Supplying and laying cable,Supplying pole,Errection of pole,end termination,indoor end termination,
Bharat Sanchar Nigam Limited Portal(bsnl)
PATNA, BIHAR
Progress
Quantity
248
Category
Supplying and laying
Bid Type
Two Packet Bid
Bharat Sanchar Nigam Limited Portal (BSNL) under the Department of Telecommunications invites bids for the supply and erection of PCC poles, RCC poles, associated components, earthing with GI materials, and related hardware in Patna, Bihar. Estimated project value is ₹581,413 with an EMD of ₹11,628. Scope includes procurement and on-site installation of multiple pole types and ancillary items such as GI strips, GI clamps, back clamps, SF MS angles/channels, suspension components, and ACSR arrangements. The contract allows a quantity adjustment of up to ±25%, with delivery timing linked to the last delivery order date and potential extended periods as described in the option clause. The tender emphasizes adherence to the purchaser’s delivery schedule and extension logic, ensuring bidders plan for flexibly scaled procurement.
Product/service names: PCC poles, RCC poles, GI hardware (GI pipe, GI strip, GI clamp, back clamp, MS angle, MS channel), conducting arrangement of ACSR
Quantities: total implied by BOQ (19 items); exact numbers not disclosed
Estimated value: ₹581,413
EMD: ₹11,628
Delivery: flexible as per option clause; minimum extension 30 days
Experience: telecom pole erection and associated hardware installation capability
Standards/certifications: IS/IEC not explicitly listed; bidders to reference ATC for required standards
Warranty/maintenance: not specified in data; refer to ATC document
Brand/OEM: not specified; ensure supply of standard telecom hardware
Delivery quantity may vary by ±25% with contracted rates
Delivery period begins after last original delivery order date
Minimum 30 days extension for added quantity; maximum under option clause
Submit GST, PAN, EMD, and experience certificates with bid
No explicit payment terms provided in data; bidders must refer to ATC for payment schedule and milestones
Delivery period linked to last date of original delivery order; extensions governed by option clause with minimum 30 days
Not specified in summary; ATC may define LD terms in uploaded documents
Experience in supplying and erecting telecom poles (PCC/RCC) and related GI hardware
Financial capability to handle an approx. ₹581k total project scope
Ability to comply with option clause delivering ±25% quantity adjustments
Tender Category
Goods
Bid To RA
No
Bid To RA Enabled
No
Item Category
Supplying and laying , Supplying PCC Pole , Errection RCC or PCC Pole , Errection of RCC or PCC Pole , Supplying and making , Supplying and errection , Providing and fixing , Supplying and fixing , Earthing with GI pipe , GI Strip , GI Strip in GI pipe , Suspension for holding , Dead end for holding , GI clamp for holding , Back clamp , Misc GI items , SF MS angle , SF MS channel , Arrangement of ACSR
Advisory Bank
PUNJAB NATIONAL BANK
ePBG Percentage
5%
ePBG Duration (Months)
12
Payment Timelines
Payments shall be made to the Seller within 45 days of issue of consignee receipt-cum-acceptance certificate (CRAC) and on-line submission of bills (This is in supersession of 10 days time as provided in clause 12 of GeM GTC)
Max Delivery Days
15
Delivery Locations
1
Delivery Cities
Patna
Delivery Pincodes
800001
| Consignee | Address | City | State | Pincode | Quantity | Delivery Days | Additional Requirement |
|---|---|---|---|---|---|---|---|
| Mukul Anthony | 800001,O/O of CE(E) ,3rd floor CTO Building Sanchar Parisar , Patna | Patna | Bihar | 800001 | 86 | 15 | - |
End-to-end support — bid preparation, GeM registration, document filing & compliance by industry experts.
Free consultation · 24h response
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS
Bharat Sanchar Nigam Limited Portal(bsnl)
PATNA, BIHAR
Bharat Sanchar Nigam Limited Portal(bsnl)
PATNA, BIHAR
N/a
KOLHAPUR, MAHARASHTRA
N/a
KOLHAPUR, MAHARASHTRA
TNEB Limited
VELLORE, TAMIL NADU
Tender Results
Loading results...
