The estimated project cost is approximately ₹19,32,11,000. The financial proposal should include a detailed breakdown of costs for materials, labor, equipment, and overheads. Payment terms are linked to project milestones, with an initial mobilization advance, progress payments based on completed work, and final settlement after acceptance. Bidders must submit a financial bid in the prescribed format, ensuring transparency and competitiveness.
| Cost Component |
Estimated Cost (₹) |
| Civil Works |
8,00,00,000 |
| Pipes & Materials |
5,00,00,000 |
| Pumping Machinery |
3,00,00,000 |
| Operation & Maintenance |
1,00,00,000 |
| Contingencies |
1,32,11,000 |
Total Estimated Cost | ₹19,32,11,000 |
Payment Schedule:
- 10% on mobilization.
- 30% on completion of civil works.
- 30% on installation and testing.
- 20% on commissioning.
- 10% after 2 years of operation & maintenance completion.