoor outdoor type transformers of any capacity at site using transformer oil filteration plant to improve di electric strength not less than 45 KV at 2 Point 5 mm electrode gap complete all as directed Note Unit rate quoted shall be deemed to include the charges for hiring of oil filteration plant shifting to different locations at cantt area testing of samples of oil as per requirement and nothing extra will be paid on this account
Title10
S and F new transformer oil for replacement or topping up the level of oil having dielectric strength not less than 45 complete all as specified and directed
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Title1 | Disconnecting HT and LT supply taking down the defective transformer Indoor outdoor type from four pole two pole structure or lifting from the outdoor type foundation or taking out from sub station bldg using a crane of suitable capacity and slings ropes etc as required and shifting the same to civil workshop for repairs complete all as directed for transformer capacity 400 KVA | 1 | each job | gejutoghbso | 30 | |
| 2 | Title2 | Shifting back the repaired transformer Indoor outdoor type from civil workshop to site reinstalling at original position and fixing properly on four pole two pole structure or outdoor type foundation or inside a sub station bldg using a crane of suitable capacity and slings ropes etc as required making HT LT side connections and testing for satisfactorily working complete all as directed for transformer of Capacity 400 KVA | 1 | each job | gejutoghbso | 30 | |
| 3 | Title3 | Draining out transformer oil from the transformer and storing the same in suitable containers to be arranged by contractor without any extra cost opening the top cover and lifting up the core assembly carefully to check the condition of transformer windings and core retanking the same after repairing checking of leakage from transformer body and repairing welding works required for making transformer body leak proof refilling the transformer oil dully dehydrated and filtered dehydration and filteration to be paid separately and making all connections with HT LT side bushings refixing the top cover and testing the transformer with a suitable capacity insulation tester complete all as directed for transformer of Cap 400 KVA | 1 | each job | gejutoghbso | 30 | |
| 4 | Title4 | M and L for rewinding of burnt out defective HT copper coils with new super enamelled heavy duty copper winding wires of size matching to the existing one including varnishing drying in a suitable oven and all insulating material such as cotton sleeves tapes etc and connections with bushing terminals complete all as specified and directed | 1 | each job | gejutoghbso | 30 | |
| 5 | Title5 | All as per item No 4 above but LT copper coils complete all as specified and directed | 1 | each job | gejutoghbso | 30 | |
| 6 | Title6 | M and L for painting the transformer tank from inside with two coats of zinc chromite after preparing the tank walls bottom top cover inner side by properly cleaning the surfaces oil free complete all as directed for transformer capacity 400 KVA | 1 | each job | gejutoghbso | 30 | |
| 7 | Title7 | M and L for replacement of defective HT porcelain bushing of suitable size for transformer of cap 400 KVA including washers of good quality complete all as specified and directed | 1 | each job | gejutoghbso | 30 | |
| 8 | Title8 | M and L for replacement of defective LT porcelain bushing of suitable size for transformer of cap 400 KVA including washers of good quality complete all as specified and directed | 1 | each job | gejutoghbso | 30 | |
| 9 | Title9 | Dehydration and filteration of transformer oil for indoor outdoor type transformers of any capacity at site using transformer oil filteration plant to improve di electric strength not less than 45 KV at 2 Point 5 mm electrode gap complete all as directed Note Unit rate quoted shall be deemed to include the charges for hiring of oil filteration plant shifting to different locations at cantt area testing of samples of oil as per requirement and nothing extra will be paid on this account | 1 | each job | gejutoghbso | 30 | |
| 10 | Title10 | S and F new transformer oil for replacement or topping up the level of oil having dielectric strength not less than 45 complete all as specified and directed | 1 | each job | gejutoghbso | 30 |
Experience Criteria
Past Performance
Bidder Turnover
OEM Authorization Certificate
OEM Annual Turnover *In case any bidder is seeking exemption from Experience / Turnover Criteria
the supporting documents to prove his eligibility for exemption must be uploaded for evaluation by the buyer
Start
10-Dec-2025, 4:00 pm
End
11-Dec-2025, 4:00 pm
Duration: 24 hours
Reverse Auction Document
✅ RA concluded. Check financial results for final rankings.
| S.No | Seller | Item | Date | Status |
|---|---|---|---|---|
| 1 | MAA DURGA ENTERPRISES Under PMA | - | 29-11-2025 17:33:35 | |
| 2 | MEHTA TRADERS Under PMA | - | 28-11-2025 21:27:19 | |
| 3 | NETLINK SYSTEM SOLUTIONS Under PMA | - | 27-11-2025 21:27:30 |
These are the final prices after the reverse auction event. Prices may be lower than initial bids.
| Rank | Seller | Final Price | Item |
|---|---|---|---|
| L1 | NETLINK SYSTEM SOLUTIONS(MSE) Under PMA Winner | ₹2,42,200 | Item Categories : Title1,Title2,Title3,Title4,Title5,Title6,Title7,Title8,Title9,Title10 |
| L2 | MAA DURGA ENTERPRISES (MSE) Under PMA | ₹2,99,240 | Item Categories : Title1,Title2,Title3,Title4,Title5,Title6,Title7,Title8,Title9,Title10 |
| L3 | MEHTA TRADERS (MSE) Under PMA | ₹3,01,390 | Item Categories : Title1,Title2,Title3,Title4,Title5,Title6,Title7,Title8,Title9,Title10 |
🎉 L1 Winner
NETLINK SYSTEM SOLUTIONS(MSE) Under PMA
Final Price: ₹2,42,200
Sign up now to access all documents
Main Document
BOQ
BOQ
GEM_GENERAL_TERMS_AND_CONDITIONS