Supplying and laying
3 Core 120 Sqmm XLPE HT 11KV Aerial Bunched Cables
Supplying PCC Pole
PCC pole of weight not less than 300 Kg for a length more than 8 metre
Errection RCC or PCC Pole
Brick ballast and ramming the foundation excavation and refilling secured with holding clamps bolts nuts
Errection of RCC or PCC Pole
RCC or PCC pole of length above 8 mtrs and upto 11 mtrs
Supplying and making
Outdoor cable end termination with heat shrinkable jointing kit 120 sqmm
Supplying and errection
Lightning arrestor suitable for 3 wire 11 KV overhead lines with rated voltage 9 KV rms
Providing and fixing
11KV triple pole Post gang operated air break switch 400 A complete with fixing angles
Supplying and fixing
11 KV DO fuse complete with necessary pin insulator with GI Pin and hardwares 1 set of 3 nos
Earthing with GI pipe
GI earth pipe 4 point 5 metre long 40 mm dia including accessories and providing masonry enclosure
GI Strip
25 mm into 5 mm GI strip on surface or in recess for connections etc as required
GI Strip in GI pipe
25 mm into 5 mm GI strip in 40 mm dia GI pipe from earth electrode
Suspension for holding
Suspension for holding the ABC cable etc complete as reqd
Dead end for holding
Dead end for holding and locking the cable at turning and end points of cable route as reqd
GI clamp for holding
GI clamp for holding suspension and dead end on existing poles as reqd
Back clamp
Back clamp on existing poles for holding the cables etc as reqd
Misc GI items
GI items like different sizes of nut botls and washers etc as reqd
SF MS angle
100mm into 75mm into 6mm thick MS Channel
SF MS channel
75mm into 40mm into 6mm MS Channel
Arrangement of ACSR
Aluminum conductor steel reinforced cable with nominal aluminum cross sectional area of 99 sqmm
| Item # | Title | Description | Quantity | Unit | Consignee | Delivery (Days) | Price Trends |
|---|---|---|---|---|---|---|---|
| 1 | Supplying and laying | 3 Core 120 Sqmm XLPE HT 11KV Aerial Bunched Cables | 86 | mtrs | mukul_anthony22 | 15 | |
| 2 | Supplying PCC Pole | PCC pole of weight not less than 300 Kg for a length more than 8 metre | 3 | jobs | mukul_anthony22 | 15 | |
| 3 | Errection RCC or PCC Pole | Brick ballast and ramming the foundation excavation and refilling secured with holding clamps bolts nuts | 1 | job | mukul_anthony22 | 15 | |
| 4 | Errection of RCC or PCC Pole | RCC or PCC pole of length above 8 mtrs and upto 11 mtrs | 2 | jobs | mukul_anthony22 | 15 | |
| 5 | Supplying and making | Outdoor cable end termination with heat shrinkable jointing kit 120 sqmm | 4 | sets | mukul_anthony22 | 15 | |
| 6 | Supplying and errection | Lightning arrestor suitable for 3 wire 11 KV overhead lines with rated voltage 9 KV rms | 1 | set | mukul_anthony22 | 15 | |
| 7 | Providing and fixing | 11KV triple pole Post gang operated air break switch 400 A complete with fixing angles | 1 | set | mukul_anthony22 | 15 | |
| 8 | Supplying and fixing | 11 KV DO fuse complete with necessary pin insulator with GI Pin and hardwares 1 set of 3 nos | 1 | set | mukul_anthony22 | 15 | |
| 9 | Earthing with GI pipe | GI earth pipe 4 point 5 metre long 40 mm dia including accessories and providing masonry enclosure | 4 | sets | mukul_anthony22 | 15 | |
| 10 | GI Strip | 25 mm into 5 mm GI strip on surface or in recess for connections etc as required | 50 | mtrs | mukul_anthony22 | 15 | |
| 11 | GI Strip in GI pipe | 25 mm into 5 mm GI strip in 40 mm dia GI pipe from earth electrode | 30 | mtrs | mukul_anthony22 | 15 | |
| 12 | Suspension for holding | Suspension for holding the ABC cable etc complete as reqd | 4 | nos | mukul_anthony22 | 15 | |
| 13 | Dead end for holding | Dead end for holding and locking the cable at turning and end points of cable route as reqd | 4 | nos | mukul_anthony22 | 15 | |
