• Drilling of 125mm diameter bore wells up to 60 meters depth using MDR rigs at designated village locations.
• Installation of I.M.II Hand Pumps on drilled bore wells, ensuring compliance with UNICEF design and specifications.
• Construction of C.C. platforms for pump installation, including foundation work, reinforcement, and finishing.
• Construction of soak pits at each bore well site to facilitate proper drainage and sanitation.
• Site preparation, mobilization, and demobilization as per project plan.
• Ensuring quality control and safety standards throughout the project duration.
• Coordination with local authorities and adherence to environmental guidelines.
| Specification |
Details |
| Bore Diameter |
125mm |
| Depth |
60 meters |
| Pump Type |
I.M.II Hand Pump |
| Construction Material |
C.C. (as per UNICEF design) |
| Project Duration |
12 months |
• Sequential Process:
- Mobilization of equipment and materials.
- Site survey and bore well drilling.
- Pump installation and platform construction.
- Soak pit construction.
- Quality inspection and handover.
• All work must conform to government standards and technical specifications.