• **Erection of HT/LT lines and Transformer Centers (TC) at Sardar Subdivision and other locations within Anand District.
• Conduct survey, planning, and asset geo-tagging to ensure accurate mapping of all electrical assets.
• Installation and commissioning of electrical equipment, including Nut-Bolt and miscellaneous low-value materials.
• Perform testing and documentation of all installed assets to ensure compliance with standards.
• Maintenance work as required under schemes like RDSS.
• Material requirements: Nut-bolts, low-value miscellaneous items, and other electrical components.
| Item |
Specification |
Quantity |
| Nut-bolts |
Standard sizes |
As per site requirement |
| Electrical cables |
HV and LV cables |
As per project plan |
| Transformer Centers |
11kV/433V |
As specified |
• Project duration: 365 days from the date of award.
• Compliance: All work must adhere to technical standards and safety regulations.
• Geo-tagging: Complete geo-tagging of all assets for asset management and future maintenance.
• Documentation: Prepare detailed reports, drawings, and asset data for project closure.