| 14 | GI clamp for holding | GI clamp for holding suspension and dead end on existing poles as reqd | 8 | sets | mukul_anthony22 | 15 | |
| 15 | Back clamp | Back clamp on existing poles for holding the cables etc as reqd | 5 | nos | mukul_anthony22 | 15 | |
| 16 | Misc GI items | GI items like different sizes of nut botls and washers etc as reqd | 10 | kgs | mukul_anthony22 | 15 | |
| 17 | SF MS angle | 100mm into 75mm into 6mm thick MS Channel | 9 | mtrs | mukul_anthony22 | 15 | |
| 18 | SF MS channel | 75mm into 40mm into 6mm MS Channel | 9 | mtrs | mukul_anthony22 | 15 | |
| 19 | Arrangement of ACSR | Aluminum conductor steel reinforced cable with nominal aluminum cross sectional area of 99 sqmm | 16 | mtrs | mukul_anthony22 | 15 |
Discover companies most likely to bid on this tender
GST registration certificate
PAN card
Experience certificates for similar telecom pole installation projects
Financial statements or turnover details confirming fiscal capacity
EMD submission proof (online/DD as applicable) for ₹11,628
Technical bid documents including method statement for pole erection
OEM authorizations or supplier confirmations for PCC/RCC poles and GI hardware
Any ATC documents viewable by bidders
Key insights about BIHAR tender market
Bidders must submit GST, PAN, experience certificates, financial statements, and EMD of ₹11,628. The ATC describes quantity variation up to 25% and a delivery extension mechanism starting from the last original delivery order date. Ensure compliance with the IS/standards referenced and provide method statements for erection work.
Required documents include GST registration, PAN, experience certificates for telecom pole work, financial statements showing turnover, EMD proof, technical bid with erection method, OEM authorizations for PCC/RCC poles and GI hardware, and any ATC attachments indicating standards and delivery terms.
Delivery begins after the original delivery order date; quantity can change ±25% at contracted rates. If additional quantity is ordered, the extension is calculated as (additional/ original) × original period, with a minimum extension of 30 days.
ATC documents may specify required standards; ensure IS/IEC alignment where applicable and obtain OEM authorizations for PCC/RCC poles and GI components. Confirm any ISI or ISO requirements in the uploaded ATC attachments before submission.
Estimated value is ₹581,413 with an EMD of ₹11,628. Prepare EMD payment proof and ensure alignment with the option clause on quantity adjustments during the contract period.
Scope includes supply and erection of PCC and RCC poles, GI hardware (strips, clamps, back clamps), SF MS angles/channels, ACSR arrangements, and related components. The work requires on-site installation and coordination with civil works for telecom network deployment in Patna.
Exact bid submission deadlines are not stated in the provided data; bidders should review the ATC document uploaded by the buyer for submission timelines, eligibility, and required bid formats.
Eligibility includes demonstrated experience in telecom pole supply/erection, ability to handle material supply and on-site installation, financial capacity to deliver within the project value range, and compliance with required ATC terms and OEM authorizations for PCC/RCC poles and GI hardware.
Bharat Sanchar Nigam Limited Portal(bsnl)
📍 PATNA, BIHAR
Indian Air Force
📍 JAISALMER, RAJASTHAN
Uttar Pradesh Power Corporation Limited (uppcl)
📍 ETAH, UTTAR PRADESH
Indian Army
📍 PITHORAGARH, UTTARAKHAND
Indian Army
📍 JAMMU, JAMMU & KASHMIR
Sign up now to access all documents
Main Document
BOQ
BOQ
ATC
GEM_GENERAL_TERMS_AND_CONDITIONS