Ductility Testing Machine with digital display,Centrifuge Extractor Capacity 1500g Electrically Ope
Directorate Of Technical Education
RUDRAPRAYAG, UTTARAKHAND
Bid Publish Date
30-Jan-2026, 8:24 pm
Bid End Date
14-Feb-2026, 9:00 pm
Value
₹39,99,993
Location
Progress
Quantity
21
Category
Complete Bowl Assembly, MOC- As per CSD
Bid Type
Single Packet Bid
Organization: Uttar Pradesh Rajya Vidyut Utpadan Nigam Limited (UPRVUNL), Lucknow. Procurement: Complete bowl assembly and associated components across multiple parts (MOC- CI, Cast Steel, Rubber, Bronze) including line shaft, suction/discharge bowls, impeller lock bush, and bearing housings, for installation at Sonbhadra, Uttar Pradesh. Estimated value: ₹3,999,993.00. Location: Sonbhadra, Uttar Pradesh 231205. The scope references nine items with material composition spanning steel, rubber, bronze, and CI castings, requiring compliance with internal standards and supplier capabilities for precision mechanical assemblies. A notable clause is the option to vary quantity by ±25% at contract rates, with delivery timing linked to the original delivery order and adjusted per policy. The tender emphasizes formal adherence to the option clause and delivery calculations. Unique aspects include a multi-material BOM and a broad range of mating components spanning bowls, shafts, and housings.
Complete bowl assembly with multiple MOC variants: CI, Cast Steel, Rubber, Bronze
Part numbers referenced in the tender: 43, 66, 68, 76, 7, 8, 81, 2, 10, 17
Nine-item BoQ with non-disclosed quantities require cross-verification with BOQ/ATC
Estimated value: ₹3,999,993.00
Option clause allows ±25% quantity variation at contract rates
Quantity variation up to 25% at contract rates
Delivery period starts after original delivery order; extended time as per formula
Consult ATC for exact item specifications and quantities
Delivery period commences from the last date of original delivery order; extended time calculation (Increased quantity ÷ Original quantity) × Original delivery period with minimum 30 days; possible extension up to original delivery period.
Purchaser may alter quantity by up to ±25% during contract and currency; rates fixed for contracted quantities.
Not specified in provided data; bidders should consult ATC for LD% and penalty terms.
Experience in supply of mechanical assemblies with multi-material components
Demonstrated capability to deliver complex bolt-on components within UP regions
Financial stability evidenced by annual turnover suitable to project scale
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Directorate Of Technical Education
RUDRAPRAYAG, UTTARAKHAND
Western Coalfields Limited
CHANDRAPUR, MAHARASHTRA
Indian Army
LEH, JAMMU & KASHMIR
Western Coalfields Limited
CHANDRAPUR, MAHARASHTRA
Indian Army
GANDHI NAGAR, GUJARAT
Tender Results
Loading results...
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) |
|---|---|---|---|---|---|---|
| 1 | Complete Bowl Assembly, MOC- As per CSD | Complete Bowl Assembly, MOC- As per CSD of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 1 | pieces | ee_sd_btps_obra | 120 |
| 2 | Thrust Bearing Housing with Mounting Cover and Bearing, MOC- CI, Cast Steel, Part No. 43, 66 and 68 | Thrust Bearing Housing with Mounting Cover & Bearing, MOC- CI + Cast Steel, Part No. 43 + 66 + 68 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 1 | pieces | ee_sd_btps_obra | 120 |
| 3 | Lower Coupling Half, MOC- Cast Steel, Part No. 76 | Lower Coupling Half, MOC- Cast Steel, Part No. 76 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 1 | pieces | ee_sd_btps_obra | 120 |
| 4 | Impeller Lock Bush with Nut, MOC- Steel, Part No. 7 and 8 | Impeller Lock Bush with Nut, MOC- Steel, Part No. 7 + 8 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 5 | pieces | ee_sd_btps_obra | 120 |
| 5 | Complete Column and Shaft Assy. | Complete Column and Shaft Assy. of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 1 | set | ee_sd_btps_obra | 120 |
| 6 | Line Shaft Bearing, MOC- Rubber, Part No. 81 | Line Shaft Bearing, MOC- Rubber, Part No. 81 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 4 | pieces | ee_sd_btps_obra | 120 |
| 7 | Suction Bowl Bearing, MOC- Rubber, Part No. 2 | Suction Bowl Bearing, MOC- Rubber, Part No. 2 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 2 | pieces | ee_sd_btps_obra | 120 |
| 8 | Inter Bowl Bearing, MOC- Rubber, Part No. 10 | Inter Bowl Bearing, MOC- Rubber, Part No. 10 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 4 | pieces | ee_sd_btps_obra | 120 |
| 9 | Discharge Bowl Lower Bearing, MOC- Bronze, Part No. 17 | Discharge Bowl Lower Bearing, MOC- Bronze, Part No. 17 of Flowmore make LP Ash Water Pump, Drg. No. 408-GLP-1M, Size-16 inch LC-Stage-4, Fig-6900 | 2 | pieces | ee_sd_btps_obra | 120 |
Discover companies most likely to bid on this tender
GST registration
PAN card
Experience certificates (similar multi-part mechanical assemblies)
Financial statements (current and past fiscal year)
Technical bid documents and compliance certificates
OEM authorizations (where applicable)
Key insights about UTTAR PRADESH tender market
Bidders should submit the technical and financial bids per ATC, provide GST, PAN, experience certificates, financial statements, and OEM authorizations. Ensure compliance with the option clause allowing ±25% quantity variation and confirm delivery schedules align with the original order plus extended periods.
Required documents include GST registration, PAN, experience certificates for similar multi-material assemblies, financial statements, EMD documentation if applicable, technical bid and compliance certificates, and OEM authorizations where required by the BoQ and ATC.
Delivery starts from the last date of the original delivery order; if quantities increase, extended time is calculated as (increased quantity ÷ original quantity) × original delivery period, with a minimum of 30 days; bidder must plan for potential extensions.
The data specifies multiple MOC materials (CI, Cast Steel, Rubber, Bronze) and part numbers; exact dimensional/specification standards are provided in the BoQ/ATC. Bidders must review those documents to confirm IS/ISO or vendor-specific requirements.
The estimated value is ₹3,999,993.00 for the complete bowl assembly and related components, covering nine items with multi-material parts; verify exact item quantities in BoQ/ATC for firm quoting.
Quantity may be increased or decreased by up to 25% at contract rates, with delivery adjustments as per the extended period formula; ensure capacity to scale production and supply schedules accordingly.
The ATC contains essential bidder guidance, technical clarifications, and potentially specific dimensional/compatibility requirements for the nine items; bidders must review ATC to ensure full compliance and accurate报价.
Exact BoQ quantities are disclosed in the official BoQ document and ATC; bidders should access these attachments to prepare precise unit-wise pricing and confirm material specifications before submission.
Western Coalfields Limited
📍 CHANDRAPUR, MAHARASHTRA
Mahanadi Coalfields Limited
📍 JHARSUGUDA, ODISHA
Nlc India Limited
📍 CUDDALORE, TAMIL NADU
South Eastern Coalfields Limited
📍 KORBA, CHHATTISGARH
South Eastern Coalfields Limited
📍 ANUPPUR, MADHYA PRADESH
Sign up now to access all documents
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS